Chorley Borough Council
Executive Cabinet, Thursday 10 November 2022 at 6.30pm

2022/23 Corporate Capital Programme and Balance Sheet Monitoring Report Position at 30th September 2022

Approved Executive 3 papers

Executive Cabinet approved this item on Thursday 10 November 2022. Below is the council's own wording, with the papers it was decided on.

Item22.EC.36

Resolved

To approve the revised capital programme as attached at Appendix A, which includes an amendment to the programme of £23k, as detailed at point 11 of the report. 2. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report); 3. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances and debtors, at 30 September 2022.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Purpose of the report

1. To report the financial position of the Council in respect of the capital programme at 30th September 2022, highlighting key issues and explaining key variances, and to provide an overview of various elements of the Council’s Balance Sheet at 30th September 2022.

Recommendations to Executive Cabinet

2. To approve the revised capital programme as attached at Appendix A, which includes an amendment to the programme of £23k, as detailed at point 11 of this report.

3. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report);

4. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances and debtors, at 30th September 2022.

Reasons for recommendations

5. To ensure the Council’s Capital Programme is monitored effectively.

Other options considered and rejected

6. None

Corporate priorities

7. The report relates to the following corporate priorities: Involving residents in improving their A strong local economy local area and equality of access for all

Clean, safe and healthy communities An ambitious council that does more to meet the needs of residents and the local area

Background to the report

8. The capital budget for 2022/23 was set at £24.2m at Council in February 2022. This was increased following approval of the 2021/22 outturn to £32.2m, then further amended in the Capital Monitoring Report as at 31st July 2022 to £27.6m.

9. Following the changes detailed in this report, the total programme now stands at £25.5m, the detail of which is shown in Appendix B.

Section A: Capital Programme

Key issues

10. The total cost of the Council’s capital investment programme for 2022/23 has decreased since the 2021/22 outturn report approved by Cabinet, from £27.6m to £25.5m as at 30th September 2022. The change reflects variations approved since the last monitoring report, along with those contained within this report. A summary of the total costs of the programme, and the funding of this, is detailed at Appendix A.

11. The breakdown of the net decrease in the programme of £2.1m is detailed in Appendix B. The net variation includes those variations approved since the previous monitoring report and variations in respect of the reprofiling of budgets within the existing programme

12. The report contains a request to increase the capital programme by £0.023m as below. Table 1: Budget changes Increase / Increase / (Reduction) (Reduction) 2023/24 Date Scheme 2022/23 and future Approved by approved years £’000 £’000 Clean, safe and healthy homes and communities Play, Recreation and Open Approval Space Projects -Westway 23 requested in Nature Reserve (see point 19) this report TOTAL 23

13. A re-profiling of budgets from 2022/23 to future years has been undertaken. The total movement of budgets from 2022/23 amounts to £2.1m. The movements are shown in Appendix B and explanations are contained in the major variations section of the report that follows.

Table 2: Slippage and reprofiling across years

Scheme Slippage and Reprofiling £'000 Chapel Street and surrounding public 1,000 realm Bengal Street 1,100 Total 2,100

14. As at 30th September the actual capital expenditure across the programme was £6.486m, which represents 25% of the forecast programme spend as at 30th September.

Major variations in the 2022/23 Capital Programme since the previous report

A strong local economy

15. Alker Lane Development – The business and industrial hub is due to complete and become operational within the next month.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2022/23 Corporate Capital Programme and Balance Sheet Monitoring Report Position at 30th September 2022Report 270 KB DownloadRead as text
PDF
Appendix AAppendix A 140 KB Download
PDF
Appendix BAppendix B 174 KB Download

At this meeting

Whole meeting

Who was there

5 of 43 attended
AB
Councillor Alistair BradleyExecutive Leader, present
PW
Councillor Peter WilsonDeputy Leader, present
BM
Councillor Beverley MurrayCommittee Member, apologies
TH
Councillor Terry HowarthCommittee Member, present
AM
Councillor Alistair MorwoodCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present
GH
Gary HallOfficer, expected
CS
Chris SinnottOfficer, in attendance
AK
Asim KhanOfficer, in attendance
ML
Mark LesterOfficer, expected
DW
Dave WhelanOfficer, in attendance
CM
Chris MoisterOfficer, expected

All 43 on the meeting page

On this subject at Chorley

Search all
  1. 2022/23 Corporate Capital Programme and Balance Sheet Monitoring Report Position at 30th September 2022This decision
  2. 2024/25 Corporate Capital Programme and Balance Sheet Monitoring Report Outturn Position as at 30th September 2024Approved
  3. 2024/25 Corporate Capital Programme and Balance Sheet Monitoring Report Outturn Position for the four months to the 31st July 2024Approved

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies