That Members agree to the procurement with South Ribble Council and Blackburn with Darwen Council, being a collaborative exercise. 2. To delegate authority to the Executive Member (Resources) to agree the route to contract ( eg full tender, framework) and to agree the scoring methodology and scoring matrix. 1. That Members agree to the procurement with South Ribble Council and Blackburn with Darwen Council, being a collaborative exercise. 2. To delegate authority to the Executive Member (Resources) to agree the route to contract ( eg full tender, framework) and to agree the scoring methodology and scoring matrix. Reasons for recommendations The procurement will result in a separate contract for each council’s valuation requirement, however running the procurement process together will create efficiencies in officer time and cost. Other options considered and rejected Tendering for this procurement without the benefit of the joint exercise would lead to additional officer resource to deliver the tender, for the same or less competitive results.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
1. To seek Member approval to engage in a joint procurement exercise with South Ribble Council and Blackburn with Darwen Council to procure property valuation services for assets within the Council’s portfolio.
Recommendations to Executive Cabinet
2. That Members agree to the procurement with South Ribble Council and Blackburn with Darwen Council, being a collaborative exercise.
3. To delegate authority to the Executive Member (Resources) to agree the route to contract (eg full tender, framework) and to agree the scoring methodology and scoring matrix.
Reasons for recommendations
4. The procurement will result in a separate contract for each council’s valuation requirement, however running the procurement process together will create efficiencies in officer time and cost.
5. Working with Blackburn with Darwen will provide access to greater resource capacity in procurement than we currently have in-house.
Other options considered and rejected
6. Tendering for this procurement without the benefit of the joint exercise would lead to additional officer resource to deliver the tender, for the same or less competitive results. Corporate priorities
7. The report relates to the following corporate priorities:
Housing where residents can live well A green and sustainable borough
An enterprising economy with vibrant Healthy, safe and engaged communities local centres in urban and rural areas
Background to the report
8. Member approval is being sought to undertake a procurement exercise with South Ribble and Blackburn with Darwen Councils for the renewal of the property valuation services.
9. The current contract is for a twelve month period and will expire in December 2024. New arrangements will be contracted under a longer term agreement to create more interest and competition in the procurement exercise, and to achieve preferential pricing.
10. The tender exercise will be undertaken in compliance with Contract Procedure Rules and Procurement Guidance. Considering the annual cost of the valuations across the councils, and the multiple years the contract will run for, this will be a high value procurement.
Joint Procurement Exercise
11. As this is a would be a joint procurement exercise, details on the route to procurement, scoring methodology and scoring matrix cannot be included at this stage.
12. It is possible that a procurement framework, such as Crown Commercial Services may be used, or a full tender exercise undertaken.
13. Tender Evaluation Criteria and Weighting will be decided jointly between the councils involved in the exercise.
14. The points in paragraphs 12 and 13 will be considered and agreed by the Executive Member (Resources).
Climate change and air quality
15. The work noted in this report has an no impact on the Councils Carbon emissions and the wider Climate Emergency and sustainability targets of the Council.
Equality and diversity
16. Not Applicable.
Risk
17. Valuation of the councils’ assets is a statutory requirement for completion of the annual accounts and without the timely valuations provided by appropriately qualified surveyors the accounts could not be completed. Comments of the Statutory Finance Officer
18. There are no direct financial implications at this stage. As the procurement moves forward, the outcome will be reported through the relevant and required approval routes. There is an existing budget for this service and it is not anticipated there will be a significant increase in costs.
Comments of the Monitoring Officer
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.