RESOLVED - 1a That the proposed Heads of Terms included at appendix 2 of the report be approved as the basis of a long leasehold sale of the Depot / Old Coach Park site to, and acquisition of the freehold interest in the current Sainsbury’s site from, The Harvest Partnership (a joint venture between Land Securities Limited and Sainsbury’s Supermarkets Ltd). 1b That authority be given to the Chief Executive to finalise Heads of Terms taking advice from G.L. Hearn into account. 1c Subsequent to 1b approval, in principle, be given to the offer from the Harvest Partnership including the transfer of ... view the full minutes text for item 163.
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Appendix 1 – site map Appendix 4 Area of Village Green application Appendix 8 Sub-report outlining Kingsmead Leisure Centre Refurbishment options
Subject: Kingsmead Leisure Centre – High Level Options Report
Head of Service: Janice McGuinness, Head of Culture & Enterprise
Decision Issues: These matters are within the authority of the Executive
Decision type: Key
Classification: Open
CCC Ward(s): All, Northgate
Summary: A decision is required on the future of Kingsmead Leisure Centre. Primarily due to its age, the quality of the facility is deteriorating resulting in an increasingly poor customer experience. Feasibility studies have considered a range of high-level options, which are set out in this report. Members are asked to agree to the principle of refurbishment of the existing Kingsmead Leisure Centre. There is an allocation of £5.5m in the council’s capital programme for this. Work will then commence with Active Life and other key stakeholders to determine the final facility mix, which along with the capital and revenue implications will be brought back to Members for consideration in April 2014
To Recommend to the To approve the principle of making improvements Executive to Kingsmead Leisure Centre (subject to a cap in budget to £5.5m) and for officers to take necessary action to move forward as indicated within the report. Next stages in process The Executive will consider this matter on 23 January. Should the principle of refurbishment be agreed, Officers will engage with stakeholders to inform a final facility mix and programme for the centre. Detailed financial analysis of the capital and revenue implications to the council and Active Life will be undertaken to inform Executive and council decisions planned for April 2014
SUPPORTING INFORMATION
1. Introduction The Scrutiny Review into Indoor leisure provision undertaken in 2011 recommended that the council consider future options for Kingsmead Leisure Centre. The swimming pool is nearly 50 years old and although the overall building is structurally sound, the quality of the facility is deteriorating resulting in an increasingly poor customer experience.
This report considers future options for Kingsmead Leisure Centre and seeks an in principle decision to undertake further work on an option to refurbish.
2. Future Options
Two studies have been carried out to consider future options for Kingsmead Leisure Centre. In 2011, a high-level feasibility study was carried out by consultants Sport, Leisure, Culture (SLC) and Castons. The report identified a suitable mix of new facilities to be incorporated into the centre to greatly improve financial performance and long-term sustainability.
It recommended that consideration be given to introducing soft-play into the existing sports hall (sports halls being in over-supply in the area), a health spa, additional studio space for exercise classes and conversion to a 25m x 6 lane pool with movable floor. Other options, such as pool closure, creation of an ice rink, ten-pin bowling were discounted due to cost, sustainability, competition, existing demand or technical and design issues.
The report also recommended that the council explore the option for replacing Kingsmead completely with a new purpose built facility which could deliver even better financial returns and service continuity.
A further, more detailed study, was commissioned from SLC and Castons in 2012. This study considered capital costs and revenue projections for the retention as is, refurbishment and new build of the centre either on its existing site or elsewhere.
Specific tasks were:
To finalise suggested facility mix for each option, including outline design work and costings; Provide an analysis of risk to the council of each option; Preparation and drafting of business plans for each option; Identification of next steps and potential timeline for the delivery of each option.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.