Cabinet, Wednesday 29 July 2026 at 10.00am

2027/28 Budget and MTFP Refresh - Strategic Framework, Transformation approach and Emerging Issues

Decided Executive 2 papers

AI summaryCornwall Council Cabinet has agreed the strategic framework and BEST transformation approach as the basis for the 2027/28 budget, with scenario modelling showing a potential £22m gap in the best case for 2027/28.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedBasis for draft 2027/28 budget to be considered on 4 November 2026
MoneyBest case £22m gap in 2027/28Approximately 2% of net revenue budget
What happens nextDraft budget to Cabinet 4 November 2026Full Council approval of budget and Council Tax on 23 February 2027
Who it affectsCornwall residents and council servicesParticularly adult and children's social care, SEND and Home to School Transport

What was decided

Cabinet agreed the strategic framework for budget setting and the approach to delivering transformation as the basis for development of the draft 2027/28 budget to be considered on 4 November 2026. Report P1

The Council will move to a four-year Medium-Term Financial Plan planning horizon, extended to the end of 2030/31. Report 2.16

Directorates have been tasked with identifying savings options equivalent to 5% of their expenditure budgets to help close the forecast gap. Report 2.23

Why

The Council faces continued demand-led pressures in adult and children's social care and SEND, alongside higher than expected inflation, increased borrowing costs, and a £14m funding reduction in 2026/27 following the Fair Funding Review 2.0. Report 2.6, 2.4

A 2025/26 revenue overspend of £7.494m had to be closed using reserve funding, suggesting a structural imbalance between demand and resources that cannot be sustained. Report 2.4

Scenario modelling shows a combined potential gap of between £10.3m and £20.9m over the next two financial years, with a best case gap of £22m in 2027/28. Report 2.22

What happens next

Cabinet to consider the draft 2027/28 budget and refreshed MTFP for consultation on 4 November 2026, with consultation concluding on 20 December 2026. Report 2.71, P113

Cabinet to consider the provisional settlement and company business plans on 16 December 2026, then recommend the budget and MTFP for approval on 10 February 2027, with Full Council approving the budget and Council Tax on 23 February 2027. Report 2.71, P113

Detailed scenario testing, base budget review, business case development and benchmarking work will be completed over the summer to inform a single scenario reported to Cabinet in the autumn. Report 2.18, 2.23, 2.54

The money

  • £22m Best case forecast budget gap for 2027/28, approximately 2% of net revenue budget Report 2.22
  • £10.3m Lower end of potential total budget gap over the next two financial years
  • £20.9m Upper end of potential total budget gap over the next two financial years
  • £7.494m 2025/26 revenue overspend closed using reserve funding Report 2.4
  • £14m Reduction in 2026/27 funding compared with previously modelled levels following Fair Funding Review 2.0 Report 2.6
  • £59.113m New savings target in the 2026/27 budget Report 2.21, P38
  • £48.842m Approved savings assumed in the MTFP for 2027/28 Report 2.21, P38
  • £46.146m Approved savings assumed in the MTFP for 2028/29 Report 2.21, P38
  • £38.112m Savings achieved in 2025/26, representing 78% of the £48.825m target Report 2.24, P53
  • £7.8m Transformation savings profiled for 2026/27
  • £28.6m Transformation savings profiled for 2027/28
  • £30.2m Transformation savings profiled for 2028/29
  • £252.865m Forecast closing balance of usable reserves at 31 March 2026 Report P93
  • £55.996m In-year deficit on the High Needs Dedicated Schools Grant Report 2.41
  • £137.148m Forecast cumulative Dedicated Schools Grant deficit for 2026/27 Report 2.41

Options considered

  • Chosen: Agree the strategic framework and transformation approach set out in the report as the basis for developing the draft 2027/28 budget and refreshed MTFP. Enables further development of the draft budget and supports the statutory duty to set a balanced and sustainable budget Report 10.1, 10.2, P1
  • Rejected: Request further analysis, information or alternative options to be considered as part of the budget development process. Not preferred; would delay the budget process Report 10.2
  • Rejected: Propose an alternative approach to the strategic framework or transformation priorities. Any alternative would still need to support the statutory duty to set a balanced and sustainable budget Report 10.2

Implications

  • Financial: A potential £22m gap in 2027/28 best case scenario must be closed through a combination of in-year management, delivery of approved and new savings, and BEST transformation savings, with reliance on reserves to be reduced over the medium term. Report 2.22, 2.23, 2.54
  • Financial: Useable reserves stood at 24% of net revenue expenditure in 2024/25, around £30m below the 28.4% average for comparator councils, while c£48.1m is allocated to PFI risks. Report 2.52, 2.53, P97
  • Legal: The Council is legally required to set a robust and balanced budget, have regard to the Section 151 Officer's advice under the Local Government Act 2003, comply with the public sector equality duty, and meet statutory consultation duties. Report 7.1
  • Risk: Key risks include continuing demand-led pressures in adult and children's services and SEND, uncertainty over future funding, inflation, collection fund performance, increasing borrowing and capital financing costs, pressures on the Council's group of companies, deliverability of existing and future savings, and adequacy of reserves. Report P133, P134, P135, P136, P137, P138
  • Equalities: All relevant savings and growth lines with an impact on staff, service users, the community or environment will be assessed using a Cornwall Development and Decision Wheel, alongside a cumulative impact assessment to be published in February 2027.
  • Staffing: Workforce redesign is a core component of the BEST transformation programme, with the Council seeking to re-train and re-deploy affected employees as far as practicable; an LGA-supported spans and layers review is in the discovery phase and due to complete in October 2026. Report 2.29
  • Other: A potential merger of the Cornwall and Isles of Scilly Integrated Care Board with the neighbouring Devon ICB is being challenged by the Council, and risk remains around the costs of being designated as a strategic and local authority. Report 2.8

Who and where

  • Residents of Cornwall, who would see changes to council services and continued increases in Council Tax assumed at 4.99% annually Report P44
  • Children and young people with SEND and their families, given a 20% forecast increase in EHCP demand over the next 12 months and a £137.148m cumulative DSG deficit forecast for 2026/27 Report 2.41
  • Council staff, given the spans and layers review, a £5m people-related savings target at risk in 2026/27, and workforce redesign within the BEST programme Report 2.27, 2.29
  • Council owned companies, whose business plans have been accepted in principle subject to more transparent reporting Report 2.39, P72
  • Business rate payers, who must be consulted on the Council's expenditure plans under section 65 of the Local Government Finance Act 1992

Timeline

  • 28 July 2026: Corporate Finance and Performance Overview and Scrutiny Committee considered the same report
  • 1 September 2026: Constitution and Governance Committee to consider review of Terms of Reference for budget scrutiny arrangements Report 5.5
  • 15 September 2026: Full Council to consider any resulting constitutional amendments Report 5.5
  • 23 September 2026: Cabinet to consider the Quarter 1 Council Performance Report including an update on savings delivery Report 2.24, P54
  • October 2026: Completion expected of the LGA-supported spans and layers review discovery phase
  • 4 November 2026: Cabinet to approve the draft 2027/28 budget and refreshed MTFP for consultation, brought forward from 11 November to allow a six-week consultation Report 2.71, P113
  • 16 December 2026: Cabinet to consider the provisional settlement impact and Council owned companies' business plans for 2027/28 Report 2.71, P113
  • 20 December 2026: Public and stakeholder consultation on the draft budget to conclude Report 2.71, P113
  • 10 February 2027: Cabinet to recommend approval of the 2027/28 budget and MTFP including Treasury Management and Capital and Investment Strategies Report 2.71, P113
  • 23 February 2027: Full Council to approve the 2027/28 Council Tax, budget and MTFP Report 2.71, P113
  • March 2029: First PFI asset hand-back, for 29 Fire Stations, with Education and Waste PFI contracts to follow Report 2.40, P74

