AI summaryChorley Cabinet approved the revised 2025/26 capital programme of £10.134m, a net decrease of £5.022m since the previous quarter, with £5.137m of spending slipped into future years.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedNet decrease of £5.022m from previous report
Money£10.134m revised programmeDown from £15.159m at Quarter 3
What happens nextNot stated
Who it affectsCapital schemes across the boroughIncluding housing, leisure, fleet and ICT
What was decided
Cabinet approved the revised capital programme, which includes an amendment of £5.958m to the programme as set out in Table 1. Report P3
Cabinet noted the variations to the programme, which are set out by scheme in Appendix B. Report P4
Cabinet noted the Balance Sheet position at 31 March 2026, covering cash, investment and loan balances, and debtors. Report P5
Why
To ensure the Council's capital programme is monitored effectively, as required by the quarterly reporting duty. Report P6, P8
Several schemes needed re-profiling or rephasing of budgets between 2025/26 and future years. Report P13, P18
The change reflects variations approved since the previous monitoring report and re-profiling within the existing programme. Report P15, P16
What happens next
Budgets totalling £5.137m will be re-profiled from 2025/26 into future years, with future-year budgets increased by £5.846m in net terms. Report P17, P18
Treasury management activity will continue to be reviewed with the Council's independent consultants MUFG Corporate Markets. Report P50
The decision takes effect five working days after publication, subject to call-in under the Council's Constitution. Report P72
The money
£5.958m Amendment to the capital programme Report P3
£10.134m Total revised capital programme at 31 March 2026 Report P12, P15
£15.159m Capital programme at Quarter 3 before this revision Report P15
£5.022m Net decrease in the 2025/26 programme Report P16
£0.112m Net increase in 2025/26 budget from variations since last report Report P17
£5.846m Net increase in future years budget from variations since last report Report P17
£5.137m Budgets re-profiled from 2025/26 into future years Report P18
£10.137m Actual capital expenditure as at 31 March 2026 Report P18
£0.095m Overspend on debt interest payable compared to budget Report P51
£0.373m Underspend on interest receivable from cash investments Report P51
£0.034m Underspend on Minimum Revenue Provision Report P51
3.75% Bank of England base rate at time of report Report P51
Options considered
Chosen: Report the outturn as required. It is a requirement to report quarterly on the capital and balance sheet budget monitoring Report P8
Implications
Financial: Capital spending of £10.137m was incurred in 2025/26 against a programme of £10.134m, with £5.137m of work slipped into future years. Report P12, P15, P18
Financial: Debt interest payable overspent by £0.095m and interest receivable underspent by £0.373m due to higher cash balances; MRP underspent by £0.034m. Report P51
Risk: Inflation pressures continue to be monitored on a project-by-project basis, and bad debt risk is mitigated by age-based provisioning. Report P62, P63
Equalities: Equality and diversity implications were considered within the budgets approved by Council in February 2025. Report P60
Climate: The report has no impact on climate change and environmental considerations are in place. Report P59
Legal: The Monitoring Officer notes there are no legal implications. Report P67
Who and where
Council taxpayers and business rate payers, whose debt collection performance is monitored in the report Report P54, P55, P56
Housing service users, including disabled residents benefiting from the Chorley Adaptation Grant Report P34
Users of leisure centres at All Seasons, Brinscall and Clayton Green, where £1.500m has been added in future years Report P35
Visitors to Astley Park and Astley Hall, with restoration and improvement budgets re-profiled Report P43, P44
Refugees being housed through the Properties for Refugees scheme, delayed into future years Report P37
Timeline
February 2025: Original capital budget of £46.838m set by Council Report P11
September 2025: Cabinet approved decrease of capital programme to £15.975m at quarter one Report P11
November 2025: Cabinet approved increase of capital programme to £17.582m Report P11
February 2026: Cabinet approved decrease of capital programme to £15.159m Report P11
2 March 2026 and 14 April 2026: Variations approved by Council outside this Cabinet meeting Report P17
31 March 2026: Year-end position: capital programme stands at £10.134m and actual spend is £10.137m Report P12, P15, P18
11 June 2026: Executive Cabinet considered the outturn report Report P17
Five working days after publication: Decision takes effect, subject to call-in Report P72
Plain English for the jargon
DFG: Disabled Facilities Grant, now called the Chorley Adaptation Grant
MRP: Minimum Revenue Provision, a charge to revenue for the repayment of debt
CIL: Community Infrastructure Levy, paid by developers to fund local infrastructure
EV: Electric Vehicle, in the context of charging point budgets
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
To approve the revised capital programme, attached at Appendix A, which includes an amendment to the programme of £5.958m, as detailed at Table 1 of this report. 2. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report). 3. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances, and debtors, as at 31 March 2026
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
1. To report the outturn financial position of the Council in respect of the capital programme as at 31 March 2026, highlighting key issues and explaining key variances, and to provide an overview of various elements of the Council’s Balance Sheet at 31 March 2026.
Recommendations to Executive Cabinet
2. To approve the revised capital programme, attached at Appendix A, which includes an amendment to the programme of £5.958m, as detailed at Table 1 of this report.
3. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report).
4. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances, and debtors, as at 31 March 2026.
Reasons for recommendations
5. To ensure the Council’s Capital Programme is monitored effectively.
Other options considered and rejected
6. None, it is a requirement to report quarterly on the Capital and Balance Sheet budget monitoring. Corporate priorities
7. The report relates to the following corporate priority: Housing where residents can live well A green and sustainable borough An enterprising economy with vibrant local centres in urban and rural areas Healthy, safe and engaged communities
Background to the report
8. The Capital Budget for 2025/26 was set at £46.838m by Council in February 2025. This was increased following approval of the 2024/25 outturn to £52.991m. Then decreased to £15.975m in quarter one following Cabinet approval in September 2025. In November 2025, Cabinet approved an increase of the Capital Programme to £17.582m. In February 2026, Cabinet approved a decrease of the Capital Programme to £15.159m.
9. Following the changed detailed in this report, the total programme now stands at £10.134m, the details of which are shown in Appendix B.
Section A: Capital Programme
Key Issues
10. The total cost of the Council’s capital investment programme for 2025/26 has decreased since the 2025/26 Quarter 3 report approved by Cabinet, from £15.159m to £10.134m as at 31 March 2026. The change reflects variations approved since the last report, along with those contained within this report. A summary of the total costs of the programme, and the funding of this, is detailed at Appendix A.
11. The breakdown of the net decrease in the 2025/26 programme of £5.022m is detailed in Appendix B. The net variation includes those variations approved since the previous monitoring report and variations in respect of the reprofiling of budgets within the existing programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.