Decision made: That the draft Capital Programme for 2008/9 to 2010/11, as now presented, be approved for consultation purposes. Reason for decision: Approval of the proposed three year Capital Programme will allow all representations received to be evaluated before formal decisions are made. Alternative option(s) considered and rejected: None.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
2. That the draft programme be approved for consultation.
EXECUTIVE SUMMARY OF REPORT 3. The Council’s Capital Programme is fundamental to delivering some of the key objectives contained in the Corporate Strategy. However any programme has to be affordable and be based upon prudence. The Executive has sought this year to focus on key priorities rather than pepper potting resources in order that the achievement of targets and measures is resourced but also that the spending has impact.
4. The Executive’s ambition was to contain borrowing costs, as the revenue position required significant savings to be made in 2008/09 and additional borrowing would add to that burden. Additionally the Executive wanted to focus on the key priorities of in particular:
● Affordable Housing ● The Town Centre
5. Consequently the draft programme is framed around the priorities with lessor allocations being made in other areas. That said the programme as it is currently drafted also allows development in other key areas for the Council.
REASONS FOR RECOMMENDATION(S) (If the recommendations are accepted)
6. The Council needs to review its medium term capital investment requirements in the contexts of the investment that is required to achieve its strategic objectives and to consider affordability.
Updated Template September 2007 ALTERNATIVE OPTIONS CONSIDERED AND REJECTED
7. None.
CORPORATE PRIORITIES
8. This report relates to the following Strategic Objectives:
Put Chorley at the heart of regional Improved access to public services economic development in the 9 9 central Lancashire sub region Improving equality of opportunity Develop the character and feel of 9 and life chance Chorley as a good place to live Involving People in their Ensure Chorley is a performing 9 Communities Organisation
Background
9. The Capital Programme sets out the Council’s Strategic Investment Plans, and if these are not delivered it may not achieve in full its strategic objectives. The Capital Programme also carries financial risk. This is in terms of ensuring Value for Money, maximising resources available, and managing performance to ensure the least possible impact on the revenue account.
10. In order to construct a 3 Year Programme from 2008/09 onward assumptions have had to be made regarding the likely resource position. The reason for this is that firstly the Council is awaiting confirmation of grant allocations and secondly a programme of asset disposal will occur over the period and the sale proceeds can only be estimated at this stage. Should the resources not be received as estimated, some of the schemes within the programme may need to be re-phased or the level of external borrowing will need to rise.
11. Set out in the table below is a summary of the estimated resource position for 2008/09 – 2010/11.
Table 1 – Estimated resource position
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.