Resolved
RESOLVED that the Audit and Procurement Committee approves the Council Tax Discounts Exemption Update and agrees the actions proposed.
Audit and Procurement Committee approved this item on Monday 7 April 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Audit and Procurement Committee approves the Council Tax Discounts Exemption Update and agrees the actions proposed.
The previous Audit Committee considered the findings of the Council Tax Discounts and Exemptions (excluding single person discounts) audit in February 2013, which concluded that ‘limited’ assurance could be provided that the Council had effective processes in place to minimise the risk of fraud and error in relation to the award of council tax discounts and exemptions. In terms of the key issues, these included:
• Instances highlighted where there was evidence that the exemption was no longer valid.
• A lack of dedicated resources in place specifically to monitor the on-going validity of discounts and exemptions that have been granted.
• Procedures were not sufficiently robust to support both the awarding and monitoring of discounts and exemptions.
• Based on points highlighted above, the risk was that a significant number of current discounts and exemptions awarded are no longer valid.
In August 2013, the Audit and Procurement Committee received an update on action in response to the audit findings. This highlighted that a working group of officers from within the Resources Directorate had been set up to consider this matter and determined that a project approach was the best way to take this issue forward in that it would assist in establishing the scale of the issue, which in turn would allow management to put in an appropriate solution.
2 Purpose of Briefing Note
The purpose of the note is to highlight:
• The key outcomes of the project, and
• Seek endorsement for actions to support sustainable improvements in this area. 3 Progress Update
The approach to this project was based on the following:
• Identifying a dedicated resource to undertake the work with support as requested from officers in both Council Tax and Internal Audit.
• Focusing the limited project resource on those discounts / exemptions where change was more likely to occur.
• Using a wide range of both internal and external data sources to assist in the process.
The project, including the initial internal audit review, has resulted in revised bills being generated to the value of approximately £117,000. There is still further work to be done to identify fraud and error as:
• There are over 50 further cases awaiting a management decision where there is no evidence to support the exemption currently awarded.
• The scale of the project is such that after excluding single person discounts, around 50% of discounts / exemptions have been reviewed to date as part of this project.
In terms of success, dedicating resources to this area of work has been effective, and has identified that this targeted approach needs to continue going forward. Another relevant factor is the robust approach adopted by the project officer in continually pursuing individual claims until evidence could be found to validate the discount / exemption. This is a time consuming piece of work, which has delivered significant results so far.
3 Next Steps
In looking forward, the approach to this project (e.g. risk based, making better use of information available to the Council) will be added to existing procedures to enhance processes in place to minimise the risk of fraud and error in relation to the award of council tax discounts and exemptions. Two other issues are also being considered to further enhance processes in this area, namely:
• A review as to whether current resources available to undertake such work are adequate and how much resource will be required once all the current cases have been reviewed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Council Tax Discounts / Exemptions UpdateReport | 36 KB | DownloadRead as text |
Follow Audit and Procurement Committee at Coventry and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jun 2026 | Internal Audit Plan 2026/27RESOLVED that, the Audit and Procurement Committee considered and approves the draft Internal Audit Plan for 2026-27,... | Approved | Open |
| 22 Jun 2026 | Outstanding IssuesRESOLVED that the Audit and Procurement Committee notes the report. | Decided | Open |
| 22 Jun 2026 | Work Programme 2026/2027RESOLVED that the Audit and Procurement Committee notes the Work Programme for 2026-27. | Decided | Open |
| 16 Mar 2026 | Exclusion of Press and PublicRESOLVED that the Audit and Procurement Committee agrees to exclude the press and public under Sections 100(A)(4) of ... | Agreed | Open |
| 16 Mar 2026 | 2025/26 Third Quarter Financial Monitoring Report (to December 2025)RESOLVED that, the Audit and Procurement Committee note the content of the report and confirms that it has no recomme... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.