RESOLVED That the following recommendations of the Executive Cabinet be approved, (a) to note the provisional outturn of the 2005/06 Capital Programme; (b) to approve the reduced Capital Programme for 2006/07, totalling £12,160,320, as presented in Appendix 3 to the submitted report, and the financing arrangements therefore; (c) to approve the reduction of the Housing Revenue Account budget for 2006/07 by £264,330, as a result of the overspend in 2005/06; (d) to approve the following recommendations of the Capital Programme Board: New Capital Schemes and Projects (e) That the following new schemes be placed on the reserve list (Category C) for future consideration when resources become available: 1. Integration software 2. Union Street/Market Street/St Thomas’s Road Mini Roundabouts and zebra crossings 3. APP/Civica Housing Assessment Module (f) That the following new schemes be placed in Category B of the 2006/07 Capital Programme: 1. Euxton Villa Football Club 2. Music Café Project 3. Gillibrand Street Site Assembly 4. Affordable Housing Project 5. Website Refresh 6. Migration to OS Master Map 7. eDevelopment and Building Control Project 8. Pedestrian improvements to Southport Road and St Thomas’s Road 9. Section 106 Funded - Various Highway Improvements linked to Gillibrand Estate and Southlands High School 10. Various Traffic Calming/Local Road Safety Schemes 11. Litter/Dog Waste/On-street recycling bins
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
1. To report to members the provisional outturn figures for the Council’s Capital budget for the financial year 2005/06.
2. To update members of the progress of the 2006/07 Capital Programme and also to outline the progress made by the Capital Programme Board.
3. To seek member approval and support for a number of recommendations from the Capital Programme Board.
CORPORATE PRIORITIES
4. The schemes within the Capital Programme contribute to the achievement of all the Council’s corporate priorities.
RISK ISSUES
5. The issue raised and recommendations made in this report involve risk considerations in the following categories:
Strategy Information Reputation Regulatory/Legal Financial Operational People Other
6. The Capital Programme sets out the Council’s strategic investment plans and if these are not delivered it will not fully achieve its strategic objectives, running the risk of damaging the Council’s reputation.
7. The Capital Programme also carries a significant financial risk. This is in terms of ensuring value for money, maximising resources available, and managing the performance to ensure that the impact on the General Fund or HRA revenue budgets is affordable. There may be an adverse impact on revenue budgets if capital expenditure exceeds the approved total to a significant degree, or estimated capital receipts or external contributions are not achieved in full. Should unplanned borrowing be required to meet a resource shortfall, there would be a cost to revenue in subsequent years.
ADMINREP/REPORT BACKGROUND
8. During the financial year the Executive Cabinet received regular monitoring reports forecasting the likely Capital Programme outturn for 2005/06. This final monitoring report for 2005/06 indicates an in year overspend of £489,114 (General Fund schemes £254,169; Housing Revenue Account schemes £234,945).
9. The figures outlined in the report are provisional and are subject to final checking and external audit. However it is not expected that these figures will change significantly, if at all. If subsequently any material differences arise these will be reported back to members.
Capital Outturn 2005/06
10. The original Capital Programme for 2005/06 allowed for expenditure of £7,854,000 including both the General Fund and Housing Revenue Account Category A and B schemes. Subsequently budget holders identified delays to the completion of some schemes and slippage to 2006/07 plus supplementary schemes were approved, leaving an approved capital programme of £10,541,950.
11. The provisional outturn of 11,031,064 is £489,114 more than the approved programme. Attached in Appendix 1 is a detailed analysis of the provisional outturn against the approved programme. This appendix also presents the proposed financing of the 2005/06 Capital Programme. Despite the overspending on General Fund schemes, it should be possible to finance that programme without use of borrowing in 2005/06. However, there will be a knock-on effect of the overspending, because capital receipts that could have been used in future years instead of borrowing will be used in 2005/06. The prudential borrowing of £269,389 indicated in Appendix 1 is in respect of Housing Revenue Account capital schemes. Though the balance in-hand at 31 March 2006 of capital receipts restricted to housing purposes exceeds the borrowing, these capital receipts are required in future years for budgeted purposes.
12. Whilst there were some minor under spends in completed schemes, there were also some overspends, some of which are within acceptable tolerances, others which were more significant, namely:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.