To approve the revised capital programme as attached at Appendix A, which includes an amendment to the programme of £190k, as detailed at point 11 of this report. 2. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report ); 3. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances and debtors, at 30th September 2023. 1. To approve the revised capital programme as attached at Appendix A, which includes an amendment to the programme of £190k, as detailed at point 11 of this report. 2. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report ); 3. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances and debtors, at 30th September 2023. Reasons for recommendation To ensure the Council’s Capital Programme is monitored effectively. Other options considered and rejected None.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
1. To report the outturn financial position of the Council in respect of the capital programme at 30th September 2023, highlighting key issues and explaining key variances, and to provide an overview of various elements of the Council’s Balance Sheet at 30th September 2023.
Recommendations to Executive Cabinet
2. To approve the revised capital programme as attached at Appendix A, which includes an amendment to the programme of £190k, as detailed at point 11 of this report.
3. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report);
4. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances and debtors, at 30th September 2023.
Reasons for recommendations
5. To ensure the Council’s Capital Programme is monitored effectively.
Other options considered and rejected
6. None Corporate priorities
7. The report relates to the following corporate priorities:
An enterprising economy with vibrant Green and sustainable Borough local centres in urban and local areas
Housing where residents live well Healthy, safe and engaged communities
Background to the report
8. The capital budget for 2023/24 was set at £21.103m at Council in February 2023. This was increased following approval of the 2022/23 outturn to £22.998m, then further amended in the Capital Monitoring Report as at 31st July 2023 to £18.190m.
9. Following the changes detailed in this report, the total programme now stands at £13.930m, the details of which is shown in Appendix B.
Section A: Capital Programme
Key issues
10. The total cost of the Council’s capital investment programme for 2023/24 has decreased since the 2023/24 Quarter 1 report approved by Cabinet, from £18.190m to £13.930m as at 30th September 2023. The change reflects variations approved since the last report, along with those contained within this report. A summary of the total costs of the programme, and the funding of this, is detailed at Appendix A.
11. The breakdown of the net decrease in the programme of £4.260m is detailed in Appendix B. The net variation includes those variations approved since the previous monitoring report and variations in respect of the reprofiling of budgets within the existing programme
12. Budget variations approved since the last monitoring report have resulted in a total increase of £190k to the capital programme. The table below details the changes.
Table 1: Approved budget changes since the last monitoring report Increase / Increase / (Reduction) Virement (Reduction) Virement To Date ` 2024/25 and From Approved by 2023/24 approved future years £’000 £’000
Market Walk Extension (5) This report N/A Markets - Works to Existing Market 5 This report N/A Chorley Adaptation Grant (Formerly 77 This report N/A DFG) Play, Recreation and Open Space 73 Cabinet 20/03/23 Projects - Gillett Playing Fields Play, Recreation and Open Space 40 This report N/A Projects Wigan Road
TOTAL 190 - (5) 5 13. A re-profiling of budgets from 2023/24 to future years has been undertaken. The total movement of budgets from 2023/24 amounts to £4.450m. The movements are shown in Appendix B and explanations are contained in the major variations section that follows.
Table 2: Slippage and reprofiling across years
Scheme Slippage and Reprofiling £'000 Strawberry Meadows Development 752 Chorley Borough Service Centres 500 Market Walk Extension 70 Public Realm Town Centre 490 Town Hall and White Hart Works 200 Bengal Street 900 Town Hall Decarbonisation 1,538
Total 4,450
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.