Resolved
RESOLVED - That the report be noted
Executive noted this item on Thursday 4 March 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That the report be noted
Subject: Third quarter monitoring of Capital Programme – Financial Year 2009/10
Director/Head of Service: Director of Corporate Services/Head of Finance
Decision Issues: These matters are within the authority of the Executive
Decision type: Non-key
Classification: This report is open to the public
CCC Wards: All
Summary: This report advises Councillors on the position of the General Fund Capital Budget for 2009/10 and its financing, nine months through the financial year.
To Resolve That the report be noted
SUPPORTING INFORMATION
1. Introduction
This year's Capital Programme was approved at Full Council on 19 February 2009. The net cost of schemes for 2009/10, after external funding contributions, is £15,637k.
Executive on 9 July 2009 gave authority to carry forward the unspent capital budget provisions for certain projects of £4,373k for General Schemes, of which £2,233k had a direct impact on the council's capital financing requirement - £1,289k from major capital receipts and £944k from borrowing.
Since the original capital programme approval, Management Team have carried out a mini capital star-chamber meeting in July with appropriate Heads of Service. This has resulted in changes particularly in the phasing of estimated costs and income, and these are reflected in the capital schedule which formed part of the budget report presented to the Executive on 21 January 2010 (and Overview & Scrutiny on 27 January 2010).This report takes account of the revised position.
The position for the current year is now as follows:
TABLE 1 – GENERAL FUND SCHEMES (excluding Coast Protection & Flood Works) £ ‘ 000 NET ORIGINAL COST OF SCHEMES FOR 2009/10 15637 Plus approved carry forwards (net) 2233 Less Star chamber adjustments -4166 TOTAL REQUIRING FINANCING 13704
FINANCING General Fund Capital Receipts - Major receipts (5318k + 1289k c/f) 6607 Other General Fund Capital Receipts 150
TOTAL FINANCING PROJECTED (excluding borrowing) 6757
BALANCE = PRUDENTIAL BORROWING 6947
In addition the coast protection and flood works approved programme is now estimated to cost £0.54 million in the current year. Under the new funding arrangements all this expenditure should be funded by Defra grant.
2 Review of Schemes
Many of the schemes are currently expected to be on target against the budget. Where there is an anticipated variance against the budget brief details are given below. Gross budget means the total estimated spend on a scheme, whereas net budget is the estimated net cost to the council, after grants, contributions and receipts specific to a particular scheme are deducted.
Head of Culture and Communications
2.1Beaney Institute Development (AC6032): Budget £4606k gross, £700k net; Slippage £4000k gross & £450k net
The project is subject to joint funding and spending arrangements. The gross cost figure above includes a carry forward from last year of £631k gross and as previously reported, utilisation of these funds hinges on KCC to some extent.
The project is about 6 months behind the anticipated position for this point of the financial year. The main contractor is unlikely to be formally appointed until March after the contract negotiations have been completed, so works will not commence until the new financial year. There will be some further expenditure on enabling works.
The exact timing of the external funding is not clear, and it may be that although the gross expenditure will be far less than budget, the receipt of grant may not reduce by a similar proportion.
2.2Marlowe Theatre Development (AC3240): Budget £9547k gross, £8005k net; Slippage £5000k gross & £5000k net
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Exec 040310 3rd qtr 0910 capital budget app 1Appendix | 80 KB | Download |
PDF |
Third quarter monitoring of Capital Programme: Financial Year 2009/10Report | 143 KB | DownloadRead as text |
Follow Executive at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 May 2015 | Call-in for the Executive Decision at Minute No. E227 - Petition to Full Council concerning household projections figures and the Draft Local PlanRESOLVED - That the Council does not withdraw the local plan and progresses with the forthcoming public examination. ... | Approved | Open |
| 23 Apr 2015 | Matters referred to the Executive by either the Overview or the Scrutiny and Audit Committees for considerationRESOLVED accordingly. Reason for the decision The current number of audit days is sufficient for the delivery of the ... | Decided | Open |
| 23 Apr 2015 | Key Performance Indicators - Targets for 2015/16RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reaso... | Approved | Open |
| 23 Apr 2015 | Litter Project ReviewRESOLVED - That approval be given to the continuation of the project as an extended pilot until 31 March, 2016 during... | Approved | Open |
| 23 Apr 2015 | Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.