Resolved
RESOLVED that the Audit and Procurement Committee endorses the 2013/14 Quarter Three Revenue and Capital Monitoring Report.
Audit and Procurement Committee decided this item on Monday 7 April 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Audit and Procurement Committee endorses the 2013/14 Quarter Three Revenue and Capital Monitoring Report.
The purpose of this report is to advise Cabinet of the forecast outturn position for revenue and capital expenditure and the Council’s treasury management activity to the end of November 2013. This is the first budgetary control cycle reported under the new Agresso financial system.
The current forecast for 2013/14 is a balanced position subject to approval of the updated reserve contribution outlined in recommendation 1 below. This position incorporates significant areas of overspend reported previously within the People Directorate, balanced largely by underspends within the Asset Management Revenue Account and other central budgets. The current balanced position compares to a forecast overspend of £1.5m at the second quarter and an overspend of £0.7m at the same point in 2012/13. Given previous budgetary control trends and management expectations of continued robust control of expenditure it is anticipated that the Council will achieve no worse than a balanced position by year-end.
Capital spending for the third quarter of 2013/14 is projected to be £66.2m. This represents a net reduction of £15.8m compared to the £82m reported at the second quarter. This reduction in the capital programme comprises £15.3m rescheduling of expenditure into 2014/15 across a range of programmes and individual schemes and a small underspend of £0.5m. Spending at this revised level will be met by resources identified previously. Recommendations:
Cabinet is recommended to:
1. Approve a further reserve contribution of £0.2m to fund one-off expenditure relating to temporary additional staffing within Children’s Social Care within the People Directorate. This is in addition to the £0.8m approved at Quarter 2.
2. Approve a future contribution of £1.0m to fund one-off expenditure relating to temporary additional staffing within Children’s Social Care within the People Directorate funded through one of the options outlined in Section 5.1.
3. Note the balanced revenue position projected currently.
4. Approve the revised capital estimated outturn position for the year of £66.2m incorporating:
(i) £15.3m net rescheduling of expenditure into 2014/15, (see Appendix 3). (ii) £0.5m net under-spending on the programme.
Audit and Procurement Committee are recommended to:
1. Consider whether there are any comments they wish to be passed to Cabinet.
List of Appendices included:
Appendix 1 Revenue Position: Detailed Directorate breakdown of forecast outturn position Appendix 2 Capital Programme: Estimated Outturn 2013/14 Appendix 3 Capital Programme: Analysis of Rescheduling Appendix 4 Prudential Indicators
None
Other useful documents:
None
Has it or will it be considered by scrutiny?
No
Has it, or will it be considered by any other council committee, advisory panel or other body?
Yes - Audit and Procurement Committee 7th April 2014
Will this report go to Council?
No Report Title: 2013/14 Third Quarter Revenue and Capital Monitoring and Treasury Management Report (to November 2013)
1. Context (or Background) 1.1 Cabinet approved the City Council's revenue budget of £267.9m on the 26th February 2013 and a capital programme of £63.8m. This is the third quarterly monitoring report for 2013/14 to the end of November 2013 (period 8) and the first budgetary control cycle reported under the new Agresso financial system, the result of which is a small number of minor presentational changes from previous reports.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Quarter Three Revenue and Corporate Capital Monitoring Report 2013-14Report | 199 KB | DownloadRead as text |
Follow Audit and Procurement Committee at Coventry and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jun 2026 | Internal Audit Plan 2026/27RESOLVED that, the Audit and Procurement Committee considered and approves the draft Internal Audit Plan for 2026-27,... | Approved | Open |
| 22 Jun 2026 | Outstanding IssuesRESOLVED that the Audit and Procurement Committee notes the report. | Decided | Open |
| 22 Jun 2026 | Work Programme 2026/2027RESOLVED that the Audit and Procurement Committee notes the Work Programme for 2026-27. | Decided | Open |
| 16 Mar 2026 | Exclusion of Press and PublicRESOLVED that the Audit and Procurement Committee agrees to exclude the press and public under Sections 100(A)(4) of ... | Agreed | Open |
| 16 Mar 2026 | 2025/26 Third Quarter Financial Monitoring Report (to December 2025)RESOLVED that, the Audit and Procurement Committee note the content of the report and confirms that it has no recomme... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.