Executive Cabinet, Thursday 11 June 2026 at 6.30pm

Capital and Balance Sheet Outturn 2025-26

Approved Executive 3 papers

AI summaryChorley Cabinet approved the revised 2025/26 capital programme of £10.134m, a net decrease of £5.022m since the previous quarter, with £5.137m of spending slipped into future years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNet decrease of £5.022m from previous report
Money£10.134m revised programmeDown from £15.159m at Quarter 3
What happens nextNot stated
Who it affectsCapital schemes across the boroughIncluding housing, leisure, fleet and ICT

What was decided

Cabinet approved the revised capital programme, which includes an amendment of £5.958m to the programme as set out in Table 1. Report P3

Cabinet noted the variations to the programme, which are set out by scheme in Appendix B. Report P4

Cabinet noted the Balance Sheet position at 31 March 2026, covering cash, investment and loan balances, and debtors. Report P5

Why

To ensure the Council's capital programme is monitored effectively, as required by the quarterly reporting duty. Report P6, P8

Several schemes needed re-profiling or rephasing of budgets between 2025/26 and future years. Report P13, P18

The change reflects variations approved since the previous monitoring report and re-profiling within the existing programme. Report P15, P16

What happens next

Budgets totalling £5.137m will be re-profiled from 2025/26 into future years, with future-year budgets increased by £5.846m in net terms. Report P17, P18

Treasury management activity will continue to be reviewed with the Council's independent consultants MUFG Corporate Markets. Report P50

The decision takes effect five working days after publication, subject to call-in under the Council's Constitution. Report P72

The money

  • £5.958m Amendment to the capital programme Report P3
  • £10.134m Total revised capital programme at 31 March 2026 Report P12, P15
  • £15.159m Capital programme at Quarter 3 before this revision Report P15
  • £5.022m Net decrease in the 2025/26 programme Report P16
  • £0.112m Net increase in 2025/26 budget from variations since last report Report P17
  • £5.846m Net increase in future years budget from variations since last report Report P17
  • £5.137m Budgets re-profiled from 2025/26 into future years Report P18
  • £10.137m Actual capital expenditure as at 31 March 2026 Report P18
  • £0.095m Overspend on debt interest payable compared to budget Report P51
  • £0.373m Underspend on interest receivable from cash investments Report P51
  • £0.034m Underspend on Minimum Revenue Provision Report P51
  • 3.75% Bank of England base rate at time of report Report P51

Options considered

  • Chosen: Report the outturn as required. It is a requirement to report quarterly on the capital and balance sheet budget monitoring Report P8

Implications

  • Financial: Capital spending of £10.137m was incurred in 2025/26 against a programme of £10.134m, with £5.137m of work slipped into future years. Report P12, P15, P18
  • Financial: Debt interest payable overspent by £0.095m and interest receivable underspent by £0.373m due to higher cash balances; MRP underspent by £0.034m. Report P51
  • Risk: Inflation pressures continue to be monitored on a project-by-project basis, and bad debt risk is mitigated by age-based provisioning. Report P62, P63
  • Equalities: Equality and diversity implications were considered within the budgets approved by Council in February 2025. Report P60
  • Climate: The report has no impact on climate change and environmental considerations are in place. Report P59
  • Legal: The Monitoring Officer notes there are no legal implications. Report P67

Who and where

  • Council taxpayers and business rate payers, whose debt collection performance is monitored in the report Report P54, P55, P56
  • Housing service users, including disabled residents benefiting from the Chorley Adaptation Grant Report P34
  • Users of leisure centres at All Seasons, Brinscall and Clayton Green, where £1.500m has been added in future years Report P35
  • Visitors to Astley Park and Astley Hall, with restoration and improvement budgets re-profiled Report P43, P44
  • Refugees being housed through the Properties for Refugees scheme, delayed into future years Report P37

Timeline

  • February 2025: Original capital budget of £46.838m set by Council Report P11
  • September 2025: Cabinet approved decrease of capital programme to £15.975m at quarter one Report P11
  • November 2025: Cabinet approved increase of capital programme to £17.582m Report P11
  • February 2026: Cabinet approved decrease of capital programme to £15.159m Report P11
  • 2 March 2026 and 14 April 2026: Variations approved by Council outside this Cabinet meeting Report P17
  • 31 March 2026: Year-end position: capital programme stands at £10.134m and actual spend is £10.137m Report P12, P15, P18
  • 11 June 2026: Executive Cabinet considered the outturn report Report P17
  • Five working days after publication: Decision takes effect, subject to call-in Report P72

Plain English for the jargon

  • DFG: Disabled Facilities Grant, now called the Chorley Adaptation Grant
  • MRP: Minimum Revenue Provision, a charge to revenue for the repayment of debt
  • CIL: Community Infrastructure Levy, paid by developers to fund local infrastructure
  • EV: Electric Vehicle, in the context of charging point budgets
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

To approve the revised capital programme, attached at Appendix A, which includes an amendment to the programme of £5.958m, as detailed at Table 1 of this report. 2. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report). 3. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances, and debtors, as at 31 March 2026
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Purpose of the report

1. To report the outturn financial position of the Council in respect of the capital programme as at 31 March 2026, highlighting key issues and explaining key variances, and to provide an overview of various elements of the Council’s Balance Sheet at 31 March 2026.

Recommendations to Executive Cabinet

2. To approve the revised capital programme, attached at Appendix A, which includes an amendment to the programme of £5.958m, as detailed at Table 1 of this report.

3. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report).

4. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances, and debtors, as at 31 March 2026.

Reasons for recommendations

5. To ensure the Council’s Capital Programme is monitored effectively.

Other options considered and rejected

6. None, it is a requirement to report quarterly on the Capital and Balance Sheet budget monitoring. Corporate priorities

7. The report relates to the following corporate priority: Housing where residents can live well A green and sustainable borough An enterprising economy with vibrant local centres in urban and rural areas Healthy, safe and engaged communities

Background to the report

8. The Capital Budget for 2025/26 was set at £46.838m by Council in February 2025. This was increased following approval of the 2024/25 outturn to £52.991m. Then decreased to £15.975m in quarter one following Cabinet approval in September 2025. In November 2025, Cabinet approved an increase of the Capital Programme to £17.582m. In February 2026, Cabinet approved a decrease of the Capital Programme to £15.159m.

9. Following the changed detailed in this report, the total programme now stands at £10.134m, the details of which are shown in Appendix B.

Section A: Capital Programme

Key Issues

10. The total cost of the Council’s capital investment programme for 2025/26 has decreased since the 2025/26 Quarter 3 report approved by Cabinet, from £15.159m to £10.134m as at 31 March 2026. The change reflects variations approved since the last report, along with those contained within this report. A summary of the total costs of the programme, and the funding of this, is detailed at Appendix A.

11. The breakdown of the net decrease in the 2025/26 programme of £5.022m is detailed in Appendix B. The net variation includes those variations approved since the previous monitoring report and variations in respect of the reprofiling of budgets within the existing programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital ProgrammeAppendix A 68 KB Download
PDF
Capital Scheme VariationsAppendix B 107 KB Download
PDF
Capital and Balance Sheet Outturn 2025-26Report 188 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 18 attended
AB
Councillor Alistair BradleyExecutive Leader, present
PW
Councillor Peter WilsonDeputy Leader, present
BM
Councillor Beverley MurrayCommittee Member, present
AH
Councillor Alex HiltonCommittee Member, present
MF
Councillor Margaret FranceCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present, as expected, virtual
CS
Chris SinnottOfficer, in attendance
RT
Rochelle TappingOfficer, expected
KL
Kay LoveladyOfficer, expected
TS
Tasneem SafdarOfficer, in attendance
NH
Neil HaltonOfficer, in attendance
CW
Caroline WolfendenOfficer, in attendance

All 18 on the meeting page

On this subject at Chorley

Search all
  1. Capital and Balance Sheet Outturn 2025-26This decision
  2. Capital and Balance Sheet Monitoring Report Q1Approved
  3. Capital and Balance Sheet Outturn 2025-26Noted
  4. Capital and Balance Sheet Monitoring Report Q3Noted
  5. Capital and Balance Sheet Monitoring Report Q2Noted
  6. Capital and Balance Sheet Monitoring Report Q1Approved

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. Noted Open