Resolved
That the minutes of the Executive Cabinet meeting held on 15 March 2018 be confirmed as a correct record for signature by the Executive Leader.
Executive Cabinet decided this item on Thursday 21 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the Executive Cabinet meeting held on 15 March 2018 be confirmed as a correct record for signature by the Executive Leader.
MINUTES OF EXECUTIVE CABINET
MEETING DATE Thursday, 15 March 2018
MEMBERS PRESENT: Councillor (Chair), Councillor (Vice-Chair) and Councillors Alistair Bradley, Peter Wilson, Beverley Murray, Paul Walmsley, Adrian Lowe and Graham Dunn
OFFICERS: Gary Hall (Chief Executive), Chris Sinnott (Director (Early Intervention and Support)), Asim Khan (Director (Customer and Digital)), Mark Lester (Director (Business, Economic and Growth)), Chris Moister (Head of Legal, Democratic & HR Services), Angela Barrago (Health and Wellbeing Manager), Dianne Scambler (Democratic and Member Services Officer) and Riley (Communications)
APOLOGIES: None.
OTHER MEMBERS: Councillor Aaron Beaver, Gordon France, Margaret France, Danny Gee, Tom Gray, Marion Lowe, Matthew Lynch, June Molyneaux, Alistair Morwood, Alan Cullens and John Walker
18.EC.20 Minutes of meeting Thursday, 15 February 2018 of Executive Cabinet
Decision: That the minutes of the Executive Cabinet meeting held on 15 February 2018 be confirmed as a correct record for signing by the Executive Leader.
18.EC.21 Declarations of Any Interests
There were no declarations of any interests.
18.EC.22 Public Questions
There were no public questions received.
18.EC.23 Coronation Recreation Ground Phase 2 Approval and Phase 1 Update
The Executive Leader presented the report of the Director (Business, Development and Growth) that sought approval for the tender process for Phase two works at Coronation and Harpers Recreation Grounds. The report also provided an update on the Phase one tender process.
Executive Cabinet Thursday, 15 March 2018 Following Executive Cabinet approval in November 2017 it was agreed that £449,000 be allocated to Coronation Recreation Ground and £207,000 be allocated to Harpers Lane Recreation Ground, funded by existing Council reserves and capital receipts, already committed to play and open development, along with S106 developer contributions and external funding bids.
As the total value for the phase 2 procurement was unknown owing to the tendering of phase 1, the procurement approach of phase 2 was agreed to be determined by Executive Cabinet once grant funding had been confirmed and the total cost of phase 1 was fixed.
Funding bids have been successful, providing £88,000 towards the project at Coronation Recreation Ground and the pre-tender estimate for delivery of phase 1 on both sites was £150,000 which will carry out essential maintenance works that have been agreed through member engagement. The appointed contractor following tender evaluation quoted £162,000 (including contingency) resulting in budgets needing to be realigned.
Phase 2 works at Coronation Recreation Ground will consist of a play area for 2-8 ages to the value of £150,000 an a MUGA, fitness zone and play equipment for 8+ to a contract value of £170,000. It was proposed to tender the two Design and Build contracts separately that would run concurrently. The Council’s procurement team have been engaged in this decision and endorsed the approach being taken.
It was noted that the provision of CCTV was planned for the next phase, although the Leader informed the meeting that they would try to bring his forward to afford protection of the newly installed equipment.
Decision: Approval granted for: 1. The procurement approach for phase two at Coronation Recreation Ground. 2. Delegated Authority to the Executive Leader and Executive Member (Economic Development and Public Service Reform) for the awarding of the phase two contract. 3. Submission of a funding bid to Fields in Trust for £5k active Spaces Funding for the provision of finance to deliver structured sessions to engage the community to use the new facilities at Harpers Lane Recreational Ground.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of meeting Thursday, 15 March 2018 of Executive CabinetMinutes | 105 KB | DownloadRead as text |
Follow Executive Cabinet at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... | Decided | Open |
| 17 Sep 2026 | Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. | Approved | Open |
| 17 Sep 2026 | Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... | Noted | Open |
| 17 Sep 2026 | Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... | Approved | Open |
| 17 Sep 2026 | Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.