Resolved
RESOLVED – (a) That the refurbishment programme for public conveniences as set out in the report as now submitted be approved. (b) That the disused Rheims Way toilet block be demolished and the ground reinstated.
Executive approved this item on Thursday 5 June 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – (a) That the refurbishment programme for public conveniences as set out in the report as now submitted be approved. (b) That the disused Rheims Way toilet block be demolished and the ground reinstated.
Subject: Public Conveniences Refurbishment
Director/Head of Service: Head of Environment and Street Scene
Decision Issues: These matters are within the authority of the Executive
Decision: Non-key
Wards: All
Summary: The Executive is asked to consider and comment on the proposed public conveniences refurbishment programme.
To Resolve: a) That the refurbishment programme for public conveniences is approved.
b) That the disused Rheims Way toilet block is demolished and the ground reinstated.
Classification: This report is open to the public
SUPPORTING INFORMATION
1. Introduction
The city council carried out a best value service review of the public conveniences in 2000. The report suggested that the city council should have fewer public toilets but maintained to a higher standard. It also recommended that a number of public conveniences should be closed and a programme of refurbishment of the remaining facilities was implemented.
On 11 March 2004 the Executive agreed the following refurbishment programme.
Programmed Facility Action taken date Worthgate Place, Canterbury
2004/2005 and Both completed with new builds.
Faversham Road, Whitstable Complete Refurbishment and new 2005/2006 Hampton Pier, Herne Bay disabled provision 2006/2007 West Beach, Whitstable Limited refurbishment carried out. A feasibility study carried out but not 2007/2008 suitable for redevelopment. Now Longport, Canterbury expected to be completed in 2008/9 with funds carried over. A sum of £75,000 was provided within the council's capital budgets that allowed the refurbishment of approximately one public toilet per annum. However, Worthgate public conveniences refurbished in 2007/08 came to a total of £113,000 plus fees because of the high specification demanded.
St Peter's Place toilets were identified as the next facilities to be refurbished. This is to coincide with the Tower House improvements. A new toilet is planned to replace the St Peter's Place facilities and the new building will be located in Tower Way (opposite Tower House).A sum of £175,000 has been provided for this work. Due to budgetary considerations the programme for refurbishments will take place every other year. A further £75,000 capital budget is provided for refurbishment in 2010/11.
The Street Scene Section is responsible for the maintenance and refurbishment of 34 public conveniences. However, engineers and architects suggest that refurbishment should take place every 10 years in order to maintain public conveniences to an acceptable standard and reflect a positive image for the council.
Best Lane will be replaced as part of the Beaney redevelopment so this should be excluded from any refurbishment programme.
Serco are responsible for the day-to-day maintenance of public conveniences. Some improvements have been carried out from maintenance budgets but there comes a point when total refurbishment is required or even a total rebuild.
Rheims Way toilets were closed primarily because of the antisocial behaviour that frequently took place there. It has a covenant on it which prevents it being used for any commercial activities and is therefore is unlikely to find a buyer.
As it regularly attracts graffiti officers suggest it is demolished and the adjoining fence at the boundary of the school extended in its place.
Future Programme
Because of limited funds it is necessary to prioritise the refurbishment of Public conveniences and therefore they have been allocated a score using the following criteria:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Refurbishment of Public ConveniencesReport | 101 KB | DownloadRead as text |
Follow Executive at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 May 2015 | Call-in for the Executive Decision at Minute No. E227 - Petition to Full Council concerning household projections figures and the Draft Local PlanRESOLVED - That the Council does not withdraw the local plan and progresses with the forthcoming public examination. ... | Approved | Open |
| 23 Apr 2015 | Matters referred to the Executive by either the Overview or the Scrutiny and Audit Committees for considerationRESOLVED accordingly. Reason for the decision The current number of audit days is sufficient for the delivery of the ... | Decided | Open |
| 23 Apr 2015 | Key Performance Indicators - Targets for 2015/16RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reaso... | Approved | Open |
| 23 Apr 2015 | Litter Project ReviewRESOLVED - That approval be given to the continuation of the project as an extended pilot until 31 March, 2016 during... | Approved | Open |
| 23 Apr 2015 | Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.