Strategic Planning Board, Wednesday 24 April 2019 at 10.30am

19/0529C-Application seeking outline planning permission for up to 19,236 sqm of employment floorspace (Use Class B1c/B2/B8) with ancillary (integral) office floorspace (Use Class B1a), associated parking, landscaping and reprofiling of sit

Refused Planning 1 paper

Strategic Planning Board refused this item on Wednesday 24 April 2019. Below is the council's own wording, with the papers it was decided on.

Item112

Resolved

RESOLVED That the application be refused for the following reason:- The Local Planning Authority considers that the proposed development by reason of its layout and massing does not allow sufficient space for landscaping to mitigate the adverse impacts of the development, or ensure a design solution which achieves a sense of place by protecting and enhancing the quality, distinctiveness and character of Alsager. As a result the proposed development is contrary to Policies SE 1 (Design), SE 4 (The Landscape) and LPS 25 ( Radway Green North, Alsager) of the Cheshire East Local Plan Strategy and the NPPF. In order to give proper effect to the Board`s intent and without changing the substance of its decision, authority is delegated to the Head of Development Management in consultation with the Chairman (or in their absence the Vice Chairman) to correct any technical slip or omission in the resolution, before issue of the decision notice. If the application is subject to an appeal approval is given to enter into a S106 Agreement with the following Heads of Terms:- S106 Amount Triggers Bus Infrastructure/Pedestrian Crossing Connectivity £120,000 50% prior to commencement and 50% prior to first occupation. (This decision was contrary to the officer’s recommendation of approval).
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Strategic Planning Board

Summary

The principle of development is considered to be acceptable as the site is allocated for employment development under LPS 25 of the CELPS

The development will not have a detrimental impact upon residential amenity (including for future occupants of the approved development to the north).

The impact upon air quality has been assessed as part of this application and subject to the imposition of planning conditions the development would comply with Policy SE 12.

Details of the proposed landscaping are now included within this application and the details are considered to be acceptable and would address the previous reason for refusal. The proposed development is considered to comply with the requirements of Policies SE 4 and SE 5.

With regard to ecological impacts, the development would not impact upon the Midland Meres and Mosses Phase 2 Ramsar and Oakhanger Moss SSSI or protected species/biodiversity (subject to the imposition of planning conditions. The development complies with the requirements of policies LPS 25 and SE 3. An update will be provided in relation to the impact upon other protected species.

The development would not have significant drainage/flood risk implications and complies with Policy SE 13. An update will be provided in relation to the points of objection raised by both the Environment Agency and United Utilities.

The development is acceptable in terms of its impact upon trees on this site and replacement planting will be secured. This development will comply with Policy SE 5. On balance it is considered that the proposed development demonstrates that an acceptable design solution can be secured in accordance with Policy SE 1. However this is a Reserved Matter and the final judgement will be made at that stage.

The impact in terms of the proximity to the licensed explosive facility will be dealt with at the reserved matters stage (as it is a design/appearance issue)..

The proposed access point is acceptable and the traffic impact as part of this development has already been accepted together with contributions for off-site highway works. This is in accordance with policies LPS 25 and CO 1.

The development of the site would provide a number of economic benefits in terms of job creation and during the construction phase of the development.

Recommendation

That the application be approved subject to referral to the Secretary of State, subject to the completion of a Section 106 Agreement and conditions

PROPOSAL:

This is an outline planning application for 19,236sqm of employment floor space (Use Classes B1c/B2/B8) with ancillary office, associated parking, landscaping and profiling of the site.

The matters to be determined at this stage are the access, landscaping, layout and scale of the development. Appearance is reserved for future determination.

The built form of the proposed development would be located to the north of the watercourse which crosses the site with part of the southern parcel being utilised for compensatory storage. The plans show a layout of 5 units arranged around an internal access road.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
19/0529C-Application seeking outline planning permission for up to 19,236 sqm of employment floorspace (Use Class B1c/B2/B8) with ancillary (integral) office floorspace (Use Class B1a), associated parking, landscaping and reprofiling of site. Matters of Access, Layout, Landscaping and Scale are applMinutes 1.2 MB DownloadRead as text

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. 19/0529C-Application seeking outline planning permission for up to 19,236 sqm of employment floorspace (Use Class B1c/B2/B8) with ancillary (integral) office floorspace (Use Class B1a), associated parking, landscaping and reprofiling of sitThis decision
  2. 21/2240C Application seeking detailed consent via Reserved Matters approval following Outline application17/1000C for 454 dwellings and the associated infrastructure and open space on Land off Giantswood Lane and Manchester Road, Congleton for Michael Blackhurst, Redrow HomesApproved
  3. 15/5407M HARMAN TECHNOLOGY SITE AND ADJOINING LAND, ILFORD WAY, MOBBERLEY, CHESHIRE - Hybrid planning application for mixed-use redevelopment seeking: A: Full planning permission for alterations to existing employment buildings, constructioApproved
  4. 15/4967N Land East Of Rope Lane, Shavington, Crewe, Cheshire: Reserved Matters application seeking consent for appearance, landscaping, layout and scale following the approval of 14/3267N - Construction of up to 53 dwellings including details of access for Wainhomes (North West) LtdApproved
  5. 15/4967N Land East Of Rope Lane, Shavington, Crewe, Cheshire: Reserved Matters application seeking consent for appearance, landscaping, layout and scale following the approval of 14/3267N - Construction of up to 53 dwellings including details of access for Wainhomes (North West) LtdDeferred
  6. 11/1879N-A Hybrid Planning Application Seeking Residential Development for up to 400 New Dwellings with Open Space;Approved

More from Cheshire East Strategic Planning Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingThat the minutes of the meeting held on 22 July 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Sep 2026 25/1573/FUL - Full planning application for a residential development including associated access, infrastructure and landscaping. Land off Cumber Lane, WilmslowThat application 25/1573/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 3-year ti... Approved Open
16 Sep 2026 25/2071/FUL - Full planning application for a residential development and the provision of associated access and infrastructure works including roads, drainage infrastructure, car parking, public open space and landscaping. Land at Dean Row Road, WilmslowThat application 25/2071/FUL be APPROVED subject to the following conditions and S106 Agreement; Conditions 2-year ti... Approved Open
16 Sep 2026 National Scheme of DelegationThat the Strategic Planning Board Noted the changes introduced by the for Planning Functions that will be implemented... Noted Open
22 Jul 2026 Minutes of the Previous MeetingThat the minutes of the meetings held on 27 May 2026 and 9 June 2026 be approved as correct records. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies