18/5811M-A new intake structure on the west bank roughly 20m upstream of the weir, 3.5m wide and protected by a coarse screen of 150mm aperture.

Approved Planning 1 paper

Northern Planning Committee approved this item on Wednesday 13 March 2019. Below is the council's own wording, with the papers it was decided on.

Item48

Resolved

RESOLVED That the application be approved subject to the following conditions:- 1. Time (3 years) – Except where varied 2. Approved plans 3. Materials as per application 4. AIA - Implementation 5. Prior submission/approval of details of an Engineer designed no dig hard surface construction for the access track 6. Prior submission/approval of agreed scheme of supervision for the approved arboricultural protection measures 7. Nesting birds 8. Prior submission/approval of breeding bird features 9. Prior submission/approval of updated badger survey 10. Watercourse protection method statement 11. Prior submission/approval of a habitat/woodland management plan for lifetime of screw 12. Prior submission/approval of a method statement to safeguard areas of retained habitat 13. Noise mitigation – Implementation 14. Temporary access track cannot implemented until the CLR works at the eastern end have been completed 15. Removal of access track upon completion of works and restoration 16. Prior submission/approval of a remediation scheme comprising of a shut-down arrangements, involving the de-commissioning/shut-down of the facility rather than its removal 17. Prior submission/approval of boardwalk construction method statement 18. Prior submission/approval of a Education Plan 19. Prior removal of any trees harming stone structure adjacent to the Weir done prior to installation of Screw In the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Planning (Regulation) delegated authority to do so in consultation with the Chairman of the Northern Planning Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision. (This decision was contrary to the Officer’s recommendation of refusal. During the course of consideration of the application the meeting was adjourned in order for Officers to compile a list of conditions given that there had been a proposal to approve the application contrary to the Officer’s recommendation).
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Northern Planning Committee

Summary

The application site is located predominantly within the Open Countryside where development is only supported in certain instances to protect it for its own sake.

Policy SE8 of the CELPS supports community-led renewable energy initiatives such as that proposed, irrespective of its location, as the benefits of such schemes are recognised. In this case, the environmental benefits are the CO2 savings (around 200 tones per year) that would be created as a result of the development, there would also be benefits to the Grade II listed building through the proposed removal of tree samplings from the brick structure, the social benefits in terms of assisting in the creation sustainable communities and the economic benefits in terms of any profits being spent on local community projects.

However, Policy SE8 of the CELPS also states that consideration also needs to be given to anticipated adverse impacts such as; the impact upon the surrounding landscape, including matters of heritage, ecology and trees; the impact upon residential amenity and the impact in this case, upon Jodrell Bank.

In response, adverse impacts are identified in relation to; ecology and trees. No significant residential amenity or Jodrell Bank impacts are identified. Balancing up the adverse impacts against the benefits of the scheme in the context of Policy SE8, whilst the weight afforded to the environmental benefits are significant, the weight afforded to the social and economic benefits are limited as there is no mechanism proposed to secure these aspects.

In consideration of the adverse impacts, whilst it is recognised that the development only relates to a relatively small portion of the Havannah Wood LWS, it is understood to be a section which is deemed particularly rich and of good quality, the loss of which would be irreversible. Furthermore, Cheshire has less than half the national average of woodland cover so its retention is particularly important. It is also a consideration that the areas of the LWS that would be impacted during construction would be greater than that of the footprint of the proposed development shown. In consideration the adverse impact upon trees, the loss of trees is considered to be significant and will have an adverse impact on the woodland. There is also a lack of information to satisfy concerns that the development would detrimentally impact a veteran tree.

It is concluded that because of the irreversible harm that would be created to the LWS and wet woodland and the lack of information relating to possible harm upon a veteran tree, the environmental harm of the development outweighs the benefits, irrespective of the community benefits being secured.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
18/5811M-A new intake structure on the west bank roughly 20m upstream of the weir, 3.5m wide and protected by a coarse screen of 150mm aperture. 30m of 1500mm dia. buried low pressure pipeline. An Archimedes Screw turbine set onto concrete foundations within a 3m-wide channel constructed from sheetMinutes 546 KB DownloadRead as text

More from Cheshire East Northern Planning Committee

All decisions
MeetingDecisionOutcome
19 Aug 2026 Minutes of the Previous MeetingThat the minutes of the meeting held on 24 June 2026 be approved as a correct record. Approved Open
19 Aug 2026 25/2053/FUL - Land Of The Former Knowle House, Sagars Road, Handforth, SK9 3EAThat for the reasons set out in the report the application be APPROVED subject to a Section 106 Agreement to secure t... Approved Open
19 Aug 2026 26/0581/FUL - The Cave, 91 - 95 Mill Street, Macclesfield, SK11 6NNThat the application be REFUSED as detailed in the Officer recommendation for the following reasons; 1. The proposals... Refused Open
19 Aug 2026 25/4532/FUL - LAST ORDERS, 116 - 118 Park Lane, Macclesfield, Cheshire East, SK11 6UAThat the application be delegated back to Officers to REFUSE the application for the following reason; 1. The submitt... Refused Open
19 Aug 2026 Tree Preservation Order 2026 - Alderley Edge - Brocklands, Brook LaneThat the Tree Preservation Order at Brocklands , Brook Lane, Alderley Edge be confirmed with no modifications. The Or... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies