CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Chorley Borough Council
Executive Cabinet, Thursday 11 June 2026 at 6.30pm

Insurance Policies

Agreed Executive 1 paper

AI summaryChorley Council's Executive Cabinet agreed to extend existing insurance policies for 16 months, from January 2027 to April 2028, and waived Contract Procedure Rules to do so. The move avoids a costly re-tender during Local Government Reorganisation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreed16 months, Contract Procedure Rules waived
MoneySee premium breakdownSix policies listed, annual and 5-year totals
What happens nextFive working days after publicationSubject to call-in under the Constitution
Who it affectsCouncil insurance cover during LGRCover from 01 January 2027 to April 2028

What was decided

Executive Cabinet agreed to extend existing insurance policies for a period of 16 months. Report P3

Executive Cabinet approved a waiver of the Contract Procedure Rules for the extension. Report P4

Why

The Audit and Risk service, advised by insurance broker A J Gallagher, concluded that extending existing arrangements is the best way to ensure continuous cover during the uncertainty of Local Government Reorganisation. Report P5, P6, P11

Re-tendering for 16 months would carry risks of limited market appetite, low competition, higher premiums, reduced cover, and possible gaps in cover at a critical transitional period. Report P7

Long Term Agreements normally attract premium discounts that would not be available on a short-term contract, and novation to a new unitary would still require a major re-negotiation. Report P7, P20, P27

What happens next

The decision takes effect five working days after publication, unless called in under the Council's Constitution. Report P42

If Local Government Reorganisation proceeds and a new unitary council is formed, a full procurement exercise will be required, including actuarial review and risk forecasting. Report P8

The money

  • £141,228.66 Combined Liability 2026 annual premium (Protector Insurance) Report P19
  • £666,527.50 Combined Liability 5 year LTA total Report P19
  • £170,277.27 Property 2026 annual premium (Protector Insurance) Report P19
  • £704,326.27 Property 5 year LTA total Report P19
  • £42,003.33 Motor Fleet 2026 annual premium (Protector Insurance) Report P19
  • £197,414.98 Motor Fleet 5 year LTA total Report P19
  • £33,876.72 Terrorism 2026 annual premium (Chaucer) Report P19
  • £116,685.78 Terrorism 5 year LTA total Report P19
  • £1,998.08 Personal Accident 2026 annual premium (Risk Management Partners) Report P19
  • £4,161.92 Personal Accident 5 year LTA total Report P19
  • £5,096.17 Fine Arts 2026 annual premium (XL Catlin / Risk Management Partners) Report P19
  • £34,793.81 Fine Arts 5 year LTA total Report P19

Options considered

  • Chosen: Extend existing insurance policies under Long Term Agreements for 16 months. Broker advice; avoids procurement risk and higher short-term premiums during Local Government Reorganisation uncertainty. Report P6, P11
  • Rejected: Run a full procurement exercise for all policies. Risks include limited market appetite, low competition, higher premiums or reduced cover, possible gaps in cover, and poor value for money over 16 months. Report P7, P10

Implications

  • Legal: Contract Procedure Rules are being waived; procurement must still accord with the best value duty in the Local Government Act 1999. Report P38
  • Financial: Extension is seen as the most likely to produce an affordable solution, retaining Long Term Agreement premium discounts. Report P7, P36
  • Risk: Other risks to be managed are resources, expenditure on professional services such as actuarial reviews, and claims history and historical liabilities from previous authorities. Report P34

Who and where

  • Chorley Borough Council Report P16, P19
  • Chorley Leisure Limited (subsidiary) Report P16
  • Future unitary council(s) under Local Government Reorganisation Report P8, P25, P27
  • Incumbent insurers including Protector Insurance, Chaucer, Risk Management Partners and XL Catlin Report P19, P26
  • Insurance broker A J Gallagher Report P5, P11

Timeline

  • Tuesday, 02 June 2026: Report authored by Senior Risk and Insurance Officer Report P41
  • 11 June 2026: Executive Cabinet meeting considers the decision
  • 31 December 2026: Current 5 year Long Term Agreement ends Report P16
  • 01 January 2027: Start of 16 month extension period Report P6
  • April 2028: End of 16 month extension period Report P6
  • Five working days after publication: Decision takes effect, subject to call-in Report P42

