Strategic Planning Board, Wednesday 24 March 2010 at 2.00pm

Manchester Airport Section 106 Agreement Annual Report

Noted Planning 1 paper

Strategic Planning Board noted this item on Wednesday 24 March 2010. Below is the council's own wording, with the papers it was decided on.

Item193

Resolved

RESOLVED 1. That the report be noted. 2. That future reports be referred to the Portfolio Holder for Prosperity for his consideration.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Strategic Planning Board

Recommendation

2.1Receive comments on the fifteenth annual monitoring report on the Section 106 Agreement

2.2approve that Manchester Airport be informed that the Council:

• accepts the findings set out in the monitoring report and the measures taken by the Airport to implement the Agreement; • continues to support the good working relationship with the Airport Company and hopes that this will continue in the implementation of the Agreement and in the discussions around other issues affecting the Airport and Cheshire East; • wishes to maintain the scope of the Agreement beyond 2011 as part of our on-going discussions towards establishing a new legal framework between the Council and the Airport.

Reasons for recommendations

3.1To fulfil the requirements of the Section 106 Agreement. 3.2 To confirm the commitment of Cheshire East to the Agreement and its wish to maintain its scope beyond 2011.

Wards affected

4.1All

5.0Local Ward Members

5.1N/A

6.0Policy Implications including - Climate change - Health

6.1The aim of the Agreement is to ensure that aspects of the environmental quality in the airport vicinity do not deteriorate as a result of its flight movements. This is in line with Cheshire East Council’s policies on sustainable development.

7.0Financial Implications for Transition Costs (Authorised by the Borough Treasurer)

7.1N/A

8.0Financial Implications 2009/10 and beyond (Authorised by the Borough Treasurer)

8.1N/A

9.0Legal Implications (Authorised by the Borough Solicitor)

9.1The monitoring report is required under the terms of the Section 106 Agreement.

Risk management

10.1Failure to acknowledge this report would mean that the requirements of the Section 106 Agreement have not been fulfilled.

11 Background and Options

11.1This annual report is the fifteenth related to the monitoring of the Section 106 Agreement originally between the former Cheshire County Council and Manchester Airport as part of the planning permission granted for the construction of the second runway. Since local government reorganisation in 2009 Cheshire East Council has become the responsible local authority.

11.2The Agreement, which dates from 1994, constitutes an agreed environmental mitigation package associated with the development of the second runway. This Agreement runs out in 2011 but contains a provision whereby the parties to the Agreement are required to undertake negotiations with a view to agreement upon alteration of the obligations so that the existing Agreement is as far as possible maintained in scope. Discussions towards this end have commenced, the progress and outcome of which will be reported to Members.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Manchester Airport Section 106 Agreement Annual ReportMinutes 69 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. Manchester Airport Section 106 Agreement Annual ReportThis decision
  2. Key Decision CE12/13-6 SEMMMS- A6 to Manchester Airport Relief RoadNoted
  3. Key Dec 12/13-6 SEMMMS A6 to Manchester Airport Relief RoadDeferred

More from Cheshire East Strategic Planning Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingThat the minutes of the meeting held on 22 July 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Sep 2026 25/1573/FUL - Full planning application for a residential development including associated access, infrastructure and landscaping. Land off Cumber Lane, WilmslowThat application 25/1573/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 3-year ti... Approved Open
16 Sep 2026 25/2071/FUL - Full planning application for a residential development and the provision of associated access and infrastructure works including roads, drainage infrastructure, car parking, public open space and landscaping. Land at Dean Row Road, WilmslowThat application 25/2071/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 2-year ti... Approved Open
16 Sep 2026 National Scheme of DelegationThat the Strategic Planning Board Noted the changes introduced by the for Planning Functions that will be implemented... Noted Open
22 Jul 2026 Minutes of the Previous MeetingThat the minutes of the meetings held on 27 May 2026 and 9 June 2026 be approved as correct records. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies