RESOLVED That the overall outturn position relating to current shared service arrangements be noted.
Shared Services Joint Committee noted this item on Friday 27 January 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the overall outturn position relating to current shared service arrangements be noted.
2.1That Members note the overall outturn position relating to current shared service arrangements.
3.1The position statement aims to ensure that the Joint Committee are up to speed on recent developments concerning shared service arrangements.
4.1This report relates to shared services that operate across both Cheshire East and Cheshire West and Chester so all wards are affected in both Councils.
5.0Local Ward Members
5.1Not applicable.
6.0Policy Implications including - Climate change - Health
6.1None.
7.0Financial Implications for Transition Costs
7.1None 8.0 Financial Implications (Summary Outturn Forecast 2011-12)
8.1As part of producing and reporting on the 2011-12 third review of the financial position, each Shared Service has been reviewed and a summary of actual costs to date and forecast outturn positions for each service agreed. This outturn forecast is then split according to the respective cost sharing arrangement for each service. This has then been compared to the 2011-12 budgets for each Authority to produce a budgetary variance and forecast outturn position.
Full details of the outturn projection for individual shared services are shown at Appendix 1. The table below provides details of the Shared Services collective position as at the final outturn position.
2011-12 Projected Budget Variance Variance Outturn £000 -under/over -under/over (@ TQR) (@TQR) (@MYR) £000 £000 £000 Total Cost 16,090 13,458 2,632 2,688 East Cost Share 7,799 6,208 1,591 1,619 West Cost Share 8,291 7,250 1,041 1,069
8.2Summary of Key Issues
8.2.1 Those Shared Services with significant forecast budgetary variances (i.e. those with total budget variances in excess of £100K) are summarised in the table below and explained further in the following section. In addition significant changes in budgetary variance from MYR to TQR are also analysed.
2011-12 Cheshire East Cheshire West Shared Total Projected Budget Variance Projected Budget Variance Service Variance Outturn -under / outturn -under / -under / over over over £000 £000 £000 £000 £000 £000 £000 ICT 2,438 4,870 3,592 1,278 5,370 4,210 1,160 HR & Finance 164 1,516 1,273 243 1,516 1,595 -79
8.2.2 HR & Finance
Cheshire East
Since the Mid-year review the forecast overspend has reduced from £273K to £243K, due to careful management of staff vacancies, agency staff, sickness cover and consultancy. Work is on-going to reduce the residual overspend via the Business Management Review with the aim of improving a range of HR, Income to Cash and procurement processes to deliver a very high level of compliance and to reduce costs.
Cheshire West and Chester
There has been careful management of staff vacancies, agency staff, sickness cover and consultancy. The service was pump primed at the start of the financial year due to the Oracle upgrade. Expectation over required support continues to be managed downwards during the financial year in anticipation of planned savings for 2012-13.
8.2.3 ICT
The overspend being reported by the ICT Shared Service is little changed from the reported mid-year position and in summary can be explained through 4 main contributing elements. These are:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Shared_Services_TQR-v2Appendix 1 | 53 KB | Download |
PDF |
Financial Review 2011-2012Minutes | 112 KB | DownloadRead as text |
Follow Shared Services Joint Committee at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jun 2025 | Appointment of ChairThat Councillor Jill Rhodes be appointed as chair for the 2025/26 municipal year. | Decided | Open |
| 27 Jun 2025 | Appointment of Vice ChairThat Councillor Carol Gahan be appointed as vice-chair for the 2025/26 municipal year. | Decided | Open |
| 27 Jun 2025 | Minutes of Previous MeetingThat the minutes of the meeting held on 25 April 2025 be approved as a correct record. | Approved | Open |
| 27 Jun 2025 | Shared Services Business Plans 2024-25 - End of Year ReportThat the Joint Committee note the Shared Services performance for 2024/25. | Noted | Open |
| 27 Jun 2025 | The Future Model for ICT: Programme Gemini UpdateThat the Joint Committee notes the progress made and current status of the Phase 1 Gemini Programme and recommends to... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.