Resolved
RESOLVED - That the report be noted.
Executive noted this item on Thursday 3 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That the report be noted.
1. To approve the bringing forward of capital works within the HRA capital 4 year programme to the current financial year, to benefit from Contract efficiencies. The HRA balance will not reduce more than planned as there are delays on the rebuilds of Ellen Court and Franklyn House 2. To approve virements between different elements of the capital programme for 2010/11, as laid out in the body of the report.
Introduction
This year's Capital Programme was approved at Full Council on 18 Feb 2010. The total cost of schemes for 2010/11 was £9,291k.
£ ‘ 000 ORIGINAL COST OF SCHEMES FOR 2010/11 9,291 Less approved negative carry forwards (net) 400 TOTAL REQUIRING FINANCING 8,891
FINANCING Major Repairs Allowance 3,878 Revenue Contribution to Capital 2,452 Supported Capital Expenditure (SCE) 324 Prudential Borrowing 1,458 HCA Grant 779 TOTAL FINANCING PROJECTED 324 8,891
Approved Negative Carry Forwards: (-) £200k Re-roofing (-) £100k Kitchens (-) £100k Central Heating
1. There are some overspends forecast in the 2010/11 capital programme, which are due to Asset Management reasons of wishing to benefit from efficiencies of doing more work ahead of time in the larger contracts within the four year programme to 2013/14. These will not lead to an overspend of the overall budget, as there are significant delays in the major capital rebuilds at Ellen Court and Franklyn House. The capital budget for 2011/12 on the overspent schemes will be reduced by the amount they are overspent in 2010/11.
2. The budget for Warwick Road/St Andrews has not been included in any of the above calculations, as there is a good deal of uncertainty over the progress of the Warwick Road scheme. It is further not clear whether the HRA funding for this scheme should be set aside for other similar projects if this scheme does not happen. The St. Andrews Scheme is now set to start on-site before the end of the 2010-11 financial year. Overspend £’000
Fire Prevention 60k Re-Roofing 670k Window Replacements 136k Central Heating 220k Bathroom / Plumbing 150k Major works on voids 25k Decent Homes Standard Works 152k IT improvements 13k
Total overspend 1,426k
Major Underspend on renovations at Ellen Court 222k Franklyn House 818k
Total 1,040k
Other underspent schemes (see review of Schemes) 391k
Total Underspend £1,431k
Net Underspend 5k
Further Background
Previously, the larger capital works contracts were let on an annual basis, meaning that a contractor was only employed for a single year. A major disadvantage of this was that the contractor would go through a learning process at the start of the contract and would be working at their most efficient just as the contract was coming to an end. The works would then be re-tendered with the risk of a different contractor going through the same process. This would also mean that there were breaks in the anticipated spend whilst a new contractor was being selected.
Changes in procurement led to a longer tendering process which is both time consuming and complex.
This led to an innovation of the extendable contracts in that each one is let on a yearly basis based on performance up to a maximum of 3 years, based on the 3 year budget. Each contractor would be contracted for the first year and, based on performance, the contract would be extended for the second and third years. This gave the council assurance that a well performing contractor would continue to work with us, but also had the safeguard that a poor performing contractor would only be employed for the minimum length of time.
A further development of this way of working is that a contractor can accelerate the works planned for year 1 to include years 2 and 3. The advantage of this being that the council would complete a longer programme in a shorter time and at costs and rates that would not be subject to increases over time.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
3 March 2011 Capital Monitoring Report 3rd quarter Appx 1 for Exec BriefingReport | 82 KB | DownloadRead as text |
PDF |
Third Quarter monitoring of Capital Programme: Financial Year 2010/11Report | 130 KB | Download |
Follow Executive at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 May 2015 | Call-in for the Executive Decision at Minute No. E227 - Petition to Full Council concerning household projections figures and the Draft Local PlanRESOLVED - That the Council does not withdraw the local plan and progresses with the forthcoming public examination. ... | Approved | Open |
| 23 Apr 2015 | Matters referred to the Executive by either the Overview or the Scrutiny and Audit Committees for considerationRESOLVED accordingly. Reason for the decision The current number of audit days is sufficient for the delivery of the ... | Decided | Open |
| 23 Apr 2015 | Key Performance Indicators - Targets for 2015/16RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reaso... | Approved | Open |
| 23 Apr 2015 | Litter Project ReviewRESOLVED - That approval be given to the continuation of the project as an extended pilot until 31 March, 2016 during... | Approved | Open |
| 23 Apr 2015 | Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.