Park and Ride Provision and Impact upon the Adoption of Wincheap Draft Development Brief

Decided Executive 1 paper

Executive decided this item on Thursday 5 June 2008. Below is the council's own wording, with the papers it was decided on.

Item23

Resolved

RESOLVED – That consultants WSP be appointed to undertake further Park and Ride site appraisal work and to carry out public consultation with the results of that work being reported to the Executive with recommendations for the location of Park and Ride provision. (Councillor Eden-Green, as Ward Member, spoke to this item.)
Word for word from the decision Canterbury published for this meeting. Source: democracy.canterbury.gov.uk

Follow this further

Built from Canterbury's papers

What the report saysPro

Report to Executive

Subject: Park and Ride Provision and Impact upon the Adoption of Wincheap Draft Development Brief.

Director: Director of Environment and Head of Regeneration and Economic Development.

Decision Issues: These matters are within the authority of the Executive

Decision type: Non-key

Classification: This report is open to the public

Ward(s): Wincheap, Harbledown and Chartham & Stone Street.

Summary: This reports discusses the option of undertaking further study and consultation work on Park and Ride provision. It outlines the impact of this on the adoption of the Wincheap Draft Development Brief.

To Resolve That further study work is completed to assess possible sites for the location of Park & Ride provision in the light of the decision of the Minister for Transport to agree in principle to the provision of A2 slip roads in Wincheap.

Next stage in process To appoint WSP consultants to undertake further Park and Ride site appraisal work, to carry out public consultation the results of that work and then report back to Committee with recommendations for the location of Park and Ride and the impact on the Wincheap Draft Development Brief.

SUPPORTING INFORMATION

Introduction

1. The Executive meeting of 17 April 2008, chose not to make a recommendation to Council on the Wincheap Draft Development Brief, pending further consultation on the paperwork related to the Officers’ conclusions that siting 1200 Park and Ride spaces within the boundaries of the Wincheap Regeneration zone, in lieu of a site at Faulkners Lane, should not be considered. Further to this debate, it is recommended that a second comprehensive site search for the possible siting of Park and Ride provision is undertaken and that the Wincheap Draft Development Brief is adopted following the completion of this study and subsequent consultation work.

2. An options appraisal study was carried out by consultants WSP in 2006/07 to investigate suitable sites for Canterbury’s 4th Park and Ride. This identified Faulkner’s Lane as the Council’s preferred location for the Fourth Park and Ride in Harbledown. WSP were appointed following a competitive tendering exercise. There is now a need to carry out a similar exercise for potential sites in the Wincheap/Thanington area, due to the decision made by the Minister of Transport to consider the principle of A2 slips roads in this area. This appraisal process will also involve comparing the advantages or disadvantages of the recommended sites from both exercises. It is recommended to use the same approach and the same consultant to complete this second phase to ensure continuity.

3. In view of the likelihood of this process leading to a planning and/or CPO inquiry it is essential that the study is robust and there is a need to ensure consistency with the methodology used by WSP and their environmental and planning specialists. As such this contract should be viewed as part of on-going investigation into Park & Ride options.

Detail

4. The possibility of the 4th Park and Ride site being located in the Wincheap Estate has only arisen because of the Minister’s decision in principle to allow new slip roads to be built at Wincheap and because of the possibility of being able to have the slip road construction funded by a combination of County Council and Developer contributions. By definition, however this also means that, potentially, there may be other sites near to the A2/A28 junction, which could provide a better location than Faulkner’s Lane at Harbledown.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Park and Ride Provision and Impact upon the Adoption of Wincheap Draft Development BriefReport 98 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Canterbury

Search all
  1. Park and Ride Provision and Impact upon the Adoption of Wincheap Draft Development BriefThis decision
  2. Wincheap Park & Ride: Options to increase capacity to 900 spaces to meet demand from the A28 and A2Agreed
  3. Application No. CA//18/02551/FUL - Wincheap Park & Ride, Ten Perch Road, Canterbury, CT1 2TQAgreed
  4. Wincheap Park and Ride ExpansionDeferred
  5. Evaluation of Wincheap / Thanington sites for Park and Ride provisionDecided

More from Canterbury Executive

All decisions
MeetingDecisionOutcome
6 May 2015 Call-in for the Executive Decision at Minute No. E227 - Petition to Full Council concerning household projections figures and the Draft Local PlanRESOLVED - That the Council does not withdraw the local plan and progresses with the forthcoming public examination. ... Approved Open
23 Apr 2015 Matters referred to the Executive by either the Overview or the Scrutiny and Audit Committees for considerationRESOLVED accordingly. Reason for the decision The current number of audit days is sufficient for the delivery of the ... Decided Open
23 Apr 2015 Key Performance Indicators - Targets for 2015/16RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reaso... Approved Open
23 Apr 2015 Litter Project ReviewRESOLVED - That approval be given to the continuation of the project as an extended pilot until 31 March, 2016 during... Approved Open
23 Apr 2015 Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies