11/1122M-Restoration of Gawsworth Quarry Using Inert Excavation and Construction/Demolition Wastes, Gawsworth Quarry, Gawsworth, Macclesfield for Mr Martin O'Gara, O'Gara Developments
ApprovedPlanning1 paper
Strategic Planning Board approved this item on Tuesday 18 March 2014. Below is the council's own wording, with the papers it was decided on.
RESOLVED That for the reasons set out in the report and in the oral update to Board the application be approved subject to completion of a Section 106 Agreement securing the following:- 1. A 10 year extended landscape and nature conservation management scheme; 2. Restriction on HGV movements associated with the scheme to an average of 300 movements a day in the event that both Gawsworth and Rough Hey Quarries are worked concurrently; And subject to the following conditions:- Duration and sequence of working Phased restoration Hours of operation Control over type of material imported Highway vehicle movements Control over noise and dust Plant and machinery Pollution control Drainage scheme Protection of footpath Protection of trees Soil storage and handling Site maintenance and maintenance of access road Details of lighting Submission of detailed landscape and nature conservation management plan Establishment of a liaison committee Control of invasive species Submission of soil tests National vegetation surveys and common standards surveys at each phase of development Biennial national vegetation surveys and common standard surveys for duration of management period ( Cllr Thorley left the meeting following consideration of the above application and did not return).
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
Proposal: RESTORATION OF GAWSWORTH QUARRY USING INERT EXCAVATION AND CONSTRUCTION/DEMOLITION WASTES
Applicant: MR MARTIN O'GARA, O'GARA DEVELOPMENTS
Expiry Date: 12-Jul-2011
SUMMARY RECOMMENDATION: APPROVE subject to conditions and s106 legal agreement
MAIN ISSUES: Principle of the Development Ground Stability Sustainable Management of Waste Feasibility of High Level Restoration Control of Imported Material Drainage Noise & Air Quality Highways and Impacts on Footpaths Landscape and Visual Amenity Ecology Impact on RIGs Designation Local Amenity
BACKGROUND TO THE REPORT
Members may recall that this application was considered by Strategic Planning Board on 29th February 2012, at which it was resolved that the application should be approved subject to a range of planning conditions and entering into a section 106 agreement to secure:
1. a 10 year extended landscape and nature conservation management scheme; 2. restriction on HGV movements associated with the scheme to an average of 300 movements a day in the event that both Gawsworth and Rough Hey Quarries are worked concurrently;
The planning permission is yet to be issued pending discussions on the section 106 legal agreement. In the intervening period, the National Planning Policy Framework has replaced the previous suite of national planning policy guidance for mineral development upon which Members based their resolution. In addition, the applicant has submitted a modified phasing plan, a more detailed conservation management plan and proposed slightly amended the hours of operation.
The item has therefore brought back to Strategic Planning Board to provide Members with the opportunity to reconsider their decision in the light of the additional revisions and new mineral planning policy context. A complete and updated report on the application is presented below.
DESCRIPTION OF SITE AND CONTEXT The site is the former Gawsworth Gritstone Quarry which is located to the east of A523 London Road, approximately 4.5km south of Macclesfield and approximately 1.1km south of the small settlement of Oakgrove.
Gawsworth Quarry and neighbouring Rough Hey Quarry directly to the north, form part of Gawsworth Common which lies in an elevated position on the western slopes of Croker Hill. Access to both sites is taken from a track which rises at sharp incline from its junction with A523 in a north east direction up to the quarry and former processing area, and then continues north east around the edge of the quarry and connects to Rough Hey Quarry approximately 600m north of the site. The track also serves a small number of neighbouring residential properties and a commercial property, the closest of which are approximately 370m from the site.
Gawsworth Quarry consists of the main extraction area, internal access tracks, and the former processing area. The 6.9ha application site is made up of the former quarry extraction zone, stockpiles of quarry overburden and soils, and internal access track. On the north west boundary is a 120m long and 35m high open, exposed quarry face. It is formed of glacial till, exposed rock face and a scree slope which is highly weathered and subject to erosion. The quarry face is actively receding northwards, generating a near vertical slope surface and leading to a loss of adjacent agricultural land. Land beyond the application site on the southeast and northeast boundary has already been subject to low level restoration associated with previous quarrying operations to grassland and linear strips of tree planting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
11/1122M-Restoration of Gawsworth Quarry Using Inert Excavation and Construction/Demolition Wastes, Gawsworth Quarry, Gawsworth, Macclesfield for Mr Martin O'Gara, O'Gara DevelopmentsMinutes
19211/1122M-Restoration of Gawsworth Quarry Using Inert Excavation and Construction/Demolition Wastes, Gawsworth Quarry, Gawsworth, Macclesfield for Mr Martin O'Gara, O'Gara DevelopmentsThis decision
11/1122M-Restoration of Gawsworth Quarry Using Inert Excavation and Construction/Demolition Wastes, Gawsworth Quarry, Gawsworth, Macclesfield for Mr Martin O'Gara, O'Gara DevelopmentsThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.