RESOLVED That for the reasons set out in the report, the appeal be defended on the following grounds: 1. The Local Planning Authority considers that having regard to the cumulative impact of developments in Sandbach that the proposed development would be contrary to Policy PC1, PC3 and H1 contained within the Sandbach Neighbourhood plan and that the development when taken cumulatively with other developments in Sandbach would prejudice the local plan making process. As a result the development would be contrary to guidance contained at Paragraph 216 of the NPPF and guidance contained within the NPPG. 2. Whilst it is acknowledged that there is a presumption in favour of sustainable development in the planning balance, it is considered that the development is unsustainable because of the conflict with the draft Sandbach Neighbourhood plan and because of the unacceptable environmental and economic impact of the scheme in terms of loss of best and most versatile agricultural land and open countryside. These factors significantly and demonstrably outweigh the social benefits in terms of its contribution to boosting housing land supply, including the contribution to affordable housing. As such the proposal is contrary to Policies PS8 and H6 of the adopted Congleton Borough Local Plan First Review 2005 and Policies PG 5 and SE 2 of the Cheshire East Local Plan Strategy – Submission Version and the provisions of the NPPF.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
1.1Planning application 14/1189C was determined by the Strategic Planning Board on 3rd June 2015. This report is to consider an update to the reasons for refusal in advance of the upcoming appeal.
1.2The minutes from the meeting are as follows:
(a) That the application be REFUSED for the following reasons:
1. The Local Planning Authority considers that having regard to the context of developments in the Sandbach area and the scale of the proposed development that it would be premature following the publication consultation draft of the Sandbach Neighbourhood plan. As such allowing this development would prejudice the outcome of the neighbourhood plan-making process and would be contrary to guidance contained at Paragraph 216 of the NPPF and guidance contained within the NPPG.
2. Whilst it is acknowledged that there is a presumption in favour of sustainable development in the planning balance, it is considered that the development is unsustainable because of the conflict with the draft Sandbach Neighbourhood plan and because of the unacceptable environmental and economic impact of the scheme in terms of loss of best and most versatile agricultural land and open countryside. These factors significantly and demonstrably outweigh the social benefits in terms of its contribution to boosting housing land supply, including the contribution to affordable housing. As such the proposal is contrary to Policies PS8 and H6 of the adopted Congleton Borough Local Plan First Review 2005 and Policies PG 5 and SE 2 of the Cheshire East Local Plan Strategy – Submission Version and the provisions of the NPPF.
(b) That, in order to give proper effect to the Board`s/Committee’s intentions and without changing the substance of the decision, authority be delegated to the Head of Strategic & Economic Planning, in consultation with the Chair (or in his absence the Vice Chair) of Strategic Planning Board, to correct any technical slip or omission in the wording of the resolution, between approval of the minutes and issue of the decision notice.
(c) That, should the application be subject to an appeal, the following Heads of Terms should be secured as part of any S106 Agreement:
1. A scheme for the provision of 30% affordable housing – 65% to be provided as social rent/affordable rent with 35% intermediate tenure. The scheme shall include: - The numbers, type, tenure and location on the site of the affordable housing provision - The timing of the construction of the affordable housing and its phasing in relation to the occupancy of the market housing - The arrangements for the transfer of the affordable housing to an affordable housing provider or the management of the affordable housing if no Registered Social Landlord is involved - The arrangements to ensure that such provision is affordable for both first and subsequent occupiers of the affordable housing; and - The occupancy criteria to be used for determining the identity of occupiers of the affordable housing and the means by which such occupancy criteria shall be enforced. 2. Provision of Public Open Space and a NEAP (8 pieces of equipment) to be maintained by a private management company 3. Primary school education contribution of £325,388.70 4. Secondary school education contribution of £343,169.49 5. PROW Contribution of £25,000 6. Highways Contribution of £137,211 towards improvements to the A533/A534 corridor
2.0Decision Required
2.1Since the refusal of this application an appeal has now been lodged and it is now necessary to update the reasons for refusal to reflect the current policy position as detailed.
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.