CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cheshire East Council
Cabinet, Tuesday 7 July 2020 at 1.00pm

Middlewich Eastern Bypass - Approval to Proceed with the Use of CPO Powers

Approved Executive 6 papers

Cabinet approved this item on Tuesday 7 July 2020. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

RESOLVED That Cabinet 1. confirms that the acquisition of the land identified on the Order Map attached to the report is necessary for highway purposes; 2. approves the draft Statement of Reasons and the draft Order Map both substantially in the form annexed to the report for the purposes of the Compulsory Purchase Order but delegates to the Director – Infrastructure and Highways, in consultation with the Director of Governance and Compliance, authority to modify them as necessary; 3. approves the draft SRO Plans substantially in the form annexed to the report for the purposes of the Side Roads Order and delegates to the Director – Infrastructure and Highways, in consultation with the Director of Governance and Compliance, authority to modify them as necessary; 4. authorises the Director – Infrastructure and Highways, in consultation with the Director of Governance and Compliance, to determine the form and contents of the Schedules (“the Schedules”) necessary as part of the CPO to identify the land contained within the Order Map; 5. authorises the Director of Governance and Compliance to make The Cheshire East Council (Middlewich Eastern Bypass) Compulsory Purchase Order 2020 (“the CPO”) pursuant to Section(s) 239, 240, 246, 250 and 260 of the Highways Act 1980, Schedule 3 to the Acquisition of Land Act 1981 and all other powers as appropriate for the purpose of acquiring the land and interests shown on the Order Map and described in the Schedules (or such lesser area of land should this in his opinion be appropriate) to facilitate the construction of the Scheme, and that the Common Seal of the Council be affixed to the CPO and to the Order Map; 6. authorises the Director of Governance and Compliance to make The Cheshire East Borough Council and Cheshire West and Chester Borough Council (Middlewich Eastern Bypass) (Classified Road) (Side Roads) Order 2020 (“the SRO”) under Sections 8, 14 and 125 of the Highways Act 1980 and all other necessary powers to improve, stop up existing highways, stop up and/or amend private means of access and provide replacement private means of access, and construct lengths of new highway as required to deliver the Scheme; 7. authorises the Director – Infrastructure and Highways, in consultation with the Director of Governance and Compliance, to make any amendments necessary to the contemplated CPO and/or SRO (“the Orders”) arising as a result of further design work or negotiations with landowners or affected parties or for any connected reasons in order to enable delivery of the Scheme; 8. authorises the Director of Governance and Compliance to advertise the making of the CPO and the SRO (“the Orders”) to comply with all associated requirements in respect of personal, press and site notices, and to take all other relevant action thereon to promote the confirmation of the Orders; 9. agrees that in the event that no objections are received to ... view the full minutes text for item 18.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Middlewich Eastern Bypass: App AMinutes 2 MB Copy on its way
PDF
Middlewich Eastern Bypass: App A1Minutes 1 MB Copy on its way
PDF
Middlewich Eastern Bypass: App BMinutes 2 MB Copy on its way
PDF
Middlewich Eastern Bypass: App B1Minutes 706 KB Copy on its way
PDF
Middlewich Eastern Bypass: App B2Minutes 349 KB Copy on its way
PDF
Middlewich Eastern Bypass: Approval to Proceed with the Use of CPO PowersMinutes 167 KB Copy on its way

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. Middlewich Eastern Bypass - Approval to Proceed with the Use of CPO PowersThis decision
  2. Decision to Let a Construction Contract for the Middlewich Eastern BypassNoted
  3. Recommendations from Corporate Policy Committee: Budget Approval and acceptance of DfT Grant for the Middlewich Eastern BypassApproved
  4. Budget Approval and Acceptance of DfT Grant for the Middlewich Eastern BypassApproved
  5. Middlewich Eastern Bypass - 2025-26 Grant Allocation AcceptanceApproved
  6. Middlewich Eastern Bypass - Authority to Enter into Construction ContractNoted

More from Cheshire East Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of Previous MeetingThat the minutes of the meeting held on 2 July 2026 be agreed as an accurate record and signed by the Chair. Agreed Open
3 Sep 2026 2026/27 Budget - Quarter 1 Forecast OutturnRESOLVED (unanimously): That Cabinet 1. Note the factors leading to a forecast balanced position and the contents of ... Noted Open
3 Sep 2026 Strategic Risk Register Update Q4 2025-26 and Q1 2026-27RESOLVED (unanimously): That Cabinet 1. Note the position of the Strategic Risk Register following the Quarter 4 2025... Noted Open
3 Sep 2026 Finance Leadership Improvement Plan Update and ReviewRESOLVED (unanimously): That Cabinet 1. Note the content and progress made against the Financial Leadership Improveme... Noted Open
3 Sep 2026 Performance Management Framework and Q4 Performance 2025/26RESOLVED (unanimously): That Cabinet 1. Approve the Performance Management Framework (PMF) attached at Appendix A. 2.... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies