Update following the resolution to approve application 18/3766N - Duelling of the existing 3.3km stretch of the A500 between Junction 16 & Meremoss Roundabout)
DecidedPlanning1 paper
Strategic Planning Board decided this item on Wednesday 24 April 2019. Below is the council's own wording, with the papers it was decided on.
RESOLVED That the mitigation period in condition 18 be revised to 25 years with no changes to the Heads of Terms or remaining planning conditions. After the 25 year period for ecological/landscaping mitigation, the applicant was advised to make best endeavours for the land to be transferred to a relevant body for the future maintenance of the land to ensure its ecological/landscape function such as the Woodland Trust etc. Note of thanks Prior to the close of the meeting, the Chairman thanked Members and Officers for their assistance over the year and wished those Members not standing for re-election the very best.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
1.1Planning application 18/3766N was referred to Strategic Planning Board (SPB) on 19th December 2018. This report is to consider an update to condition 18 listed at the bottom of the committee report.
1.2The minutes from the meeting are as follows:
RESOLVED
That the Board be minded to approve subject to the referral to the Secretary of State and the receipt of the financial off-set payment to Ecology of £32,144.86. In the event that the consented development is not implemented the payment would be returned to the applicant. And subject to the following conditions:-
1. Time limit 2. Plans 3. Materials 4. Drainage strategy 5. Contaminated land 6. Remediation strategy 7. Verification report 8. Ongoing contamination 9. Foundation Design / Piling 10. Management scheme of the PROW 11. Landscaping scheme provided 12. Landscaping scheme implementation 13. Tree Protection measures 14. Retention of existing trees/shrubs 15. Detailed tree felling / pruning specification 16. Programme of archaeological work 17. The provision and management of proposed compensatory habitat creation Englesea Brook and Barthomley Brook 18. 30 year landscape and ecological management plan 19. Full design and construction details of any required improvements to M6 junction 16 20. Carried out in accordance with the Flood Risk Assessment 21. Construction Management Plan to include temporary “unsuitable for HGV” signage at Snape Lane, Radway Green Road and Main Road 22. Liaison Committee with Parishes to be established for construction phase
2.0Decision Required
2.1The mitigation period in condition 18 is revised to 25 years with no changes to the Heads of Terms or remaining planning conditions
Background
3.1This report relates to condition 18 of the committee report which requires the applicant to provide and implement 30 year landscape and ecological management plan.
3.2Since the SPB resolution, the negotiations regarding pre- commencement conditions have been taking place over the number of years the ecological/landscape management plan requires mitigation. The CIL section of the committee report, advises that the mitigation period should be in perpetuity (200 years) but condition 18 at the bottom of the report proposes this as being for 30 years. As members may be aware, similar road schemes have recently been approved by the Council but with a 25 year management plan condition.
4 Proposed Development
4.1The full planning permission that the Council resolved to approve in 2018 was for the widening of the existing 3.3km stretch of the A500 between Junction 16 & the Meremoor Moss roundabout to facilitate 2 lanes on both sides of the road.
5 Officer Comment
5.1Following discussions with the Councils Ecologist to consider what is a reasonable mitigation period and to separate what is aspirational and to be consistent with other consented schemes in the Borough for similar infrastructure proposals, it is necessary to amend the wording of the condition to propose a revised mitigation period. There is no change to the proposed level of developer contribution (£32,144.86) towards the ecological mitigation. Therefore the Strategic Planning Board’s agreement is sought for the mitigation period for this condition to be revised from 30 to 25 years.
5.2There is an aspiration that the land will be transferred to another body after this period, such as the Woodland Trust, however it is not possible to request this in the application process. 6 Conclusion
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Update following the resolution to approve application 18/3766N: Duelling of the existing 3.3km stretch of the A500 between Junction 16 & Meremoss Roundabout)Minutes
113Update following the resolution to approve application 18/3766N - Duelling of the existing 3.3km stretch of the A500 between Junction 16 & Meremoss Roundabout)This decision
Update following the resolution to approve application 18/3766N - Duelling of the existing 3.3km stretch of the A500 between Junction 16 & Meremoss Roundabout)This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.