AI summaryCambridgeshire and Peterborough Combined Authority's Transport Committee noted the 2025/26 outturn for its Transport division, including a £699,000 supported bus services underspend, and the four-year Transport division budget updated for approved carry-forwards.
Written from the decision and the officer reportPDF Pro
OutcomeNotedPosition for 2025/26 and next four years
Money£699,000Supported bus services underspend
What happens nextUnderspend to reserveTransferred to passenger transport operations reserve
Who it affectsTransport projects and passengersSeveral capital projects slip into 2026/27
What was decided
The Committee noted the 2025/26 outturn position for the Transport division, including Board approved carry-forwards. Report P1
The Committee noted the four-year Transport division budget updated for approved carry-forwards. Report P1
The Committee noted a £699,000 underspend on supported bus services, to be transferred to the passenger transport operations reserve.
Why
Income was higher than estimated because RTPI and bus services received additional contributions, with some income from section 106 receipts and an advance receipt for Peterborough Station Quarter. Report 3.2
Concessionary fares patronage remains below pre-COVID levels even with the pre-09:30 extension, producing an underspend.
The A10 capital spend was deferred while the Combined Authority waits for government feedback on the Major Road Network funding programme. Report 4.2
What happens next
Several capital projects will slip into 2026/27, including the A10 Upgrade, BP Roundabout, Active Travel, Civil Parking Enforcement, Soham Station, Road Safety Fund, and the remaining balance of March Junction Improvements. Report 4.2
Elements of the bus franchising programme will slip into 2026/27 to accommodate the independent review of bus franchising.
The Tiger Pass cost has been re-negotiated for 2026/27 on a fixed basis rather than demand driven.
The money
699 Underspend on supported bus services to be transferred to passenger transport operations reserve (text uses £699k)
37,487 Highways Maintenance and Pothole Fund income received (column is £k) Report 3.1
10,179 Bus Service Improvement Plan (BSIP+) income received (column is £k) Report 3.1
13,727 Transport Levy income received (column is £k) Report 3.1
14,397 Public Transport Bus Services revenue expenditure (column is £k) Report 3.3
8,527 Public Transport Concessionary Fares expenditure (column is £k) Report 3.3
42,120 Highways Maintenance and Pothole Fund capital expenditure (column is £k) Report 4.1
2,921 Peterborough Station Quarter LUF capital expenditure, covered by DfT grant (column is £k) Report 4.1
Options considered
Chosen: Note the 2025/26 outturn financial position and Board approved carry-forwards. Recommendation A in the report Report P1
Chosen: Note the Transport division budget for the next 4 years updated for approved carry-forwards. Recommendation B in the report Report P1
Implications
Financial: £699,000 supported bus services underspend will be transferred to the passenger transport operations reserve.
Financial: Fare Cap extension underspend will offset the overspend on the Tiger Pass budget, in line with the Board's previous decision to cease the fare cap.
Financial: Several capital schemes are being reprofiled into future years, including A10 Upgrade, A141, BP Roundabout, Active Travel, March Junction Improvements and Soham Station. Report 4.2
Legal: The Combined Authority is required to prepare a balanced budget in accordance with statutory requirements. Report 6.2
Other: Public Health, Environmental and Climate Change, and other significant implications are marked N/A. Report 6.3, 6.4, 6.5
Who and where
Bus passengers in Cambridgeshire and Peterborough
Active Travel programme users and delivery partners Report 4.2
Peterborough Station Quarter project (Combined Authority, Peterborough City Council, Department for Transport) Report 4.2
Fenland residents using the Civil Parking Enforcement scheme Report 4.2
Concessionary bus pass users, including Under-25s on the Reduced Fares scheme
Timeline
Period to 31 March 2026: Outturn position reported for 2025/26 revenue and capital budgets Report 1.1, 3.1, 4.1
May 2026: Market Towns Cycle Support lessons started being delivered by the newly appointed provider
Spring 2026: Mobilisation and construction of the Fletton Quays Footbridge expected Report 4.2
2026/27: Bus franchising work, BP Roundabout, A10 elements, Active Travel capital, Civil Parking Enforcement, Soham Station, Road Safety Fund and March Junction Improvements to be delivered Report 4.2
End of March 2029: Peterborough Station Quarter project still forecast to complete, within budget Report 4.2
Plain English for the jargon
BSIP+: Bus Service Improvement Plan (plus), a government funding stream for buses
BSOG: Bus Service Operators Grant
LEVI: Local Electric Vehicle Infrastructure
LTCP: Local Transport and Connectivity Plan
RTPI: Real Time Passenger Information
MRN: Major Road Network, the government funding programme
GFA: Grant Funding Agreement
LUF: Levelling Up Fund
S106: Section 106 planning obligation receipts
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15
Resolved
It was resolved to: A Note the outturn financial position of the Transport division for the financial year 25/26 and Board approved carry-forwards . B Note the Transport division budget for the next 4 years updated for approved carry-forwards .
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A To note the outturn financial position of the Transport division for the financial year 25/26 and Board approved carry-forwards. B To note the Transport division budget for the next 4 years updated for approved carry-forwards.
Strategic Objectives:
The proposals within this report fit under the following strategic objective(s):
☒ Growth ☒ Jobs ☐ Resilience
☐ Connectivity ☐ Homes ☒ Performance
1. Purpose
1.1To provide the outturn position for 2025/26 against the 2025/26 budgets. 1.2 The Combined Authority annually approves a budget for the forthcoming year as part of a 4-year Medium-Term financial plan.
Background
2.1At the last meeting, the Committee was provided with an analysis of the 2025/26 performance against budget to January 2026. This report provides an update covering up to March 2026. 2.2 Details of the Transport division budgets for the next 4 years are shown in appendix A. 3. Revenue Income and Expenditure
3.1A breakdown of the Transport income for the period to 31 March 2026 is set out in Table 1 below: 25/26 25/26 25/26 25/26 Table 1 Budget Actual Variance Slippage Transport Income FY FY FY £k £k £k £k Highways Maintenance and Pothole Fund -37,487 -37,487 0 - Local Transport Grant -4,633 -4,633 Bus Service Improvement Plan (BSIP+) -10,179 -10,179 0 - Public Transport - Bus Service Operators Grant -409 -409 0 - Active Travel -3,795 -3,795 0 - LEVI Pavement Channels -362 -362 0 - LEVI Capacity -202 -202 0 - Public Transport - Passenger Transport Contributions 0 -94 -94 Public Transport - Supported bus costs s106 0 -851 -851 Peterborough Station Quarter 0 -7,956 -7,956 Transport capacity grant -819 -819 0 - Transport Levy -13,727 -13,727 0 - Total Transport Income -71,613 -80,514 -8,901 0
3.2Income was slightly higher than estimated as RTPI and bus services received contributions to support these services. Some income is from section 106 receipts which will support services in future years. Income for Peterborough Station quarter is a receipt in advance to fund future works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting on 17 June 2026 were approved as an accurate record. The Action Log was noted by the Commi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.