Provisional Revenue and Capital Outturn 2017/18

Noted Executive 6 papers

Executive Cabinet noted this item on Thursday 21 June 2018. Below is the council's own wording, with the papers it was decided on.

Item18.EC.34

Resolved

To note the full year outturn position for the 2017/18 revenue budget and capital investment programme. 2. To note the use of the £2.2m Southport Road capital receipt, as outlined in paragraph 34, to pay off the borrowing used to fund assets with short useful lives and instead use prudential borrowing to fund the purchase of the Oak House. The outcome being a £176k saving to the council’s revenue budget. 3. To approve slippage requests outlined in Appendix 2 of the report to finance expenditure on specific items or projects in 2018/19. 4. Request Council approval for the contribution of £300,000 from in-year revenue underspends to the Change Management Reserve to finance one-off redundancy and pension strain costs arising from transformation and shared service strategies. 5. Request Council approval for the contribution of £100,000 from in-year revenue underspends to the Asset Maintenance Reserve to finance one-off costs relating to the Council’s maintenance of offices and buildings. 6. Request Council approval for the contribution of £156,835 from in-year revenue underspends to the Business Rates Retention Equalisation Reserve. 7. To note the 2017/18 outturn position on the Council's reserves outlined in Appendix 4. 8. To note the impact of the final capital expenditure outturn and the re-phasing of capital budgets to 2018/19 and approve the additions to the capital programme outlined in paragraph 72. 9. Request Council approval of the financing of the 2017/18 capital programme to maximise the use of funding resources available to the Council. 1. To note the full year outturn position for the 2017/18 revenue budget and capital investment programme. 2. To note the use of the £2.2m Southport Road capital receipt, as outlined in paragraph 34, to pay off the borrowing used to fund assets with short useful lives and instead use prudential borrowing to fund the purchase of the Oak House. The outcome being a £176k saving to the council’s revenue budget. 3. To approve slippage requests outlined in Appendix 2 of the report to finance expenditure on specific items or projects in 2018/19. 4. Request Council approval for the contribution of £300,000 from in-year revenue underspends to the Change Management Reserve to finance one-off redundancy and pension strain costs arising from transformation and shared service strategies. 5. Request Council approval for the contribution of £100,000 from in-year revenue underspends to the Asset Maintenance Reserve to finance one-off costs relating to the Council’s maintenance of offices and buildings. 6. Request Council approval for the contribution of £156,835 from in-year revenue underspends to the Business Rates Retention Equalisation Reserve. 7. To note the 2017/18 outturn position on the Council's reserves outlined in Appendix 4. 8. To note the impact of the final capital expenditure outturn and the re-phasing of ... view the full minutes text for item 18.EC.34
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Report of Meeting Date Chief Finance Officer (Introduced by the Executive Executive Cabinet 21 June 2018 Member for Resources)

PROVISIONAL REVENUE AND CAPITAL OUTTURN 2017/18

PURPOSE OF REPORT 1. To present the provisional revenue outturn figures for the Council as compared against the budgets and efficiency savings targets set for the financial year 2017/18.

2. To present the provisional outturn figures for the 2017/18 capital programme and update the capital programme for financial years 2018/19 to 2020/21 to take account of the re-phasing of expenditure from 2017/18 and other proposed budget changes.

3. The accounts are provisional at this stage and are also subject to final checking and scrutiny by the Council’s external auditor. Should there be any significant changes to the outturn as a result of this process a further report will be submitted to Executive Cabinet.

RECOMMENDATION(S) 4. Note the full year outturn position for the 2017/18 revenue budget and capital investment programme.

5. Note the use of the £2.2m Southport Road capital receipt, as outlined in paragraph 34, to pay off the borrowing used to fund assets with short useful lives and instead use prudential borrowing to fund the purchase of the Oak House. The outcome being a £176k saving to the council’s revenue budget.

6. Request Executive Cabinet approval for slippage requests outlined in Appendix 2 of the report to finance expenditure on specific items or projects in 2018/19.

7. Request Council approval for the contribution of £300,000 from in-year revenue underspends to the Change Management Reserve to finance one-off redundancy and pension strain costs arising from transformation and shared service strategies.

8. Request Council approval for the contribution of £100,000 from in-year revenue underspends to the Asset Maintenance Reserve to finance one-off costs relating to the Council’s maintenance of offices and buildings.

9. Request Council approval for the contribution of £156,835 from in-year revenue underspends to the Business Rates Retention Equalisation Reserve.

10. Note the 2017/18 outturn position on the Council's reserves outlined in Appendix 4.

11. Note the impact of the final capital expenditure outturn and the re-phasing of capital budgets to 2018/19 and approve the additions to the capital programme outlined in paragraph 72.

12. Request Council approval of the financing of the 2017/18 capital programme to maximise the use of funding resources available to the Council. EXECUTIVE SUMMARY OF REPORT

13. There is a provisional underspend against the budget at year-end of £715k (as detailed in Appendix 1) prior to requests for slippage of committed items of £105k.

14. The provisional underspend excludes any variation to projected expenditure on investment items included in the budget in 2017/18. Details of the balances remaining at year end are shown in Appendix 3 and will be transferred into specific reserves and matched to expenditure in future years.

15. In the 2017/18 budget the expected net income from Market Walk after deducting financing costs is £0.998m. The final outturn position shows an overspend of £3k but this includes £120k of revenue expenditure relating to the Market Walk Extension project including £70k cost of the temporary parking arrangements at the Flat Iron Car Park.

16. The capital outturn expenditure for 2017/18 is £11.391m.

17. The Council’s Medium Term Financial Strategy proposed that working balances are to reach £4.0m over the 3 year lifespan of the MTFS to 2018/19 due to the financial risks facing the Council. A budgeted contribution into General Balances of £500k was contained within the budget for 2017/18. Should the recommendations in this report be accepted, the level of balances at 31 March 2018 will be £4.0m and the target achieved a year early.

Confidential report Yes No Please bold as appropriate

Key Decision? Yes No Please bold as appropriate

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
General Fund SummaryAppendix 1 56 KB Download
PDF
Transfers to ReservesAppendix 2 55 KB Download
PDF
Investment BudgetsAppendix 3 89 KB Download
PDF
Analysis of Reserves & ProvisionsAppendix 4 60 KB Download
PDF
Capital ProgrammeAppendix 5 52 KB Download
PDF
Provisional Revenue and Capital Outturn 2017/18Report 283 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 25 attended
AB
Councillor Alistair BradleyExecutive Leader, present
PW
Councillor Peter WilsonDeputy Leader, apologies
BM
Councillor Beverley MurrayCommittee Member, present
JF
Councillor Jane FitzsimonsCommittee Member, present
PW
Councillor Paul WalmsleyCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present
GH
Gary HallOfficer, in attendance
CS
Chris SinnottOfficer, expected
AK
Asim KhanOfficer, in attendance
ML
Mark LesterOfficer, in attendance
RH
Rebecca HuddlestonOfficer, expected
CM
Chris MoisterOfficer, in attendance

All 25 on the meeting page

On this subject at Chorley

Search all
  1. Provisional Revenue and Capital Outturn 2017/18This decision
  2. Provisional Revenue and Capital Outturn 2019/20Noted
  3. Provisional Revenue and Capital Outturn 2018/19Noted
  4. Provisional Revenue and Capital Outturn 2016/17Approved
  5. Provisional Revenue and Capital Outturn 2016/17Approved
  6. Revenue and Capital Budget Monitoring - Provisional Outturn 2015-16Approved

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies