Environment Overview and Scrutiny Committee approved this item on Thursday 28 January 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED That Cabinet be recommended to approve delegated authority to the Portfolio Holder for Open Spaces in consultation with the Chief Operating Officer and Director of Legal Services to vary the Service Operating Contract of Ansa Environmental Services and associated agreements, subject to due diligence being undertaken by legal, procurement and finance.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
Report to Environment Overview and Scrutiny Committee
Recommendation
2.1That the Cabinet approve delegated authority to the Portfolio Holder for Open Spaces in consultation with the Chief Operating Officer and Director of Legal Services to vary the Service Operating Contract of Ansa Environmental Services and associated agreements, subject to due diligence being undertaken by legal, procurement and finance.
3. Other Options Considered
3.1To achieve best value for the Council Ansa need to relet our main waste and recycling procesing contracts. There is currently insufficient time (5 years) remaining on Ansa’s contract with the Council to enable them to effectively secure value for money. Any new contracts let would extend beyond the current end date of Ansa’s contract with the Council.
3.2The alternative would be for the Council to procure and manage these waste and recycling processing contracts itself. This would however involve
1 a contract modification to Ansa’s operating contract as this function and the procurement staff involved have been transferred to Ansa. It would also be against the high level objectives of the Council’s waste strategy that seek to deliver services in a cost effective way through a wholly owned company.
Reasons for recommendation
4.1In its waste strategy 2030 the council set out to deliver services in a cost effective way through a wholly owned company. Since its inception in April 2014, Ansa has delivered what has been asked of it by the council. Targets are being met and efficiencies made so that a quality service is maintained on the council’s behalf. It is now important to consider ensuring this positive development is not stunted before further benefits are reaped.
4.2As part of the waste strategy to reduce disposal to landfill to zero and achieve 100% disposal to waste to energy generation the Council is constructing its central environmental hub. Ansa now need to procure a number of contracts to coincide with the opening of the hub to allow the treatment and disposal of waste ending landfilling and delivering savings associated with it. At present however Ansa’s contract with the Council is due for renewal only 4 years after the hub is completed.
4.3This time limitation on the scope of Ansa’s development would be unduly restrictive since any contracts they subsequently entered into with third parties dealing with various aspects of waste management and treatment would be too short for most companies to agree with. To hamstring our succesful ASDV in this way would not make economic, environmental or financial sense.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment Overview and Scrutiny Committee at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.