Audit Committee (now Governance Committee), Thursday 18 January 2007 at 4.30pm

Interim Report on Internal Audit Activities as at 29th December 2006

Noted Finance 1 paper

Audit Committee (now Governance Committee) noted this item on Thursday 18 January 2007. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

RESOLVED – That the report be noted.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Audit Committee (now Governance Committee)

Purpose of report

1. To advise members of the work undertaken in respect of the Annual Internal Audit Plan during the third quarter of 2006/7 and to comment on the results.

2. To provide details of further reviews, investigations and other Internal Audit activities during the period.

CORPORATE PRIORITIES

3. As an independent assurance function, Internal Audit’s prime objective is to evaluate and report on the adequacy of the Council’s governance, risk management and internal control framework. In so doing, Internal Audit also contributes to the economic, efficient and effective use of resources.

4. The Internal Audit Service therefore makes a vital contribution to ensuring that the Council is a performing organisation.

RISK ISSUES

5. All Internal Audit activity is geared towards the identification and management of business risks.

Background

6. This is the second Interim Progress Report for the current financial year and covers the period between 8th September and 29th December 2006.

7. Appendix 1 to this report shows the overall progress made in relation to the 2006/7 Internal Audit Plan. The Audit Plan is firmly on course to be delivered and the remaining paragraphs summarise the main elements of the work undertaken since the last meeting.

Continued.... AUDIT REVIEWS

Management of Partnerships & Partnering Contracts

8. The draft report was presented to Strategy Group on 19/12/06. The report is now being finalised and there will be a presentation to members at the next meeting of the Audit Committee in March.

Business Continuity Management

9. Business Continuity Management (BCM) is an ongoing process of risk assessment and management which aims to ensure that the Council can continue to operate and deliver services if adverse events occur. Such events could include things like a serious fire, a terrorist incident or failure of the computer network.

10. The Council has operated Business Continuity Plans (BCP's) since 2002 and we found them to be fit for purpose. We did however recommend that they be tested more regularly to ensure that they remain up to date and would actually work in the event of a real emergency.

11. We also recommended that the BCM and BCP arrangements of out-sourced services be checked to ensure that they are also sound.

Project Management

12. Sound project management disciplines are key to the delivery of all the main service developments within the Council. Such developments include important capital projects and the key business projects in the Corporate Strategy.

13. We found that the Council's project management arrangements are strong, and include a standard methodology which meets the international standard ISO 10006:2997(E) and has also been adopted by the North-West Centre of Excellence as its preferred template.

14. In terms of potential improvements, we recommended that project management training is made compulsory for all officers working on project boards or acting as project managers. We also proposed that project boards should assume greater responsibility for scrutiny of capital projects as the Capital & Efficiencies Programme Board currently does this and it isn't resourced to scrutinise projects in detail.

Freedom of Information

15. As a public authority the Council is required to comply with the provisions of the Freedom of Information Act 2000 (FOIA) in conducting its business activities and in the management of its records. We undertook a review to assess the adequacy of the corporate arrangements, policies and procedures established to ensure compliance with the Act.

16. We concluded that the procedures in place ensure that the Council is generally compliant with the Act. Also that staff are aware of the FOIA and the need to respond to requests for information from the public within the statutory deadlines.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Interim Report on Internal Audit Activities as at 29th December 2006Report 415 KB DownloadRead as text

At this meeting

Whole meeting
2MinutesOn the agenda 4Financial Statements MemorandumNoted
5Interim Report on Internal Audit Activities as at 29th December 2006This decision
6Training Presentation - Partnerships & Partnering ContractsNoted

Who was there

4 of 13 attended
JG
John Gerald WilsonChair, present
AG
Anthony GeeVice-Chair, present
MC
Magda Cullens (profile used as a Councillor)Committee Member, apologies
KI
Councillor Keith IddonCommittee Member, apologies
GR
Geoffrey RussellCommittee Member, present
SS
Councillor Shaun SmithCommittee Member, apologies
JS
Joyce SnapeCommittee Member, apologies
MW
Councillor Mary Wilson (passed away 7 April 2008)Committee Member, present
DH
Donna Hall CBEOfficer, in attendance
GH
Gary HallOfficer, in attendance
GB
Garry BarclayOfficer, in attendance
AA
Andy ArmstrongOfficer, in attendance

All 13 on the meeting page

On this subject at Chorley

Search all
  1. Interim Report on Internal Audit Activities as at 29th December 2006This decision
  2. Internal Audit Interim ReportNoted
  3. Internal Audit Interim ReportNoted
  4. Internal Audit Interim Report as at 30th September 2022Noted
  5. Internal Audit Interim Report as at 31st December 2021Noted
  6. Internal Audit Interim Report as at 29 October 2021Noted

More from Chorley Audit Committee (now Governance Committee)

All decisions
MeetingDecisionOutcome
15 Mar 2012 Internal Audit Plan 2012 -13RESOLVED – That the report be noted. Noted Open
15 Mar 2012 Anti Fraud Corruption PoliciesRESOLVED – 1. That the report be noted. 2. That the Chair of Audit Committee write to all Members of the Council to e... Noted Open
15 Mar 2012 Audit Committee Update 2011/12RESOLVED – That the report be noted. Noted Open
15 Mar 2012 Strategic risk update reportRESOLVED – That the report be noted. Noted Open
19 Jan 2012 Annual Audit Letter 2010/11RESOLVED – That the Audit Letter for 2010/11, as presented by the Audit Commission, be noted. Noted Open