09/1292W-Proposed Four Classroom Extension and Ancillary Accommodation following Demolition of Existing Building, Gorsey Bank County Primary School, Altrincham Road, Styal, Wilmslow for Mr Peter Davies, Cheshire East Council
ApprovedPlanning1 paper
Northern Planning Committee approved this item on Wednesday 1 July 2009. Below is the council's own wording, with the papers it was decided on.
RESOLVED That the application be delegated to the Head of Planning and Policy to approve the application subject to no adverse comments raising any new matters of objection being receievd within the consultation period and subject to the following conditions:- A03FP - Commencement of development (3 years) A01AP - Development in accord with approved plans A06EX - Materials as application A22GR - Protection from noise during construction (hours of construction) A23GR - Pile Driving
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
Application No: 09/1292W Location: GORSEY BANK COUNTY PRIMARY SCHOOL, ALTRINCHAM ROAD, STYAL, WILMSLOW, CHESHIRE, SK9 5NQ Proposal: PROPOSED FOUR CLASSROOM EXTENSION AND ANCILLARY ACCOMODATION FOLLOWING DEMOLITION OF EXISTING BUILDING.
For MR PETER DAVIES, CHESHIRE EAST COUNCIL
Registered 01-Jun-2009 Policy Item No Grid Reference 383602.85 381291.61
Date Report Prepared: 19th June 2009
SUMMARY RECOMMENDATION Authority REASONbe FORdelegated REPORT to the Head of Planning and Policy to consider any representations and consultation responses as part of the consultation period
MAIN ISSUES OF SITE AND CONTEXT DESCRIPTION Impact of the development on: Character and appearance of the locality Residential amenity
1. REASON FOR REFERRAL
The application has been referred to the Northern Planning Committee by the Head of Planning and Policy.
2. DETAILS OF PROPOSAL
Cheshire East Council has applied for planning permission to provide a replacement extension at Gorsey Bank Primary School following the demolition of the existing building which is considered to be unsafe.
3. RELEVANT HISTORY
5/08/2055p (Delegated approval with conditions) Erection of two temporary 2-classroom mobile units together with ancillary works for a period of 12 months
5/07/1411p (Withdrawn) Erection of 2m high clack powder-coated steel vertical bar boundary fencing with 2m wide single access gate to match 5/05/1980p (Delegated approval with conditions) Proposed replacement 4 classroom block extension, removal of one twin and two single temporary classrooms and proposed hall extension
5/04/3001 (Delegated approval with conditions) Proposed replacement 4 classroom block extension, removal of one twin and two single temporary classrooms and proposed hall extension
4. POLICIES
Regional Spatial Strategy (NW)
Policy DP7 ‘Promote Environmental Quality’
Macclesfield Borough Local Plan Policy
BE1 Design Guidance H13 Protecting Residential Amenity DC1 Design – New Build DC2 Extensions and Alterations DC3 Amenity RT1 Open Space
Other Material Considerations
PPS1 Delivering Sustainable Development
5. CONSIDERATIONS (External to Planning)
Environmental Health:
No objection.
Design Officer:
No issues raised in relation to Design.
Ecology:
It is not anticipated that there would be any significant ecological impacts associated with the proposed development.
Landscape:
No objection.
Trees: Views awaited at the time of writing this report.
6. VIEWS OF THE PARISH / TOWN COUNCIL
Views awaited at the time of writing this report.
7. OTHER REPRESENTATIONS
No representations have been received at the time of producing this report.
8. APPLICANT'S SUPPORTING INFORMATION
Design & Access Statement
- School was originally constructed in the 1960s and has been subject to various alterations and extensions during the interim years. - Design – applicant sought high quality and inclusive design in terms of both impact and function in line with the approach set out in PPS1. - Layout – Plan and location of the building is based upon the existing building footprint in order to reduce environmental impact. - Infill area adjacent to existing two storey block to create group rooms and storage - A separate entrance included in proposal to provide greater flexibility of use. - Scale & Appearance – proposal sympathetic in scale to existing building, which apart from a two storey block, is mainly single storey. - Materials to complement existing school building
9. OFFICER APPRAISAL
Principle of Development
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
09/1292W-Proposed Four Classroom Extension and Ancillary Accommodation following Demolition of Existing Building, Gorsey Bank County Primary School, Altrincham Road, Styal, Wilmslow for Mr Peter Davies, Cheshire East CouncilMinutes
3409/1292W-Proposed Four Classroom Extension and Ancillary Accommodation following Demolition of Existing Building, Gorsey Bank County Primary School, Altrincham Road, Styal, Wilmslow for Mr Peter Davies, Cheshire East CouncilThis decision
09/1292W-Proposed Four Classroom Extension and Ancillary Accommodation following Demolition of Existing Building, Gorsey Bank County Primary School, Altrincham Road, Styal, Wilmslow for Mr Peter Davies, Cheshire East CouncilThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.