RESOLVED That for the reasons set out in the report the application be APPROVED subject to the following conditions: 1. Commencement of development (3 years) 2. Development in accord with approved plans, including, materials, levels, boundary treatments 3. Delivery of affordable housing 4. Grampian condition mitigation for Lesser silver diving beetle and Mud snail 5. Mitigation for Breeding Birds in accordance with submitted details 6. Reptile method statement 7. Submission of landscape scheme 8. Submission of drainage scheme 9. Arboricultural method statement and tree protection measures 10. Dust Management and site welfare plan in accordance with details provided 11. Noise mitigation scheme 12. Details of lighting to be submitted 13. Details of construction management plan 14. Electric vehicle charging points to be provided for dwellings 15. Travel plan to be submitted 16. Phase II investigation to be submitted 17. Bin Storage 18. Cycle Storage Informatives : 1. Hours of construction 2. Contamination informative 3. Environment Agency contamination informative
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
The site is within the Open Countryside where, under policies NE.2 there is a presumption against new residential development. However, as Cheshire East cannot demonstrate a 5 year supply of deliverable housing sites, the presumption in favour of sustainable development at paragraph 14 of the Framework applies where it states that LPAs should grant permission unless any adverse impact of doing so would significantly and demonstrably outweigh the benefits from it, when assessed against the Framework as a whole; or specific policies in the Framework indicate development should be restricted.
The site has an ‘in principle’ planning approval, which is awaiting the finalisation of the section 106 agreement, the previously approved scheme was for the same site, however was a market scheme. Therefore the principle of housing development on this site has been accepted by the Local Planning Authority.
The development would provide significant social benefits in terms of much needed affordable housing provision by providing 100% social rented affordable housing which is desperately needed, and would contribute to the Council’s delivery of 5 year housing land supply. It would provide a small area of public open space facility for future residents, and the development would provide significant economic benefits through the provision of employment during the construction phase, new homes and benefits for local businesses. Due to its landscape designation, it is not considered that the proposal will have a significant landscape impact.
Balanced against this are the adverse impacts of the development including the loss of open countryside and the lack of planning obligations for infrastructure which play a vital role in ensuring the social wellbeing of the community. However the contribution of affordable housing is also considered an important and overriding consideration.
On the basis of the above, it is considered that the proposal represents sustainable development and paragraph 14 is engaged due to the provision of 81 social rented affordable homes. Furthermore, applying the tests within paragraph 14 it is considered that the adverse effects of the scheme are significantly and demonstrably outweighed by the benefits. SUMMARY RECOMMENDATION Approval subject to conditions
PROPOSAL The application seeks full planning permission for 81 affordable dwellings, 15 units will be made available for affordable sale, however if they are not sold within 8 weeks they will revert back to social rented, the proposal is for a mix of 10 x three bed dwellings, 45 x two bed dwellings, 6 x two bed apartments and 20 x one bed apartments in three two storey apartment blocks. The layout has been subject to some design changes over the course of the application process, however the mix and broad location of the units has remained the same. The application proposes one point of access to the site. The main access road runs through the site with clusters of dwellings off it. A large amount of boundary landscaping will be retained, with additional landscaping proposed to mitigate impacts on the landscape.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
15/5063N: Land West Of, Broughton Road, Crewe: Residential development (Use Class C3) consisting of 81 no. new affordable dwellings comprising 10 no. three bed houses, 45 no. two bed houses, 6 no. two bed apartments and 20 no. one bed apartments in three two storey apartment blocks with associatedMinutes
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.