Capital and Balance Sheet Monitoring Report Q2

Noted Executive 3 papers

AI summaryChorley Cabinet approves £1.608m net increase to 2025/26 capital programme, now £17.582m, and notes balance sheet position at 30 September 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRevised programme and Table 1 changes endorsed
Money£17.582mTotal revised 2025/26 capital programme
What happens nextFive working days after publicationSubject to call-in under the Constitution
Who it affectsCapital programme and balance sheetPosition as at 30 September 2025

What was decided

Cabinet noted the revised Capital Programme, which includes an amendment of £4.977m since the September 2025 report, and approved the budget changes in Table 1. Report P3, P4

Cabinet noted the variations to the programme, detailed by scheme at Appendix B. Report P5

Cabinet noted the balance sheet position at 30 September 2025 in respect of cash, investment and loan balances, and debtors. Report P6

Why

To ensure the Council's Capital Programme is monitored effectively. Report P9

It is a requirement to report quarterly on capital and balance sheet budget monitoring. Report P11

What happens next

The Scrutiny Committee is asked to review the Capital Programme, balance sheet position and virements at Appendix B. Report P7, P8

The decision will come into force and may be implemented five working days after its publication date, subject to call-in. Report P68

The money

  • £4.977m Amendment to the capital programme since the September 2025 report Report P3
  • £17.582m Total 2025/26 capital programme after this report's changes Report P16, P19
  • £15.974m Capital programme at Q1 after Cabinet approval in September 2025 Report P15
  • £52.991m Capital programme increased following approval of 2025/26 outturn Report P15
  • £46.233m Original 2025/26 capital budget set by Council in February 2025 Report P15
  • £1.608m Net increase in 2025/26 capital programme Report P20
  • £3.515m Increase in 2025/26 capital programme from variations approved since previous report Report P21
  • £1.462m Increase in future years from variations approved since previous report Report P21
  • £1.907m Slippage and reprofiling of budgets from 2025/26 to future years Report P22
  • £1.332m Actual capital expenditure across the programme as at 30 September 2025 Report P24
  • £1.722m Slippage of Town Centre Wide Improvements into future years Report P27
  • £1.700m Yarrow Bridge Depot budget for refuse and food waste collection facilities Report P29
  • £0.498m DFG added to 2025/26 capital programme Report P30
  • £1.250m Early works decarbonisation programme at All Seasons Leisure centre Report P33
  • £43k Forecast underspend on interest compared to previous forecast Report P42
  • £35k Underspend on Minimum Revenue Provision budget Report P42
  • £425k Bad debt provision released back into Council funds Report P51

Options considered

  • Rejected: No alternative action. It is a requirement to report quarterly on the capital and balance sheet budget monitoring. Report P11

Implications

  • Financial: Capital programme for 2025/26 rises from £15.974m to £17.582m, with a net £1.608m increase, including a £1.907m slippage to future years. Report P16, P19, P20, P22
  • Financial: Total borrowing at 30 September 2025 stood at £78.878m, with cash balances of £12.650m and investments of £4.000m. Report P44
  • Financial: Council Tax and Business Rates collection rates are higher than at the same point in 2024/25. Report P47
  • Risk: Inflation, individual project costs and bad debt recovery remain areas to be closely monitored. Report P56, P57
  • Equalities: Equality and diversity implications are considered within the budgets approved by Council in February 2025. Report P55
  • Climate: The report has no impact on climate change and all environmental considerations are in place. Report P53

Who and where

  • Chorley Borough Council's capital programme and balance sheet Report P1, P16
  • Strawberry Meadows residents receiving compensation for development impacts Report P25
  • Users of Astley Hall, with essential roof repairs required after vandalism Report P35
  • Refuse and food waste collection services, supported by the Yarrow Bridge Depot budget Report P29
  • Users of All Seasons Leisure centre, with a decarbonisation early works programme Report P33

Timeline

  • February 2025: Council set the 2025/26 capital budget at £46.233m Report P15
  • Following 2025/26 outturn approval: Capital programme increased to £52.991m Report P15
  • September 2025: Cabinet approved Q1 report, with capital programme reduced to £15.974m Report P15
  • 30 September 2025: Balance sheet position reported, with actual capital expenditure of £1.332m Report P24, P44
  • 19 November 2025: Report dated Report P67
  • 27 November 2025: Executive Cabinet decision
  • Five working days after publication: Decision may be implemented, subject to call-in Report P68

Plain English for the jargon

  • MRP: Minimum Revenue Provision, an amount set aside to repay borrowing over time.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item47

Resolved

To note the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £4.977m since the last capital monitoring report was approved by Cabinet in September 2025, as detailed at Table 1 of the report. 2. To approve the budget changes in table 1 noted for the report. 3. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report). 4. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances, and debtors, as at 30 September 2025.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Purpose of the report

1. To report the outturn financial position of the Council in respect of the capital programme at 30 September 2025, highlighting key issues and explaining key variances, and to provide an overview of various elements of the Council’s Balance Sheet at 30 September 2025.

Recommendations to Executive Cabinet

2. To note the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £4.977m since the last capital monitoring report was approved by Cabinet in September 2025, as detailed at Table 1 of this report.

3. To approve the budget changes in table 1 noted for this report.

4. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report).

5. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances, and debtors, as at 30 September 2025.

Recommendations to Scrutiny

6. The Committee is asked to review the Capital Programme and the Balance Sheet, based on the position as at 30 September 2025 and to comment on the report. 7. The Committee is asked to review the virements made to the Capital Programme during the period, as detailed in Appendix B of the report. Reasons for recommendations

8. To ensure the Council’s Capital Programme is monitored effectively.

Other options considered and rejected

9. None, it is a requirement to report quarterly on the Capital and Balance Sheet budget monitoring.

Corporate priorities

10. The report relates to the following corporate priority: Housing where residents can live well A green and sustainable borough An enterprising economy with vibrant local centres in urban and rural areas Healthy, safe and engaged communities

Background to the report

11. The Capital Budget for 2025/26 was set at £46.233m by Council in February 2025. This was increased following approval of the 2025/26 outturn to £52.991m. Then decreased to £15.974 in quarter one following Cabinet approval in September 2025.

12. Following the changes detailed in this report, the total programme for 2025/26 now stands at £17.582m the details of which are shown in Appendix B.

Section A: Capital Programme

Key issues

13. The total cost of the Council’s capital investment programme for 2025/26 has increased since the last report from £15.974m to £17.582m. The change reflects variations approved since the last report, along with those contained within this report. A summary of the total costs of the programme, and the funding of this, is detailed at Appendix A.

14. The breakdown of the net increase in the programme of £1.608m in 2025/26 is detailed in Appendix B. The net variation includes those variations approved since the previous monitoring report and variations in respect of the reprofiling of budgets within the existing programme net increase.

15. Budget variations approved since the previous monitoring report are shown in the table below; there has been an increase in the 2025/26 capital programme of £3.515m and an increase in future years if £1.462m – this has been offset by the slippage detailed in Table 2. Virements between the schemes totals £0.041m. The table below details the changes.

16. A slippage and re-profiling of budgets from 2025/26 to future years has been undertaken. The total movement of budgets from 2025/26 amounts to £1.907m. The movements are shown in Appendix B and explanations are contained in the major variations section that follows.

Table 2: Slippage And Reprofiling Across Financial Years

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme 2025.26: Position at 30 September 2025Appendix A 68 KB Download
PDF
Capital Programme Scheme Variations at 30 September 2025Appendix B 95 KB Download
PDF
Capital and Balance Sheet Monitoring Report Q2Report 132 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 19 attended
AB
Councillor Alistair BradleyExecutive Leader, present
PW
Councillor Peter WilsonDeputy Leader, present
BM
Councillor Beverley MurrayCommittee Member, present
TH
Councillor Terry HowarthCommittee Member, present
AH
Councillor Alex HiltonCommittee Member, present
MF
Councillor Margaret FranceCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present
CS
Chris SinnottOfficer, in attendance
SB
Sarah BullockOfficer, in attendance, virtual
RT
Rochelle TappingOfficer, expected
TS
Tasneem SafdarOfficer, in attendance
NH
Neil HaltonOfficer, in attendance

All 19 on the meeting page

On this subject at Chorley

Search all
  1. Capital and Balance Sheet Monitoring Report Q2This decision
  2. Capital and Balance Sheet Monitoring Report Q1Approved
  3. Capital and Balance Sheet Outturn 2025-26Noted
  4. Capital and Balance Sheet Outturn 2025-26Approved
  5. Capital and Balance Sheet Monitoring Report Q3Noted
  6. Capital and Balance Sheet Monitoring Report Q1Approved

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. Noted Open