Resolved
To approve the Housing Delivery Test Action Plan for publication on the Council’s website.
AI summaryChorley Council's Executive Cabinet approved the Housing Delivery Test Action Plan for publication after the 2023 measurement of 57% triggered all three national planning policy requirements.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
To approve the Housing Delivery Test Action Plan for publication on the Council’s website.
1. To set out the Housing Delivery Test 2023 results and the Action Plan that has been prepared as required by national planning policy.
Recommendations to Executive Cabinet
2. Approve the Housing Delivery Test Action Plan for publication on the Council’s website.
3. The National Planning Policy Framework (NPPF) requires local authorities to publish a Housing Delivery Test Action Plan when the latest published measurement falls below 95%.
Other options considered and rejected
4. None, the requirements for the Housing Delivery Test are set out in national planning policy.
Corporate priorities
5. The report relates to the following corporate priority: Housing where residents can live well Background to the report
6. The Housing Delivery Test (HDT) was introduced in 2018 and is an annual measurement of housing delivery against the number of homes that are required for the preceding three years. The National Planning Policy Framework (NPPF) sets out the following HDT requirements:
• Where the HDT falls below 95%, the requirement is to publish an action plan. • Where the HDT falls below 85%, a 20% buffer must be applied to the authority’s five year land supply. • Where the HDT falls below 75%, the presumption in favour of sustainable development must be applied.
Latest HDT Results
7. The latest published HDT is the 2023 measurement, published in December 2024 which covers the financial years 2020/21, 2021/22 and 2022/23. The calculation is set out below.
Total net homes Total number of Housing Delivery Monitoring Period delivered homes required Test Measurement 2020/2021 286 379 - 2021/2022 228 537 - 2022/2023 312 542 - TOTAL 826 1,458 57%
8. As the result is below 75%, all three of the HDT requirements set out in the NPPF apply. This is the first time since the introduction of the HDT that the Council’s measurement has fallen below 95%.
9. The number of homes required is calculated using standard method, as the adopted requirement in the Central Lancashire Core Strategy is more than five years old. The government applied a discount to the number of homes required in 2020/21 due to the Covid 19 pandemic.
10. In addition to the preparation of the Action Plan, a 20% buffer has been applied to the latest five year housing land supply calculation. The presumption in favour of sustainable development also applies, this means that planning applications for housing development should be approved unless the adverse impacts would significantly and demonstrably outweigh the benefits of the development. However this has been the case already in Chorley for several years given the Council has not been able to demonstrate a five year supply of housing against the standard method.
11. It should be noted that the government is working to a delayed timetable for the publication of HDT measurements. They were originally published in November each year covering the preceding three financial years. The latest published HDT should therefore be the 2024 measurement. However, the Council are able to calculate what the 2024 measurement will be for Chorley and it will still be below 75% therefore the same requirements would apply.
HDT Action Plan
12. The HDT Action Plan is appended to this report. National Planning Practice Guidance (PPG) requires an action plan to identify the reasons for under-delivery, explore ways to reduce the risk of further under-delivery and set out measures the authority intends to take to improve levels of delivery.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
for Housing Delivery Test Action PlanAppendix 1 | 617 KB | Download |
PDF |
Housing Delivery Test Action PlanReport | 106 KB | DownloadRead as text |
Follow Executive Cabinet at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... | Decided | Open |
| 17 Sep 2026 | Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. | Approved | Open |
| 17 Sep 2026 | Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... | Noted | Open |
| 17 Sep 2026 | Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... | Approved | Open |
| 17 Sep 2026 | Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.