Plain English for the jargon

  • MTFP: Medium-Term Financial Plan
  • BEST: Bold, Empowering, Sustainable, Together; the Council's mission and the name of its transformation programme
  • FAIR: Fairness, Ambition, Inclusion, Respect; the Council's values
  • DSG: Dedicated Schools Grant
  • EHCP: Education, Health and Care Plan
  • SEND: Special Educational Needs and Disabilities
  • ISP: Independent School Provision
  • FFR: Fair Funding Review
  • LGA: Local Government Association
  • ICB: Integrated Care Board
  • LGR: Local Government Reorganisation
  • MHCLG: Ministry for Housing, Communities and Local Government
  • LOF: Local Outcomes Framework
  • CFR: Capital Financing Requirement, reflecting the underlying need to borrow
  • PPE: Property, Plant and Equipment
  • PFI: Private Finance Initiative
  • CPI: Consumer Price Index
  • HRA: Housing Revenue Account
  • CFPOSC: Corporate Finance and Performance Overview and Scrutiny Committee
  • BDOSC: Budget Development Overview and Scrutiny Committee
  • CDDW: Cornwall Development and Decision Wheel
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB/568

Resolved

DECISION: As contained within the report.
Word for word from the decision Cornwall published for this meeting. Source: democracy.cornwall.gov.uk

Follow this further

Built from Cornwall's papers

What the report saysPro

Report to Cabinet, 24 pages

Recommendation

1. In light of the refreshed Medium-Term Financial Plan (MTFP) projections, that Cabinet agrees the strategic framework for budget setting moving forward and the approach to delivering transformation that will be used as the basis for the development of the draft budget to be considered by the Cabinet on 4 November 2026. Information Classification: PUBLIC

Executive summary

1.1This report provides an update on how the Council updates its corporate planning, ensuring that the Council Priorities and Delivery Plan are at the core of resource prioritisation, whilst refreshing the Medium-Term Financial Plan to reflect on emerging pressures from 2025/26 and the early part of 2026/27.

1.2The proposed approach is underpinned by the Council’s BEST (Bold, Empowering, Sustainable, Together) mission and FAIR (Fairness, Ambition, Inclusion, Respect) values, which has shaped a single, outcome-focused transformation framework to redesign services, reduce demand and deliver sustainable savings aligned to the associated savings as set out in the Medium-Term Financial Plan. 1.3 The Council is developing the 2027/28 budget and refreshed Medium -Term Financial Plan in a period of continued uncertainty. Financial forecasts will continue to evolve over the coming months as further information becomes available and assumptions are tested. Like many local authorities, the Council continues to face significant demand-led pressures in adult and children's social care and Special Educational Needs and Disabilities (SEND), alongside wider inflationary, economic and public sector reform pressures. It is therefore important that a clear and transparent understanding is maintained of the factors driving changes to the forecast position, enabling informed decision-making throughout the budget development process.

1.4Against this backdrop, the Council's forecast financial position remains fragile. For the first time in several years, the Government has provided a three-year financial settlement covering the period 2026/27 to 2028/29. Whilst this provides greater certainty for financial planning and service delivery, the scope for additional funding is expected to be limited. The Council's delivery and budget plans must therefore be based on the funding that has been announced, whilst recognising that underlying forecasts and assumptions will continue to be refined. 1.5 To deliver a balanced budget for 2027/28, the Council is in the process of evaluating emerging pressures and developing options that can mitigate these. Forecasts for the two years beyond the current MTFP period are to be developed over the summer so that the Council has a four-year planning horizon which is in line with best practice. Throughout the process, there will be the opportunity for Directorates to engage and consult with Members.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2027/28 Budget and MTFP Refresh: Strategic Framework, Transformation approach and Emerging Issues: Appendix 1 /568Appendix 26 pages Download
PDF
2027/28 Budget and MTFP Refresh: Strategic Framework, Transformation approach and Emerging IssuesReport 24 pages DownloadRead as text

More from Cornwall Cabinet

All decisions
MeetingDecisionOutcome
11 Nov 2026 Minutes of the Meeting Held on 23 September 2026 / Kovnotennow an Kuntelles Synsys 23 mis Gwynngala 2026It was proposed by Councillor Frost, seconded by Councillor Paynter and RESOLVED that the minutes of the Cabinet meet... Decided Open
11 Nov 2026 Council Performance Report 2026/27(Q2)DECISION: As contained within the report. Decided Open
11 Nov 2026 Digital Connectivity Investment ProgrammeDECISION: As contained within the report. Decided Open
11 Nov 2026 Cornwall Education Partnership Education StrategyDECISION: As contained within the report. Decided Open
11 Nov 2026 Farms Strategy 2019-2039 (2026 Review)DECISION: Decided Open