Coventry City Council
Audit and Procurement Committee, Monday 14 July 2014 at 4.00pm

Internal Audit Annual Report 2013-14

Noted Finance 1 paper

Audit and Procurement Committee noted this item on Monday 14 July 2014. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

RESOLVED that the Committee:- 1. Note the performance of Internal Audit against the Audit Plan for 2013/14. 2. Note the summary findings of the key audit reviews completed between January and March 2014 and concurs that the agreed focus for improvements identified and the timescales agreed for implementation for each review is appropriate. 3. Note the opinion of the Internal Audit and Risk Manager on the overall adequacy and effectiveness of Coventry City Council’s internal control environment.
Word for word from the decision Coventry published for this meeting. Source: edemocracy.coventry.gov.uk

Follow this further

Built from Coventry's papers

What the report saysPro

Report to Audit and Procurement Committee

Executive summary

This report to the Audit and Procurement Committee has two purposes:

• To summarise the Council’s Internal Audit activity for the period April 2013 to March 2014 against the agreed Audit Plan for 2013-14.

• To provide the Audit and Procurement Committee with the Internal Audit and Risk Manager's opinion on the overall adequacy and effectiveness of Coventry City Council's internal control environment for the financial year 2013-14 (as documented in section 2.3 of this report).

Recommendations

Audit and Procurement Committee is recommended to note and consider:

1. The performance of Internal Audit against the Audit Plan for 2013-14 (see section 2.1).

1 2. The summary findings of the key audit reviews (attached at appendix two) completed between January and March 2014 and to decide whether it considers the agreed focus of improvements identified and the timescales agreed for implementation for each review, is appropriate.

3. The opinion of the Internal Audit and Risk Manager on the overall adequacy and effectiveness of Coventry City Council's internal control environment.

List of Appendices included:

Appendix One - Audits completed in 2013-14

Appendix Two - Summary findings from key audit reports completed between January and March 2014

Other useful background papers:

Half Year Internal Audit Progress Report 2013-14 Half Year Progress Report

Internal Audit Plan 2013-14 – Quarter Three Progress Report Quarter Three Progress Report

Internal Audit Update Report Update Report

Has it or will it be considered by scrutiny?

No other scrutiny consideration other than the Audit and Procurement Committee.

Has it, or will it be considered by any other council committee, advisory panel or other body?

No

Will this report go to Council?

No

2 Report title: Internal Audit Annual Report 2013-14

1. Context (or background)

1.1The Audit Committee (now the Audit and Procurement Committee) approved the Council's Internal Audit Plan for 2013-14 at its meeting on the 10th April 2013. During the last financial year, the Committee has received progress reports summarising completed audit activity in October 2013, February and April 2014.

1.2This report details the performance of the Internal Audit and Risk Service against the Plan for 2013-14, which is presented in order for the Audit and Procurement Committee to discharge its responsibility, as reflected in its term of reference - “To consider the Head of Internal Audit's Annual Report and Opinion, and a summary of internal audit activities (actual and proposed) and the level of assurance given within the Annual Governance Statement incorporated in the Annual Accounts”.

1.3The report is split into the following sections:

• Assessment of the performance of the Internal Audit Service against its key targets.

• A summary of the audit activity in 2013-14, and highlighting issues that have occurred in the final quarter of 2013-14, that have not been reported to the Audit and Procurement Committee previously, and are relevant to the overall opinion provided in section 2.3.

• The Internal Audit and Risk Manager's opinion on the overall adequacy and effectiveness of Coventry City Council's internal control environment.

2. Options considered and recommended proposal

2.1Performance of the Internal Audit Service

2.1.1 The key target for the Internal Audit Service is to complete 90% of its agreed work plan by the 31st March 2014. The chart below shows that the Service completed 91% of the agreed Audit Plan in this period. It needs to be acknowledged that the planned work plan reduced in size as three audits (i.e. Care Director, IT Security and a post implementation review of Agresso) were deferred for operational reasons until 2014-15.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Annual Report 2013-14Report 169 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
SB
Councillor Sucha BainsDeputy Chair, present
DG
Councillor David GalliersChair, present
LH
Councillor Lindsley HarvardCommittee Member, present
RS
Councillor Richard SandyCommittee Member, present
TW
Councillor Timothy Winspear SawdonCommittee Member, present
DS
Councillor David Stuart WelshCommittee Member, present

On this subject at Coventry

Search all
  1. Internal Audit Annual Report 2013-14This decision
  2. Internal Audit Plan 2026/27Approved
  3. Quarter Three Internal Audit Progress Report 2025/2026Decided
  4. Internal Audit Professional Standards UpdateApproved
  5. Internal Audit Plan 2024-25 - Half Year Progress ReportNoted
  6. Internal Audit External Quality AssessmentApproved

More from Coventry Audit and Procurement Committee

All decisions
MeetingDecisionOutcome
22 Jun 2026 Internal Audit Plan 2026/27RESOLVED that, the Audit and Procurement Committee considered and approves the draft Internal Audit Plan for 2026-27,... Approved Open
22 Jun 2026 Outstanding IssuesRESOLVED that the Audit and Procurement Committee notes the report. Decided Open
22 Jun 2026 Work Programme 2026/2027RESOLVED that the Audit and Procurement Committee notes the Work Programme for 2026-27. Decided Open
16 Mar 2026 Exclusion of Press and PublicRESOLVED that the Audit and Procurement Committee agrees to exclude the press and public under Sections 100(A)(4) of ... Agreed Open
16 Mar 2026 2025/26 Third Quarter Financial Monitoring Report (to December 2025)RESOLVED that, the Audit and Procurement Committee note the content of the report and confirms that it has no recomme... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies