13/4683W-Removal of Condition 11 (Hours of Operation) on Approved Application 7/2006/CCC/19 (Development for the winning and working of sand and peat), White Moss Quarry, Radway Green, Alsager for Land Recovery Ltd
RefusedPlanning1 paper
Strategic Planning Board refused this item on Wednesday 18 February 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED That the application be refused for the following reasons:- 1. The proposed hours of plant maintenance do not conform with those stipulated in the development plan and special circumstances have not been demonstrated to justify any deviation from the policy. As such the proposal conflicts with the provisions of policy 37 of the Cheshire Replacement Minerals Local Plan; 2. Insufficient information has been provided to demonstrate that the proposed variation would not have an adverse impact upon the amenity of nearby residential properties which is contrary to policies 9 and 26 of Cheshire Replacement Minerals Local Plan, and policies and NE. 17 and BE.1 of Crewe and Nantwich Local Plan and guidance within the NPPF. In the event of any changes being needed to the wording of the Board’s decision (such as to delete, vary or add conditions/ informatives /planning obligations or reasons for approval/refusal) prior to the decision being issued, the Principal Planning Manager has delegated authority to do so in consultation with the Chairman of the Strategic Planning Board, provided that the changes do not exceed the substantive nature of the Board’s decision. Should this application be the subject of an appeal, authority be delegated to the Principal Planning Manager in consultation with the Chairman of the Strategic Planning Board to enter into a planning agreement in accordance with the S106 Town and Country Planning Act to secure the Heads of Terms for a S106 Agreement.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
The NPPF states that in assessing development proposals, local planning authorities should apply the presumption in favour of sustainable development.
In terms of sustainability, the proposal would satisfy the economic sustainability role by helping to support the operation of the existing quarry business which provides both direct and indirect benefits to the local economy. However these considerations would not outweigh the harm to the local environmental and social sustainability considerations having regard to the impacts on residential amenity.
The noise and disruption generated during these extended hours has the potential to present an unacceptable impact on residential amenity, and this impact has not been quantified or assessed through a noise survey. The hours proposed do not conform with those stipulated in Policy 37 of CRMLP and no information has been provided to demonstrate the exceptional circumstances to justify such an increase in hours nor any mitigation identified to address any associated impacts as required by this condition. The proposal therefore conflicts with policies 9, 26 and 37 of the CRMLP, policies NE.17 and BE.1 of Crewe and Nantwich Local Plan, along with paragraph 144 of the NPPF.
RECOMMENDATION: Refuse
PROPOSAL
This is an application for the variation of condition 11 of planning permission 7/2006/CCC/19 at White Moss Quarry. The condition currently stipulates:
‘Operations authorised with this consent shall not be carried out other than between the hours of:
0730 – 1800 hours Monday to Fridays 0730 – 1230 hours Saturdays Plant maintenance shall not be carried out other than between the hours of: 0730 – 1800 hours Monday to Saturday
On Saturdays moveable plant and vehicle maintenance will only be carried out within the designated buildings in the processing plant and stockpile area shown on plan 8/115/1A, except in emergencies. All emergencies will be notified to the Mineral Planning Authority on the next working day. Only plant and vehicles which are solely used within White Moss Quarry can be maintained on site.
No working shall take place on Sundays or Public Holidays’.
The application seeks to vary this condition to allow plant maintenance on Sundays from 0730 – 1800 hours in addition to the hours currently stipulated by this condition.
SITE DESCRIPTION
White Moss Quarry is located on Crewe Road (B5077), between the western extent of Alsager and the M6 motorway. Land to the north beyond Nursery Road comprises a number of residential properties, farms and agricultural land. To the east are fields beyond which are a number of properties on Close Lane and further properties forming the western edge of Alsager. To the south lies a garden centre and Crewe Road beyond which is the extensive development of Radway Green BAE Plant; whilst the M6 lies to the west beyond open fields.
The closest residential properties lie adjacent to the northern and western site boundary, and on Crewe Road, with further properties lying along Close Lane the closest of which is approximately 100m from the site. A public footpath runs along the southern and western site boundary. The site is within Open Countryside, as defined in the local plan, albeit the quarry boundary adjoins the settlement boundary of Alsager.
RELEVANT HISTORY
Long planning history on the wider quarry site. Most relevant of which are:
7/2006/CCC/19 Variation of conditions of permission 7/P04/1054 granted February 2007 7/P04/1054 Extension of time until 2028 granted December 2004 13/4132N Outline application for residential development – approved at SPB August 2014
NATIONAL & LOCAL POLICY
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
13/4683W-Removal of Condition 11 (Hours of Operation) on Approved Application 7/2006/CCC/19 (Development for the winning and working of sand and peat), White Moss Quarry, Radway Green, Alsager for Land Recovery LtdMinutes
11213/4683W-Removal of Condition 11 (Hours of Operation) on Approved Application 7/2006/CCC/19 (Development for the winning and working of sand and peat), White Moss Quarry, Radway Green, Alsager for Land Recovery LtdThis decision
13/4683W-Removal of Condition 11 (Hours of Operation) on Approved Application 7/2006/CCC/19 (Development for the winning and working of sand and peat), White Moss Quarry, Radway Green, Alsager for Land Recovery LtdThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.