Plain English for the jargon

  • LGR: Local Government Reorganisation, the planned restructuring creating new unitary councils from existing district and county councils.
  • LTA: Long Term Agreement, the standard 3 to 5 year procurement arrangement used for public sector insurance.
  • Novation: The transfer of a contract from one party to another, which for insurance policies is complicated by a shift in the insured risk profile.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

To agree the proposed approach of an extension of existing insurance policies for a period of 16 months 2. To approve the waiver of the Contract Procedure Rules associated with the extension of insurance policies.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Purpose of the report

1. Members are asked to consider the proposal to extend existing agreements with incumbent insurers.

Recommendations to Executive Cabinet

2. That Executive Cabinet agree the proposed approach of an extension of existing insurance policies for a period of 16 months

3. That Executive Cabinet approve the waiver of the Contract Procedure Rules associated with the extension of insurance policies.

Reasons for recommendations

4. The Audit and Risk service has sought advice from Insurance Broker, A J Gallagher, researched information and articles on Local Government Reorganisation (LGR) from professional bodies and conversed with other authorities.

5. The service is of the opinion the best approach for Chorley Council is to seek an extension of existing arrangements to cover the period 01 January 2027 to April 2028 to ensure sufficient cover for the Council. The extension arrangement will hold adequate insurance cover to mitigate any risks associated with phased implementation and transfer of risk.

6. The alternative is to procure new agreements for the period of 16 months. This approach would carry the following risks: • Limited market appetite: Public sector insurers are unlikely to commit underwriting capacity to a contract of this duration, particularly where future organisational form and risk profile are uncertain. • Reduced competition: There is a material risk of low or nil compliant bids, or participation only from incumbent insurers only. • Higher premiums and/or reduced cover: Short-term contracts are typically priced less competitively, with insurers seeking to offset uncertainty through higher premiums or narrower cover. Long Terms Agreements bring with that discounts of annual premiums which would not be offered in this situation. • Operational and coverage risk: Re-tendering increases the risk of delay, procurement failure, or gaps in cover at a critical transitional period. • Limited value for money: The cost and officer time associated with a further procurement exercise are unlikely to be justified by the outcomes achievable over a 16-month period.

7. A full procurement of insurance policies will be necessary if local government reorganisation proceeds and a new unitary council is formed, which will be an extensive project, requiring actuarial review and risk forecasting before the procurement exercise can be designed.

Other options considered and rejected

8. The alternative option is to undertake a full procurement exercise, approaching the market for all policies currently contracted through Long Term Agreements. The risks associated with this option have been highlighted in the report.

9. A J Gallagher, the Council’s Insurance Broker, advise is it in the council’s interest to extend existing insurance policies and agreements. That a procurement exercise in the current environment carries strategic and financial risks.

Corporate priorities

10. The report relates to the following corporate priorities: Housing where residents can live well A green and sustainable borough An enterprising economy with vibrant local centres in urban and rural areas Healthy, safe and engaged communities

Background to the report

11. Insurance contracts for public sector authorities are typically procured under Long Term Agreements (LTAs) of three to five years. This reflects insurer underwriting practices, the need for stability of risk, and the requirement to demonstrate value for money over time.

12. The LTA for Chorley Council (and subsidiary Chorley Leisure Limited) was procured last on a 5 year (3 +1, +1) basis, ending 31 December 2026. Prior to the announcement of Local Government Reorganisation (LGR) the Audit and Risk service planned to run a procurement exercise during 2026.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Insurance PoliciesReport 76 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 18 attended
AB
Councillor Alistair BradleyExecutive Leader, present
PW
Councillor Peter WilsonDeputy Leader, present
BM
Councillor Beverley MurrayCommittee Member, present
AH
Councillor Alex HiltonCommittee Member, present
MF
Councillor Margaret FranceCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present, as expected, virtual
CS
Chris SinnottOfficer, in attendance
RT
Rochelle TappingOfficer, expected
KL
Kay LoveladyOfficer, expected
TS
Tasneem SafdarOfficer, in attendance
NH
Neil HaltonOfficer, in attendance
CW
Caroline WolfendenOfficer, in attendance

All 18 on the meeting page

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies