CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cheshire East Council
Northern Planning Committee, Wednesday 10 April 2024 at 10.00am

23/1174M - Dawson Farm, BUXTON ROAD, BOSLEY, SK11 0PX: Demolition of existing agricultural buildings and dwellinghouse, and construction of new replacement dwellinghouse with associated renewables and landscaping for Mr Alan Budden, Eco Design Consultants

Approved Planning 2 papers

Northern Planning Committee approved this item on Wednesday 10 April 2024. Below is the council's own wording, with the papers it was decided on.

Item66

Resolved

The Committee was minded to APPROVE the application against officer recommendation, for the following reasons: 1. The proposal faces up to the challenges of climate change, in terms of providing multigenerational living and reducing its energy consumption using renewable energy. 2. The design is appropriate as it fits into the landscape, would be pleasant in the Peak Park Fringe and would maintain the openness of the countryside. 3. The economic benefits to the local economy are considerable given the scale of development and the construction required. 4. The environmental benefits of the scheme are considerable given the proposed multigenerational living and renewable energy. 5. The proposal would result in the removal of some aesthetically displeasing agricultural buildings. 6. The size, scale, siting, and design would not be a visually obtrusive feature and would create and add a new concept of what is acceptable in the landscape with a modern multigenerational living arrangement. 7. Impacts on protected species would be ameliorated through habitat mitigation comprising of extensive bat boxes and retention of a barn. The development is of overriding public interest because of its experimental multigenerational living to reduce the development requirements in terms of the need for buildings and would provide sufficient renewable energy to sustain it. Under the terms of the Council’s Constitution and Terms of Reference, Members resolved to refer the application to Strategic Planning Board for determination as officer advice was that approval of the development would represent a significant departure from planning policies within the Development Plan, regarding development in the open countryside, design and those affecting protected species. In order to give proper effect to the Committee’s intentions and without changing the substance of the decision, authority is delegated to the Head of Planning, in consultation with the Chair (or in their absence the Vice Chair) of Northern Planning Committee to correct any technical slip or omission in the wording of the resolution, between approval of the minutes and issue of the decision notice. (This decision was contrary to the officer’s recommendation of refusal). The Committee adjourned for a short break.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Northern Planning Committee

Summary

The application site lies within the Open Countryside within the Peak Park Fringe Local Landscape Designation Area.

The application proposals would result in a replacement dwelling that is materially larger than the buildings it replaces. In addition, the proposals are considered to result in undue harm to the rural character of the countryside by virtue of the scale, siting, size and design and the extent of land to be reprofiled to accommodate the dwelling which would have a disruptive and adverse effect of the visual qualities of the existing landscape character.

The proposals would result in environmental harm that would be created due to the risks posed in relation to Bats present on site. There are no overriding reasons to approve the application proposals and therefore the development is deemed contrary to the Habitat Regulations and development plan policy relating to ecology.

No concerns are raised with regard to heritage, amenity, highway safety, trees, flood risk or drainage, contamination, loss of best or most versatile agricultural land and airport safeguarding or subject to conditions where appropriate.

In consideration of the benefits of the proposals limited weight is afforded to the economic benefits of the scheme with regards to the job creation through the construction period and the social benefits of the scheme which are the location of accommodation within the countryside.

Significant weight is afforded to the environmental benefits of the scheme which would be the sustainability credentials of the dwellings Passivhaus premium construction, the renewable energy generating solar panels and the positive contributions to biodiversity through planting and rewilding and the resulting net gain.

Overall, as highlighted above, although the environmental benefits are compelling, the benefits overall identified are not deemed to outweigh the combined harm to the visual qualities of the

OFFICIAL surrounding open countryside, the unsustainable location of the site, the harm to protected species and the in principle open countryside harm.

The application is subsequently recommended for refusal.

SUMMARY RECOMMENDATION

REFUSE

REASON FOR REFERRAL

This application is referred to the Northern Planning Committee because the site area is 3.6 hectares, in line with the terms of the Council’s Constitution.

DESCRIPTION OF SITE AND CONTEXT

The site comprises 3.6 hectares of land and buildings which form Dawsons Farm located within Bosley, to the northeast of Congleton. The farmstead is within an agricultural holding of around 36ha grazed by dairy cattle and accessed via a long track, (from the A54), which slopes upwards in a northerly direction leading to the brick farmhouse, brick barns and outbuildings and a range of modern agricultural buildings and sheds, totalling 9 buildings in all.

The existing farmhouse sits at the northern end of the site. It is a two-storey building with a brick exterior, although parts have been rendered, with a stone slate roof. There is a single storey pitched roof outbuilding on the rear elevation, with a lean-to on the west gable, with this having a corrugated sheet roof and an open porch on the front elevation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
23/1174M: Dawson Farm, BUXTON ROAD, BOSLEY, SK11 0PX: Demolition of existing agricultural buildings and dwellinghouse, and construction of new replacement dwellinghouse with associated renewables and landscaping for Mr Alan Budden, Eco Design ConsultantsMinutes 750 KB DownloadRead as text
PDF
Key Plans 23 1174MMinutes 11 MB Download

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. 23/1174M - Dawson Farm, BUXTON ROAD, BOSLEY, SK11 0PX: Demolition of existing agricultural buildings and dwellinghouse, and construction of new replacement dwellinghouse with associated renewables and landscaping for Mr Alan Budden, Eco Design ConsultantsThis decision
  2. 25/1197/FUL - DAWSON FARM BUXTON ROAD, BOSLEY, MACCLESFIELD, CHESHIRE EAST, SK11 0PX: Demolition of existing agricultural buildings and dwellinghouse, and construction of new replacement dwellinghouse with associated renewables and landscapingApproved
  3. 23/1174M - Dawson Farm, BUXTON ROAD, BOSLEYRefused

More from Cheshire East Northern Planning Committee

All decisions
MeetingDecisionOutcome
19 Aug 2026 Minutes of the Previous MeetingThat the minutes of the meeting held on 24 June 2026 be approved as a correct record. Approved Open
19 Aug 2026 25/2053/FUL - Land Of The Former Knowle House, Sagars Road, Handforth, SK9 3EAThat for the reasons set out in the report the application be APPROVED subject to a Section 106 Agreement to secure t... Approved Open
19 Aug 2026 26/0581/FUL - The Cave, 91 - 95 Mill Street, Macclesfield, SK11 6NNThat the application be REFUSED as detailed in the Officer recommendation for the following reasons; 1. The proposals... Refused Open
19 Aug 2026 25/4532/FUL - LAST ORDERS, 116 - 118 Park Lane, Macclesfield, Cheshire East, SK11 6UAThat the application be delegated back to Officers to REFUSE the application for the following reason; 1. The submitt... Refused Open
19 Aug 2026 Tree Preservation Order 2026 - Alderley Edge - Brocklands, Brook LaneThat the Tree Preservation Order at Brocklands , Brook Lane, Alderley Edge be confirmed with no modifications. The Or... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies