Cornwall Council
Cabinet, Wednesday 29 July 2026 at 10.00am

Treveth 1-Year Delivery Plan 2026 to 2027

Decided Executive 3 papers

AI summaryCornwall Council Cabinet approves Treveth 1-Year Delivery Plan 2026/27 in principle, with £5.878m equity for two new housing schemes and a £35m Revolving Credit Facility cap.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved1-Year Delivery Plan, equity, and delegated authority approved
Money£5.878m equityfor Bedowan Meadows and Connor Downs schemes
What happens nextDecember 2026updated 4-Year Business Plan to Cabinet
Who it affectsTreveth Holdings LLPCouncil-owned housing and commercial delivery company

What was decided

Cabinet approved the Treveth Holdings LLP 1-Year Delivery Plan 2026/27 in principle, with an updated 4-Year Business Plan to come to Cabinet in December 2026. Report P1, 2.1

Cabinet approved in principle equity investment in Treveth schemes and delegated authority to the Chief Executive Officer, in consultation with the Cabinet Member for Resources, the Section 151 Officer and the Monitoring Officer, to put in place the necessary agreements. Report P2

Cabinet approved £5.878m of equity for the Bedowan Meadows and Connor Downs schemes, funded by reallocating capital resources from within the existing approved Capital Programme. Report P3, 6.17, P75, P79, 10.3

Why

Treveth's funding, capital and risk position is in transition, so a longer-term Business Plan cannot yet be finalised; a 1-Year Plan maintains delivery and financial stability while a sustainable longer-term funding and operating model is developed. Report 1.1, 1.3, P6, 2.1, P14

The Council is capping the Revolving Credit Facility made available to Treveth at £35m to manage short-term development funding risk and protect Council liquidity, with the Delivery Plan built to operate within this limit. Report 6.8, P65, P66, P67

Equity funding in two new schemes is intended to reduce overall development borrowing, lower interest costs, improve scheme viability and replace retained-asset revenue shortfalls, helping the company move away from the existing delivery model. Report 6.13, 6.14, 6.17, 6.18, 6.19

What happens next

An updated 4-Year Business Plan for Treveth will be brought to Cabinet in December 2026, aligned with the Council's Medium Term Financial Planning process. Report P1, 2.1

A new Cornwall Council Commercial Strategy and review of its company portfolio will be reported to Cabinet in September 2026 and may inform a future Treveth business plan. Report 2.25

Treveth will provide additional monthly reporting on management accounts, cashflows, debt and investment portfolio, and contracts during the 2026/27 transitional year, with RCF utilisation monitored to keep within the £35m cap. Report 2.24, P41, P42

The money

  • £5.878m Equity investment for Bedowan Meadows and Connor Downs schemes Report P3, 6.17, P79
  • £35m Maximum Revolving Credit Facility balance for Treveth in 2026/27
  • £82.375m Treveth Revolving Credit Facility balance as at 31 March 2026 Report 6.2
  • £65.677m Treveth Term Loan balances as at 31 March 2026 Report 6.2
  • £150.300m Total forecast Treveth capital expenditure 2026/27 to 2028/29 Report P58, P59, P60, P61
  • £25.400m Treveth forecast capital expenditure 2026/27 Report P58
  • £59.000m Treveth forecast capital expenditure 2027/28 Report P59
  • £65.900m Treveth forecast capital expenditure 2028/29 Report P60
  • £2.000m Approved Council revenue budget assumption from Treveth-related financing activity Report 2.13, 6.15
  • £1.6 m Capital funding requirement within 2026/27 plan to support pipeline development
  • £5.134m Reduced capital plans for Cornwall Airport Newquay against an approved Budget of £13.382m, source of reallocated capital Report P75
  • c£0.350m Estimated MRP and interest cost of alternative option to reprofile Treveth Term Loan provision Report 10.2

Options considered

  • Chosen: Approve the 1-Year Delivery Plan, equity investment and delegated authority as recommended. Maintains delivery and financial stability during transition while capping Council exposure through a £35m RCF limit and £5.878m equity funded from within the existing Capital Programme Report P1, P2, P3, 10.1, 10.3, P75
  • Rejected: Reprofile existing Treveth Term Loan provision within the approved Capital Programme to fund the equity. Would generate c£0.350m of MRP and interest cost; reallocating from elsewhere in the Capital Programme is cost neutral Report 10.2, 10.3
  • Chosen: Reallocate existing capital resources from elsewhere in the Council's Capital Programme to fund the equity. Cost neutral to the Council's MRP and interest budget and keeps funding within company-related activity Report P75, 10.2, 10.3
  • Rejected: Prioritise Coinagehall Street and Perran Foundry schemes in the 2026/27 Delivery Plan. Plan does not have sufficient funding capacity for all schemes that could start in 2026/27; chosen schemes better maximise housing delivery and the development pipeline Report P26, 2.15, P28

Implications

  • Financial: Equity of £5.878m creates a direct financing cost; borrowing and MRP costs arise one year after investment but are manageable within existing budget, while reducing pressure on the RCF. Report 6.17, 6.19
  • Financial: Approval does not increase overall Council capital expenditure; equity will be funded by reallocating £5.134m of reduced Cornwall Airport Newquay capital within the approved Capital Programme. Report P75
  • Financial: RCF drawn balance is to be reduced from £82.375m to a target of around £35.000m by 31 March 2027 through completions, sales, term loan conversions, exercise of land options at Trevithick Manor Farm and equity investment. Report 6.2, 6.8, P65, P66, P67
  • Financial: The £2.000m pa revenue net interest receipt budget from Treveth-related financing is forecast to be maintained in 2026/27. Report 2.13, 6.15
  • Legal: Council relies on Local Government Act 2003 (ss12, 15), Local Government Act 1972 (s120) and Localism Act 2011 (s1) as principal statutory powers for participating in Treveth. Report 7.5
  • Legal: Equity funding must be assessed against subsidy control rules, most likely under the commercial market operator principle, and require the Council to act as a prudent private investor. Report 7.6, 7.7
  • Legal: Treveth's compliance with the Social Housing (Regulation) Act 2023 and the Building Safety Act 2022 remains a priority, with pace of delivery potentially influenced by future funding.
  • Risk: Delivery risk: delays in completions, weaker sales, slower term loan conversions or failure to secure equity could increase RCF pressure and require further intervention. Report 6.9, 6.10
  • Risk: Pipeline expenditure of £1.6m carries a risk that future schemes may not proceed to construction or may require further funding decisions. Report 2.21
  • Equalities: A Cornwall Development and Decision Wheel has been completed for Treveth Holdings LLP; further detail is in Appendix 4. Report 9.1, P92, P94
  • Staffing: Additional monthly reporting on budgeted core establishment, consultancy, agency and professional services spend is required for 2026/27. Report P42, 2.24

Who and where

  • Treveth Holdings LLP, the Council's delivery partner for the Investment Programme Report 2.4, P9
  • Residents and prospective tenants of new homes delivered by Treveth Report 2.8, P16, 2.17, P29
  • Cornwall Council, as owner, funder and treasury manager of Treveth Report 6.1, 6.4, 8.2
  • Contractors and supply chain working on Treveth residential and commercial schemes Report 2.17, P26
  • Cornwall Airport Newquay, from whose reduced capital plans equity funding is reallocated Report P75

Timeline

  • 26 March 2025: Previous Cabinet approval of the 2025-29 Council Owned Companies Business Plans Report P48
  • 18 June 2025: Previous Cabinet decision to end the proposed Airport Joint Venture
  • November 2025 to July 2026: Treveth Holdings LLP Project Committee meetings progressed the 1-Year Delivery Plan Report 5.2
  • December 2025 and July 2026: Treveth Holdings LLP Owners Board meetings considered the Plan Report 5.3
  • 13 February 2026: Previous Cabinet budget report Report 4.1
  • 13 March 2026: Informal Corporate Finance and Performance Overview and Scrutiny Committee considered draft direction of travel
  • May and June 2026: Joint Business Plan Working Group meetings between Cornwall Council and Treveth Holdings LLP Managing Directors and Officers Report 5.5
  • 7 July 2026: Extraordinary Treveth Project Committee approved the 1-Year Delivery Plan Report 5.6
  • 10 July 2026: Extraordinary Treveth Owners Board endorsed in principle the 1-Year Delivery Plan
  • 20/07/2026: Finance sign-off on the Cabinet report Report P104
  • 21/07/2026: Governance/Legal and Service Director sign-off on the Cabinet report Report P104
  • 23rd July 2026: Informal Corporate Finance and Performance Overview and Scrutiny Committee briefing on the Plan
  • 28 July 2026: Corporate Finance and Performance Overview and Scrutiny Committee formally considered the Plan Report 5.9
  • 29 July 2026: Cabinet decision on the 1-Year Delivery Plan Report P1
  • September 2026: New Commercial Strategy and review of Council companies to be reported to Cabinet Report 2.25
  • December 2026: Updated 4-Year Business Plan for Treveth to be presented to Cabinet Report P1, 2.1
  • During 2026/27: 70 new homes forecast to be delivered by Treveth, with a further 86 by end of 2028/29 Report 2.8, 2.17, P31
  • 31 March 2027: Target date for Treveth RCF balance to be reduced to approximately £35.000m

Plain English for the jargon

  • RCF (Revolving Credit Facility): A short-term borrowing facility made available by Cornwall Council to Treveth, capped at £35m for 2026/27
  • Term Loan: A longer-term loan from Cornwall Council to Treveth used to refinance completed development assets, with principal assumed to be repaid
  • Equity investment: Council funding provided in exchange for a share of ownership in a scheme, rather than as a repayable loan, reducing reliance on debt but not generating immediate interest income
  • IPAG (Investment Programme Assurance Group) approval: Cornwall Council's internal assurance step required before a development scheme can proceed
  • MRP (Minimum Revenue Provision): The revenue charge a council must set aside to repay capital borrowing over time
  • Commercial market operator principle: Subsidy control test requiring a public body to invest on the same terms as a prudent private investor would in the same market
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB/575

Resolved

DECISION: As contained within the report.
Word for word from the decision Cornwall published for this meeting. Source: democracy.cornwall.gov.uk

Follow this further

Built from Cornwall's papers

What the report saysPro

Report to Cabinet, 17 pages

Recommendations

1. That Cabinet approves in-principle the Treveth Holdings LLP 1-Year Delivery Plan for 2026/27 and supporting conditions, with an updated Business Plan to be submitted for consideration and approval in December 2026 .

2. That Cabinet approves the principle of equity investment in Treveth schemes and the consequential amendment to the Capital Programme and funding strategy and delegates authority to the Chief Executive Officer, in consultation with the Cabinet Member for Resources, the Section 151 Officer and the Monitoring Officer, to put in place such agreements as are necessary to facilitate this.

3. That Cabinet approves the application of equity £5.878m for the Bedowan Meadows and Connor Downs schemes.

Executive summary

1.1The Council Owned Companies are required to produce a 4-Year Business Plan, with annual budget updates. These need to align with the Council’s priorities and financial assumptions. Due to the current transition in Treveth’s funding, capital and risk position, Treveth is presenting a 1 ‑Year Delivery Plan for review on this occasion. This approach reflects the need to maintain delivery and financial stability in the short term while work progresses to define a sustainable longer‑term funding and operating model. A multi‑year plan cannot be responsibly finalised until this work is complete. 1.2 This Treveth Holdings LLP 1-Year Delivery Plan 2026-2027 sets out the proposed activity and organisational development for the coming year. Their Project Committee approved the principle of the equity contribution and inclusion of Bedowan and Connor Downs in the 1 Year Delivery Plan. The Council’s Owners Board has endorsed the plan in principle subject to additional transparency and reporting measures being introduced during 2026/27 to support development of an updated 4 Year Business Plan that will be presented to Cabinet in December 2026, aligned with the Council’s Medium Term Financial Planning process.

1.3The plan is being presented later than the start of the financial year as Treveth and Cornwall Council have been undertaking work to determine the future funding, governance and operating arrangements for the Treveth Group. This has included consideration of alternative funding and support arrangements beyond 2026/27. Until there is greater certainty regarding the future funding Information Classification: PUBLIC

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Treveth 1-Year Delivery Plan 2026 to 2027: Appendix 2 /575Appendix 20 pages Download
PDF
Treveth 1-Year Delivery Plan 2026 to 2027: Appendix 4 /575Appendix 6 pages Download
PDF
Treveth 1-Year Delivery Plan 2026 to 2027Report 17 pages DownloadRead as text

More from Cornwall Cabinet

All decisions
MeetingDecisionOutcome
11 Nov 2026 Minutes of the Meeting Held on 23 September 2026 / Kovnotennow an Kuntelles Synsys 23 mis Gwynngala 2026It was proposed by Councillor Frost, seconded by Councillor Paynter and RESOLVED that the minutes of the Cabinet meet... Decided Open
11 Nov 2026 Council Performance Report 2026/27(Q2)DECISION: As contained within the report. Decided Open
11 Nov 2026 Digital Connectivity Investment ProgrammeDECISION: As contained within the report. Decided Open
11 Nov 2026 Cornwall Education Partnership Education StrategyDECISION: As contained within the report. Decided Open
11 Nov 2026 Farms Strategy 2019-2039 (2026 Review)DECISION: Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies