Extension to current commissioned voluntary sector support services

Decided Executive 1 paper

Executive decided this item on Thursday 23 January 2014. Below is the council's own wording, with the papers it was decided on.

Item164

Resolved

RESOLVED – That the commissioning of infrastructure support be extended for one further year (2014-15) Reason for the decision It allows continued provision whilst a review of need of these services is being carried out.
Word for word from the decision Canterbury published for this meeting. Source: democracy.canterbury.gov.uk

Follow this further

Built from Canterbury's papers

What the report saysPro

Report to Executive

Subject: Extension to current commissioned voluntary sector support services

Director/Head of Service: Head of Community Development & Outdoor Leisure

Decision Issues: These matters are within the authority of the Executive

Decision type: Non-key

Classification: This report is open to the public.

CCC Ward(s): ALL

Summary: The council commissioned infrastructure support services from the 1 April 2012 to the 31 March 2014. There is still a need for these services and we would like to extend funding for 1 further year from 1 April 2014 to the 31 March 2015 at the amount outlined in this report

Resolve: Whether to : Option 1. Extend the commissioning of infrastructure support for one further year (2014- 15) Option 2. Not to extend the commissioning of infrastructure support for one further year (2014- 15)

Next stage in process If agreed, outcomes and targets will be renegotiated and a new agreement would be in place by the 1 April 2014. Funding including in Budget for 2014-15 to be agreed by Full Council in February 2014.

SUPPORTING INFORMATION

1. Introduction

By infrastructure support we mean the provision of advice support and capacity building to voluntary and community groups to enable them to work more effectively. Making front line voluntary organisations fit for purpose and fit for the future.

It was agreed in the Single Grants Gateway Policy 2012-13 that funding for infrastructure services was removed from the normal grants process, and that the council would in future commission such services.

The council awarded the contracts to Canterbury & Herne Bay Volunteer Centre, Whitstable Volunteer Centre and East Kent Voluntary Action Support.

The table below provides further details on these two year contracts: Organisation 2012-13 2013-14 £ £ Canterbury & Herne Bay Volunteer Centre 15,000 14,000 Whitstable Volunteer Centre 7,500 7,000 East Kent Voluntary Action Support 14,000 14,000

The outcomes and outputs achieved by these organisations have been satisfactory and based on this performance we would re-engage them all.

2. Detail

The proposal is to extend the current commissioned services to deliver for a further one year period (1 April 2014-31 March 2015). There is no clause within the funding agreements to allow for an extension. Hence we are requesting the Executive to consider permitting this extension with existing providers without formally going out to tender for the one year period.

The table below provides details on the proposed value of the one year extension which remains the same as in the previous year and allows for continued levels of support:

Organisation 2014-15 £ Canterbury & Herne Bay Volunteer Centre 14,000 Whitstable Volunteer Centre 7,000 East Kent Voluntary Action Support 14,000

The justification for extending the commissioning of existing providers for one additional year is as follows:

• Under ‘Canterbury – 2015 and beyond’ the council’s ambitions place a greater emphasis on commissioning, this provides an opportunity to review both external and internal provision of infrastructure support

• A policy review of the Single Grants Gateway needs to be carried out, this may identify issues/needs that are pertinent to future commissioning of these services

• The terms of the proposed contracts have not been substantially altered from the terms originally agreed. There are good technical and economic reasons for commissioning the existing providers in this way and not to do so would cause major inconvenience to the authority in delivery of services.

In this particular case all three organisations deliver specialist support for a niche market, they all have extensive knowledge of the subject area, the specific skills to deliver the services and a wealth of local networks and relationships. These qualities would not be easy for other organisations to develop in the one year available.

3. Relevant Council Policy/Strategies/Budgetary Documents Single Grants Gateway policy 2012-16 Procurement Strategy

4. Consultation planned or undertaken

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Extension to current commissioned voluntary sector support servicesReport 83 KB DownloadRead as text

More from Canterbury Executive

All decisions
MeetingDecisionOutcome
6 May 2015 Call-in for the Executive Decision at Minute No. E227 - Petition to Full Council concerning household projections figures and the Draft Local PlanRESOLVED - That the Council does not withdraw the local plan and progresses with the forthcoming public examination. ... Approved Open
23 Apr 2015 Matters referred to the Executive by either the Overview or the Scrutiny and Audit Committees for considerationRESOLVED accordingly. Reason for the decision The current number of audit days is sufficient for the delivery of the ... Decided Open
23 Apr 2015 Key Performance Indicators - Targets for 2015/16RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reaso... Approved Open
23 Apr 2015 Litter Project ReviewRESOLVED - That approval be given to the continuation of the project as an extended pilot until 31 March, 2016 during... Approved Open
23 Apr 2015 Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies