22/0560M - Barclays Bank Plc, Radbroke Hall, Stocks Lane, Over Peover WA16 9EU: Installation of Photovoltaic cells above existing car parking spaces for Barclays Plc

Approved Planning 1 paper

Northern Planning Committee approved this item on Wednesday 7 June 2023. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That for the reasons set out in the report, the application be APPROVED, subject to referral to the Secretary of State and the following conditions 1. Commencement of development (3 years) 2. In accordance with approved plans 3. Details of materials to be submitted (including details of protective coating) 4. Temporary for a period of 30 years 5. Submission/approval of a de-commissioning statement 6. Submission/approval of an updated Arboricultural Method Statement (including updated Tree Protection Plan) 7. Submission/approval of an updated Landscaping Scheme (to include replacement tree planting) 8. Landscape - Implementation 9. Submission/approval of proposed external lighting scheme 10. Submission/approval of a Construction Management Plan 11. Nesting birds 12. Submission/approval of ecological enhancement scheme 13. If cease to be used for solar panels / renewable energy purposes structures to be removed from site 14. Submission/approval of elevated details of single solar panels. In the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add Conditions and/or Informatives or reasons for approval prior to the decision being issued, the Head of Planning has delegated authority to do so in consultation with the Chairman of the Northern Planning Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Northern Planning Committee

Summary

The proposed development for a solar array scheme above car parking spaces at this commercial site results in numerous benefits and disbenefits and an overall planning balance of the development is subsequently required.

With regards to the disbenefits, the proposed development would represent inappropriate development in the Green Belt. Additional harm to the Green Belt would be created in relation to openness in visual and spatial terms. The proposals would also result in ‘less than substantial’ harm to heritage assets, and according to the Council’s Heritage Officer, the degree of harm would be at the upper end of the scale. This harm is primarily due to the adverse impact of the development to the setting of the Grade II listed Radbroke Hall. Harm would also be derived from possible further tree losses on site around the perimeter given their possible shading implications on the solar panels. This remains a concern given that none of the trees are afforded protection.

The key benefits of this proposal would be that over a year, the development would account for 35% of the electricity demand of the site (during daylight hours) and for the summer months, the site could potentially be completely ‘off-grid’ in terms of electricity. In addition, there would be electricity to power 100 EV charging points.

It is accepted that the location of the development and the type of green energy proposed is the best option for green electricity production at the site. When this is considered in conjunction with the significant environmental benefits of the scheme and the important fact that the development is easily reversible, therefore any harm to the heritage assets and natural environment would not be permanent, subject to a condition to control the temporary nature of the development and a condition to control its de-commissioning, it is deemed that the environmental benefits of the development are sufficient to represent Very Special Circumstances that clearly outweigh all of the harm identified.

The application is therefore recommended for approval.

As the proposed development represents inappropriate development in the Green Belt and is over a certain scale and is being recommended for approval, the application needs to be referred to the Secretary of State for consideration as to The application is therefore recommended for approval.

As the proposed development represents inappropriate development in the Green Belt and is over a certain scale and is being recommended for approval, the application needs to be referred to the Secretary of State for consideration as to whether they wish to ‘call-in’ the application for consideration for consideration prior to a decision being issued.

Recommendation

APPROVE subject to referral to the Secretary of State for consideration, and conditions

REASON FOR REFERRAL

This application has been referred to Northern Planning Committee as it is deemed that the proposals represent a significant departure from policy, on a site of between 2 and 4 hectares.

DESCRIPTION OF SITE AND CONTEXT

The application lies within the grounds of Radbroke Hall, which is located off Stocks Lane and accommodates a large employment site housing Barclays Bank plc.

The complex includes a number of office buildings, including the original Radbroke Hall which is a Grade II Listed Building which also contains a small amount of office accommodation. The site has a number of car parking areas and the site is set within extensive grounds with recreation areas & on site catering.

There are a large number of mature trees around and within the site which provides a parkland setting.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
22/0560M: Barclays Bank Plc, Radbroke Hall, Stocks Lane, Over Peover WA16 9EU: Installation of Photovoltaic cells above existing car parking spaces for Barclays PlcMinutes 436 KB DownloadRead as text

At this meeting

Whole meeting

More from Cheshire East Northern Planning Committee

All decisions
MeetingDecisionOutcome
19 Aug 2026 Minutes of the Previous MeetingThat the minutes of the meeting held on 24 June 2026 be approved as a correct record. Approved Open
19 Aug 2026 25/2053/FUL - Land Of The Former Knowle House, Sagars Road, Handforth, SK9 3EAThat for the reasons set out in the report the application be APPROVED subject to a Section 106 Agreement to secure t... Approved Open
19 Aug 2026 26/0581/FUL - The Cave, 91 - 95 Mill Street, Macclesfield, SK11 6NNThat the application be REFUSED as detailed in the Officer recommendation for the following reasons; 1. The proposals... Refused Open
19 Aug 2026 25/4532/FUL - LAST ORDERS, 116 - 118 Park Lane, Macclesfield, Cheshire East, SK11 6UAThat the application be delegated back to Officers to REFUSE the application for the following reason; 1. The submitt... Refused Open
19 Aug 2026 Tree Preservation Order 2026 - Alderley Edge - Brocklands, Brook LaneThat the Tree Preservation Order at Brocklands , Brook Lane, Alderley Edge be confirmed with no modifications. The Or... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies