That the Committee 1 note continuing programme activity to deliver the recommendations supported by the Committee in November 2019 and agreed by both Council’s Cabinet in late 2019; and 2 note the anticipated timescales for completion of commercial negotiations with supplier Agilisys.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
3.1This paper provides information to the Committee Members to enable them to review the plans for the implementation of the replacement Finance and HR system. It also provides an update on the detailed commercial negotiations that have been undertaken with the provider.
4.0Report Background
4.1At the May 2016 meeting of this Committee, Members approved a programme of work to procure a new system to replace the existing Finance and HR system. Both Councils’ Cabinet meetings approved a recommendation in July 2017 to award a contract to Agilisys for the implementation of the Unit 4 Business World system. 4.2 In November 2019 (Cheshire West & Chester) and December 2019 (Cheshire East), each Council’s Cabinet approved recommendations relating to the Best4Business programme. This report provided an update regarding the scope and phasing of the programme, the revised programme governance arrangements, the procurement of external advisors, future arrangements for Member oversight of the programme and the scope of revised commercial arrangements with Agilisys.
4.3Delegated authority was also given to senior officers to finalise negotiations and agree variations to the contract with Agilisys, and to update the Inter-Authority Agreement appropriately.
4.4This report provides an update to members of this Committee on progress in the implementation of these decisions with a particular focus on the scope and phasing of the programme, the revised commercial arrangements with Agilisys and arrangements for Member oversight of the programme.
5.0Scope and phasing of programme
5.1The report to this committee of November 2019, noted that different options had been considered in relation to phasing, such as going live with the Finance, Procurement, Income and Payments elements of the solution at an earlier date to the HR and Payroll elements. The recommendation approved by the committee and subsequently by the Cabinet meetings is that the programme is delivered in phases.
5.2Further work has been undertaken to assess and validate the previously reported recommendation to pursue a phased approach to the programme. Having validated this approach in principle, a detailed programme plan is now being developed on this basis, in conjunction with our supplier Agilisys, which will confirm the target go lives dates for each phase of the implementation. This plan will be presented to the Councils for approval via established programme governance mechanisms. It is currently expected that this plan will be available for review and approval by early February 2020.
6.0Revised commercial arrangements
6.1The key principles underpinning the renegotiated commercial arrangement and financial settlement with Agilisys include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.