RESOLVED – (a) That the report be forwarded to Kent County Council. (b) That Kent County Council be requested to investigate radical options to improve traffic flow in Whitstable Town Centre, including a one way system. (c) That the City Council continues to seek opportunities to introduce a viable park and ride service for Whitstable. (d) That proposals should be prepared to amend the present parking regulations for implementation in the short term, these proposals to be presented to the Joint Transportation Board and the Executive prior to local public consultation. (Councillor Seath, as a Ward Member, spoke to this item prior to the consideration of the report).
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Subject: Whitstable Parking and Traffic Management
Head of Service: Head of Transportation and Engineering
Decision Issues: Parking matters are within the authority of the City Council’s Executive for deciding and funding. Traffic management and the signing of Traffic Regulation Orders are the responsibility of the Kent County Council.
Decision: Non-key
Classification: This report is open to the public
Wards: Gorrell, Harbour
Summary: This report is intended to review the implementation of the traffic management and parking scheme in Whitstable Town Centre. The scheme has been operational for 3 years and an investigation has been carried out to assess whether any changes could lead to improvements.
To Resolve: 1. That this report be forwarded to Kent County Council. 2. That Kent County Council be requested to investigate radical options to improve traffic flow in Whitstable Town Centre, including a one way system. 3. That the City Council continues to seek opportunities to introduce a viable park and ride service for Whitstable.
To Consider: 4. Whether, in the meantime, proposals should be prepared to amend the present parking regulations for implementation in the short term, these proposals to be presented to the Joint Transportation Board and the Executive prior to local public consultation (see paragraph 35 of this report).
Background 1. A Whitstable town centre traffic management scheme was developed and consulted upon in the early 1990s, but there failed to be an overall consensus for wholesale change. This resulted in some changes being implemented, including rear access roads and parking provision in Cromwell Road, a traffic calming scheme in Cromwell Road, junction improvement at Cromwell Road/Harbour Street, a link road between Waterloo Road and Cornwallis Circle and pedestrian crossing and environmental improvements in High Street, Sea Street and Harbour Street, but previous proposals for either some form of limited access in the High Street to improve the shopping environment or a one way system were dropped.
2. In 2000/01 a parking study was undertaken to assess the future parking needs of the town with a view to improving parking facilities for residents, shoppers and visitors to the town. An Access Study was also undertaken to examine ways in which improvements to access and the environment for all residents and visitors to the town could be improved.
3. Following the publication and public consultation of parking changes in Whitstable in the summer of 2001, Whitstable Area Member Panel (WAMP) asked for the implementation of any parking scheme to be considered alongside traffic management changes in the town centre.
4. In Spring 2002, a sub group of WAMP met with officers to consider the results of these studies, agreed the primary objectives, and set out a series of proposed actions. Later in 2002, a draft Traffic Management and Parking Scheme was approved by WAMP and the Joint Transportation Board for public consultation. A public exhibition was held at the Horsebridge followed by a public meeting to which members of the public were invited to view and comment on the draft proposals. The exhibition and public meeting were publicised by a leaflet drop (to 14,000 properties in the CT5 postcode area), posters on street through the town centre and press releases, which appeared in the local papers and on the local radio; both were very well attended by local people.
5. Following the consultation exercise, a number of changes were made and the scope of the scheme was significantly reduced. WAMP and the JTB agreed not to pursue the option of a one-way gyratory system. The final scheme was approved in 2003 and constructed in 2004/05 with funding from both the County and City Councils.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.