Canterbury City Council
Executive, Thursday 8 January 2009 at 6.30pm

The New Marlowe & Beaney Enabling Works

Approved Executive 1 paper

Executive approved this item on Thursday 8 January 2009. Below is the council's own wording, with the papers it was decided on.

Item231

Resolved

RESOLVED – That approval be given to the completion of enabling works on the Marlowe prior to the consideration and approval of the main contractor in March 2009. At this point, Councillor Cragg, left the meeting during the consideration of the enabling works for the Beaney development. Having considered the enabling works for the Beaney development as set out the report for the meeting, the Executive RECOMMENDED (to Full Council ) – That approval be given to the closure of the Beaney on 28 th February 2009 and to commence enabling works on the Beaney development prior to consideration and approval of the main contractor in May/June 2009.
Word for word from the decision Canterbury published for this meeting. Source: democracy.canterbury.gov.uk

Follow this further

Built from Canterbury's papers

What the report saysPro

Report to Executive

Subject: New Marlowe & Beaney enabling works

Director/Head of Service: Head of Culture and Communications

Decision Issues: These matters are within the authority of the Executive

Decision type: Non-key

Classification: This report is open to the public.

CCC Ward(s): Westgate

Summary: This report details enabling works required on the Marlowe and Beaney developments before the commencement of construction on site. To reduce the risk of delay to the construction timetables for both projects some enabling works require completion before Council considers tenders for the main contractors in March and May 2009. Executive approval for the completion of enabling works on the Marlowe, and recommendation to Council for approval of enabling works on the Beaney is therefore sought.

To Resolve: 1. Approval of completion of enabling works on the Marlowe prior to the consideration and approval of the main contractor in March 2009.

2. Recommendation to Council to approve the To Recommend: closure of the Beaney on 28th February 2009 and to commence enabling works on the Beaney development prior to consideration and approval of the main contractor in May/June 2009.

Next stage in process Council meeting on 15th January 2009.

SUPPORTING INFORMATION

1. Introduction

The New Marlowe

The New Marlowe Theatre is intended to be the first international centre for theatre in Kent. It is a transformational project that, together with the Heritage Lottery funded new Beaney Museum and Library, will revitalise the city’s old town, extend and reinforce the role of Canterbury as one of SEEDA’s key regional hubs and, with other major developments, build on East Kent’s ambition and growing reputation for cultural innovation and excellence. It is hoped that the New Marlowe will be a well-used facility with daytime activity offering local residents and visitors services that supplement the current traditional evening and matinee entertainment. The New Marlowe will be a presenting and producing theatre, creating new work and new productions. A new second performance space will create a facility dedicated to participation and learning in the performing arts involving children, university students, and graduates; facilities that the current theatre is unable to offer.

The redevelopment of the Marlowe will create:

• An enlarged main auditorium

• Increased seating capacity of up to 1,200

• Orchestra pit for up to 80 musicians

• Seating over three tiers, bringing the audience up to 10 metres closer to the stage

• Improved acoustics and sightlines

• Capacity to attract the largest performances such as Glyndebourne on Tour, National Theatre or major musicals such as [name removed]

• A new second performance space, with flexible capacity for up to 150

• Production house capacity

• Enhanced front-of-house facilities

• A central box office providing information and a ticketing service for the Theatre and other cultural organisations across Kent

• Function rooms for meetings, training and educational workshops and corporate hospitality areas.

The Beaney Project

The project to refurbish and extend the Beaney Institute is a partnership between Kent County Council and Canterbury City Council. The aim is to transform and revitalise the existing gallery, museum and library services; to enhance the user’s experience of the services; to make the Beaney a fully accessible and attractive community and visitor facility; and to create opportunities for closer, more integrated working between the KCC and CCC services operating in the building.

The building will be developed to make it fully accessible throughout. Its renovation and refurbishment will increase both its use and value to the community, while at the same time, (with the proposed New Marlowe), acting as part of the counter-balance to Whitefriars, promoting regeneration and economic growth.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The New Marlowe & Beaney Enabling WorksReport 115 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Canterbury

Search all
  1. The New Marlowe & Beaney Enabling WorksThis decision
  2. Poor Priest's Hospital and Marlowe Kit lease renewalAgreed
  3. New Marlowe TheatreApproved
  4. The New Marlowe and Beaney- Enabling worksApproved
  5. Urgent Item of Business - New Marlowe Theatre ProjectApproved

More from Canterbury Executive

All decisions
MeetingDecisionOutcome
6 May 2015 Call-in for the Executive Decision at Minute No. E227 - Petition to Full Council concerning household projections figures and the Draft Local PlanRESOLVED - That the Council does not withdraw the local plan and progresses with the forthcoming public examination. ... Approved Open
23 Apr 2015 Matters referred to the Executive by either the Overview or the Scrutiny and Audit Committees for considerationRESOLVED accordingly. Reason for the decision The current number of audit days is sufficient for the delivery of the ... Decided Open
23 Apr 2015 Key Performance Indicators - Targets for 2015/16RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reaso... Approved Open
23 Apr 2015 Litter Project ReviewRESOLVED - That approval be given to the continuation of the project as an extended pilot until 31 March, 2016 during... Approved Open
23 Apr 2015 Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies