CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cheshire East Council
Strategic Planning Board, Wednesday 18 February 2015 at 10.30am

14/4296N-Installation of a solar park with an output of approximately 8.28 MW on land associated with Hatherton Lodge Farm, Agricultural land at, Hatherton Lodge Farm, Hunsterson, Road, Hatherton, Nantwich for Mr Markus Wierenga, Green Switch Developments Ltd

Refused Planning 1 paper

Strategic Planning Board refused this item on Wednesday 18 February 2015. Below is the council's own wording, with the papers it was decided on.

Item115

Resolved

RESOLVED That the application be refused for the following reasons:- 1. The development of the proposed solar park would have a significant adverse impact on the landscape character of the site. In particular the views from public footpath 9 an 12 Hatherton and 2 Hunterston . This adverse impact significantly and demonstrably outweighs the benefits of the scheme in terms of renewable energy production. The proposal is therefore contrary to paragraph 98 of the NPPF and Policies NE.2, and NE.19 of the Borough of Crewe and Nantwich Replacement Local Plan 2011. 2. The proposal would result in loss of the best and most versatile agricultural land. The use of the best and most versatile agricultural land is unsustainable and contrary to Policy NE.12 of the Borough of Crewe and Nantwich Replacement Local plan 2011, Paragraph 112 of the National Planning Policy Framework and guidance contained within paragraph 13 of the Renewable and Low Carbon Energy Section of the Planning Practice Guidance. (This decision as contrary to the Officer’s recommendation of approval. The meeting adjourned for a short break. Councillor B Murphy left the meeting and did not return).
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Strategic Planning Board

Application No: 14/4296N

Location: AGRICULTURAL LAND AT, HATHERTON LODGE FARM, HUNSTERSON ROAD, HATHERTON, NANTWICH, CW5 7RA

Proposal: Installation of a solar park with an output of approximately 8.28 MW on land associated with Hatherton Lodge Farm.

Applicant: [name removed], Green Switch Developments Ltd

Expiry Date: 11-Dec-2014

SUMMARY The NPPF requires that Local Planning Authorities should recognise the responsibility on all communities to contribute to energy generation from renewable or low carbon sources.

In terms of sustainability, the benefits of the provision of a source of renewable energy, for which there is a recognised need, outweighs any harm having regard to the impact on open countryside and loss of best and most versatile agricultural land.

The proposal would satisfy the economic and social sustainability roles by providing energy from a renewable, low carbon source.

The proposal is considered to have an impact on the landscape of the area but not sufficiently harmful in the overall balance. It is acceptable in terms, amenity, flood risk, highway safety and ecology.

The scheme therefore represents a sustainable form of development and the planning balance weighs in favour supporting the development.

RECOMMENDATION: Approve subject to conditions.

PROPOSAL

The development proposal is for a circa 8.25MWp Solar Park laid out across approximately 16 hectares of agricultural land within the existing field boundaries.

The panels would be freestanding units constructed of toughened glass set in aluminium frames. They would be mounted close to the ground (approx 2.33m high with a tilt angle of 25 degrees), and fixed in position through piles driven into the ground, meaning that no concrete foundations are required. There would be approximately 28,160 panels. The panels would be arranged in rows on an east to west alignment, facing south to maximise exposure to sunlight. Security fencing would be erected around the boundary to restrict access to the site.

The panel frames are secured into position through piles driven into the ground, meaning there is no requirement for excavation or concrete laying.

There would be inverters housed in weather proof fibre glass enclosures and a small control building/substation within the site.

Access during the construction period, for maintenance and subsequent decommissioning, would be via a track which leads from Hunterston Road to the north and through Hatherton Lodge Farm.

The operational life of the solar park would be 25 years.

SITE DESCRIPTION:

The site is located southeast of Nantwich close to the villages of Hatherton and Hunsterson on land at Hatherton Lodge Farm. It consists of four fields with an overall area of 15.98 hectares. The site is located in a shallow basin and is generally flat. There are mature but gappy hedgerows and trees around the site perimeter and on the boundaries between the four fields and a low ridge along the north eastern site boundary. The topography of the surrounding area is broadly undulating.

The land has been assessed as being 82% Grade 4, 4% Grade 3b and 14% Grade 3a.

The site is designated as being within Open Countryside in the adopted local plan.

RELEVANT HISTORY:

An Environmental Impact Assessment screening opinion was requested relating to this site. (13/5090S) This concluded that the development would not constitute EIA development.

NATIONAL & LOCAL POLICY

National Policy: The National Planning Policy Framework establishes a presumption in favour of sustainable development.

Of particular relevance are paragraphs 14 and 98.

Development Plan:

The Development Plan for this area is the Borough of Crewe and Nantwich Replacement Local Plan 2011, which allocates the site as being within Open Countryside.

The relevant Saved Polices are: -

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
14/4296N-Installation of a solar park with an output of approximately 8.28 MW on land associated with Hatherton Lodge Farm, Agricultural land at, Hatherton Lodge Farm, Hunsterson, Road, Hatherton, Nantwich for Mr Markus Wierenga, Green Switch Developments LtdMinutes 225 KB DownloadRead as text

At this meeting

Whole meeting
108Minutes of the Previous MeetingApproved 109Public SpeakingNoted 11014/3649C-Outline application for development of land to the west of Padgbury Lane, Congleton for up to 120 dwellings, up to 180 sq.Refused 11114/3657C-Outline application for development of land to the west of Padgbury Lane, Congleton for up to 150 dwellings, community facilities and associated infrastructure (Resubmission of 13/4216C), Land West of Padgbury Lane, Congleton, Cheshire for Northern Property Company LimitedRefused 11213/4683W-Removal of Condition 11 (Hours of Operation) on Approved Application 7/2006/CCC/19 (Development for the winning and working of sand and peat), White Moss Quarry, Radway Green, Alsager for Land Recovery LtdRefused 11313/4685W-Removal of Condition 24 on Approved Application 7/2008/CCC/8 - Aggregate Recycling Operations, to allow flexibility for essential site maintenance of plant. To also allow plant maintenance 07.30 - 18.00 on Sundays, White Moss Quarry, Radway Green, Alsager for Land Recovery LimitedRefused 11414/5338C-Variation of condition 4 and removal of conditions 35 and 36 to planning application 13/2746C - Erection of up to 180 dwellings, public open space, green infrastructure and associated works, Land Between, Black Firs Lane, ChelfordRefused
11514/4296N-Installation of a solar park with an output of approximately 8.28 MW on land associated with Hatherton Lodge Farm, Agricultural land at, Hatherton Lodge Farm, Hunsterson, Road, Hatherton, Nantwich for Mr Markus Wierenga, Green Switch Developments LtdThis decision
116Land to the West of Goldfinch Close, CongletonDecided 117Land adjacent to Heath End Farm, Hassall Road, AlsagerRefused 118Cheshire Fresh, Middlewich: Approval sought for delegation to Cheshire West and Chester CouncilDecided

More from Cheshire East Strategic Planning Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingThat the minutes of the meeting held on 22 July 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Sep 2026 25/1573/FUL - Full planning application for a residential development including associated access, infrastructure and landscaping. Land off Cumber Lane, WilmslowThat application 25/1573/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 3-year ti... Approved Open
16 Sep 2026 25/2071/FUL - Full planning application for a residential development and the provision of associated access and infrastructure works including roads, drainage infrastructure, car parking, public open space and landscaping. Land at Dean Row Road, WilmslowThat application 25/2071/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 2-year ti... Approved Open
16 Sep 2026 National Scheme of DelegationThat the Strategic Planning Board Noted the changes introduced by the for Planning Functions that will be implemented... Noted Open
22 Jul 2026 Minutes of the Previous MeetingThat the minutes of the meetings held on 27 May 2026 and 9 June 2026 be approved as correct records. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies