Astley Hall West Wing Renovations - Contractor Appointment

Approved Executive 2 papers

AI summaryChorley Executive Cabinet appoints Bullens Conservation Ltd to renovate Astley Hall West Wing under a £472,941.13 contract, and adds £155,000 to the capital scheme to cover costs and contingency.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedBullens Conservation Ltd to renovate Astley Hall West Wing
Money£472,941.13 inclusive of VATContract value plus £155,000 capital increase
What happens nextFive working day call-in periodDecision takes effect after publication unless called in
Who it affectsAstley Hall heritage buildingWest Wing repairs including timber frame, lime mortar, leadwork and windows

What was decided

Appoint Bullens Conservation Ltd under a JCT Minor Works Building Contract for £394,117.61 excluding VAT, £472,941.13 including VAT, to deliver the construction phase. Report P3

Increase the existing capital scheme budget by £155,000, including a 10% contingency of £40,000, and formalise the contract award. Report P4, P5

Why

Bullens Conservation Ltd was the only bidder through a competitive CHEST tender and offered the most advantageous tender on cost, quality and social value. Report P6, P19, P26

Appointing the main contractor now allows the council to meet the two-year deadline to claim the £100,000 Wolfson Foundation grant, received 10 June 2024. Report P6, P12, P18, P40

The additional £155,000 is needed because the original budget did not include detailed survey and design work, and the final tendered cost of £473,000 including VAT is higher than first estimated. Report P15, P17

What happens next

Enter into a JCT Minor Works Building Contract with Bullens Conservation Ltd and commence the construction phase. Report P3, P44

The Conservation Consultant who prepared the specification will stay involved throughout the project to manage heritage and grant risks. Report P29, P40

Decision takes effect five working days after publication, subject to call-in under the council's Constitution. Report P49

The money

  • £394,117.61 Contract value exclusive of VAT Report P3, P20, P27
  • £472,941.13 Contract value inclusive of VAT Report P3, P20
  • £155,000 Additional capital scheme approval, including £40,000 contingency Report P4, P17, P42
  • £40,000 10% council contingency for unforeseen issues on the heritage asset Report P4, P16
  • £100,000 Wolfson Foundation grant funding the scheme Report P12, P15
  • £295,000 Council contribution to the tendered cost Report P15
  • £5,000 Contribution from the Friends of Astley Hall Report P15
  • £473,000 Total tendered cost including VAT Report P15
  • £7,640.00 Value of local FTE employment commitment from the contractor Report P25
  • less than £10k per annum Estimated additional revenue cost of the £155,000 borrowing Report P42

Options considered

  • Chosen: Appoint Bullens Conservation Ltd. Only successful bidder via competitive CHEST tender; strongest score on cost, quality and social value; benchmarked within 10% variance. Report P3, P6, P22, P26, P28
  • Rejected: Award the contract to another contractor. No other compliant tender was received during the competitive process. Report P8, P19

Implications

  • Financial: An extra £155,000 will be added to the capital programme and financed through council borrowing, with an additional revenue cost of less than £10,000 per year. Report P42
  • Legal: A JCT Minor Works Building Contract will be used to provide legal protection and accountability between the council and the supplier. Report P44
  • Equalities: An Integrated Impact Assessment found no adverse impacts for people with protected characteristics. Report P36
  • Climate: Works are expected to improve heat retention and carbon performance, with reuse of existing timbers where possible. Report P31, P32
  • Risk: Cost could rise if latent defects are found when the building is opened up; a £40,000 contingency has been set aside. Report P16, P39
  • Risk: The Wolfson Foundation grant could be forfeited if works do not start within two years of the award letter dated 10 June 2024. Report P18, P40
  • Other: Bat surveys have been completed before any building works to protect nesting or roosting bats. Report P34

Who and where

  • Chorley Borough Council as client and capital funder Report P13, P15, P42
  • Bullens Conservation Ltd as the appointed contractor Report P3, P22
  • Friends of Astley Hall as a contributing funder Report P15
  • Wolfson Foundation as grant funder with a two-year claim deadline Report P12, P18
  • Visitors and users of Astley Hall, a heritage asset Report P14, P16
  • Local unemployed residents recruited under social value commitments Report P25

Timeline

  • 17 September 2023: Full Council approved acceptance of the £100,000 Wolfson Foundation grant and added it to the capital budget. Report P12, P13
  • 10 June 2024: Council received the Wolfson Foundation award letter; the two-year claim window started. Report P18
  • Two years from 10 June 2024: Deadline to claim the Wolfson Foundation funding and complete the works. Report P18, P40
  • Five working days after publication: Decision takes effect unless called in under the council's Constitution. Report P49
  • Tuesday, 02 December 2025: Report dated and signed by the Major Projects Delivery Manager. Report P48
  • 11 December 2025: Executive Cabinet considered the contractor appointment.

Plain English for the jargon

  • JCT Minor Works Building Contract: A standard industry contract for smaller building projects, published by the Joint Contracts Tribunal.
  • CHEST: A procurement platform used by the council to invite and evaluate competitive tenders.
  • Wolfson Foundation: A grant-giving charity funding heritage and other projects, which awarded £100,000 to this scheme.
  • Capital scheme contingency: A reserve sum set aside within a capital budget to cover unexpected costs during construction.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item57

Resolved

To appoint Bullens Conservation Ltd under a JCT Minor Works Building Contract at a contract value of £394,117.61 (exclusive of VAT), £472,941.13 (inclusive of VAT) and secure approval to proceed to the construction phase of the Astley Hall West Wing renovation scheme. 2. To approve an increase in an existing capital scheme project to the value of £155,000 (including 10% contingency totalling £40k). 3. To formalise the contract award.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Purpose of the report

1. The report details the procurement process undertaken to select a contractor for the Astley Hall West Wing renovations and seeks approval to appoint Bullens Conservation Ltd as the preferred contractor to carry out the identified repair works to the property.

Recommendations to Executive Cabinet

2. To appoint Bullens Conservation Ltd under a JCT Minor Works Building Contract at a contract value of £394,117.61 (exclusive of VAT), £472,941.13 (inclusive of VAT) and secure approval to proceed to the construction phase of the Astley Hall West Wing renovation scheme.

3. To approve an increase in an existing capital scheme project to the value of £155,000 (including 10% contingency totalling £40k).

4. To formalise the contract award.

Reasons for recommendations

5. Bullens Conservation were selected through a competitive tender process conducted in accordance with the Council’s Contract Procedure Rules and via the CHEST, based on evaluations of cost and quality. They have demonstrated that they meet the required skills, experience, and social commitments. 6. Appointing the main contractor at this stage will facilitate the delivery of requirements associated with the Wolfson Foundation funding.

Other options considered and rejected

7. To award the contract to another contractor, this has been rejected as the robust competitive tender process only attracted one successful bidder and in turn demonstrated that Bullens Conservation Ltd offered the most advantageous tender.

Corporate priorities

8. The report relates to the following corporate priority: An enterprising economy with vibrant local centres in urban and rural areas

Background to the report

9. A report was presented to Full Council on 17 September 2023 advising of the successful bid to the Wolfson Foundation and seeking approval to accept a grant of £100,000 to support renovations to the West Wing of Astley Hall.

10. Council resolved to accept the £100,000 grant funding from the Wolfson Foundation and approved an increase in the Astley Hall capital budget by an equivalent amount to reflect the receipt of the grant.

11. This scheme forms part of the Corporate Strategy for 2025–2026 under the priority of delivering “a green and sustainable borough”. The grant will fund essential works including the review and repair of the timber frame, removal of cement infill panels and replacement with lime mortar, as well as repairs to leadwork and windows.

12. The total tendered cost is £473,000 including VAT comprising £100,000 from the Wolfson Foundation, £295,000 from the Council, and £5,000 from the Friends of Astley Hall.

13. It is recommended that a 10% Council contingency of £40,000 is allocated to address any unforeseen issues arising during the construction phase due the nature of the heritage asset.

14. An additional £155,000 is needed because the initial budget did not include detailed survey and design work; after completing these and the contractor procurement process, it was determined that more funding is required to finish the project.

15. The Wolfson Foundation funding must be claimed within two years of the award letter, which the Council received on 10 June 2024. Procurement - Astley Hall West Wing Renovations

16. The tender was issued via the CHEST procurement platform to four nominated bidders with appropriate heritage construction experience; one submission was received prior to the deadline.

17. The submitted price and moderated scores, with a maximum weighting of 30%, are summarised below. The tendered amount of £394,117.61 (exclusive of VAT), £472,941.13 (inclusive of VAT)) achieved the full 30% weighting.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Astley Hall West Wing Renovations: Contractor AppointmentAppendix A 434 KB Download
PDF
Astley Hall West Wing Renovations: Contractor AppointmentReport 75 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 18 attended
AB
Councillor Alistair BradleyExecutive Leader, present
PW
Councillor Peter WilsonDeputy Leader, present
BM
Councillor Beverley MurrayCommittee Member, present
TH
Councillor Terry HowarthCommittee Member, present
AH
Councillor Alex HiltonCommittee Member, apologies
MF
Councillor Margaret FranceCommittee Member, apologies
AL
Councillor Adrian LoweCommittee Member, present
CS
Chris SinnottOfficer, in attendance
SB
Sarah BullockOfficer, in attendance
RT
Rochelle TappingOfficer, in attendance
TS
Tasneem SafdarOfficer, in attendance
NH
Neil HaltonOfficer, expected

All 18 on the meeting page

On this subject at Chorley

Search all
  1. Astley Hall West Wing Renovations - Contractor AppointmentThis decision
  2. Re-opening of Astley HallAgreed
  3. 21/01020/LBC - Astley Hall, Astley Park, Park Road, Chorley, PR7 1NPDecided
  4. 20/00930/LBC - Astley Hall, Park Road, ChorleyDecided
  5. Update on and contract award for Astley Hall conservation workNoted
  6. 20/00811/LBC - Astley HallDecided

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies