Quarter Three Internal Audit Progress Report 2025/2026

Decided Finance 1 paper

AI summaryCoventry Audit and Procurement Committee notes Q3 2025/26 internal audit performance at 53% of plan, with prediction of over 80% completion by end of March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCommittee noted Q3 performance and key audit findings
MoneyNo specific financial implicationsNo direct cost changes reported
What happens nextNot stated
Who it affectsNot stated

What was decided

The Committee noted the performance as at quarter three against the Internal Audit Plan for 2025-26. Report P3

The Committee noted the summary findings of the key audit reviews attached at Appendix Two. Report P4, P7

Why

The Committee has responsibility to consider summaries of specific internal audit reports and reports on the management and performance of internal audit. Report 1.1, P18

The report shows delivery is below the 75% benchmark at 53%, mainly due to unplanned absence, but is forecast to exceed 80% by the end of March 2026. Report P22, P25, P26

What happens next

There is no implementation timetable because this is a monitoring report; audits in progress will be completed and key reviews will be followed up and reported back to the Committee. Report 4.1, P43, P40

The Chief Internal Auditor expects the delivery position will not significantly affect the ability to deliver the annual internal audit conclusion. Report P27

Options considered

  • Chosen: Note Q3 performance against the Internal Audit Plan 2025-26. Recommended by the Director of Finance and Resources to enable the Committee to discharge its oversight role. Report P2, P3
  • Chosen: Consider the summary findings of the key audit reviews at Appendix Two. Recommended action; no alternative proposal set out in the report. Report P2, P4, P7

Implications

  • Financial: No specific financial implications; internal audit work supports value for money through recommendations made. Report P46
  • Legal: No legal implications; reporting on progress supports the Council's statutory duty to maintain an internal audit function. Report P47, P48
  • Risk: Main risk is that agreed audit actions are not implemented; mitigated by defined follow-up process and Committee oversight. Report P55, P56
  • Equalities: No equalities impact identified. Report 6.4, P60
  • Climate: No impact on climate change or the environment identified. Report 6.5, P62
  • Other: Customer feedback score was 5 out of 5 against a target of 4.8; only 50% of agreed audit recommendations were implemented against a 70% target. Report P32, P33, P34

Who and where

  • Internal Audit Service, Coventry City Council Report P22, P23
  • Directorates and services subject to completed and ongoing audits, including Waste Services, Building Control, Schools, Adult Education, SEND Transport, Occupational Therapy and Repairs and Maintenance Report P39, P74, P76, P84
  • Audit and Procurement Committee Report 1.1, P18

Timeline

  • April to December 2025: Period covered by this progress report. Report P1
  • 31st December 2025: 53% of the revised audit plan completed against a 75% benchmark; customer feedback score 5; 50% of recommendations implemented. Report P25, P32, P33
  • 2nd February 2026: Committee received update on Internal Audit Service resources and the amended plan of 550 days. Report P22
  • 31st March 2026: Target date to complete 90% of the audit plan; forecast is over 80% completion. Report P23, P25, P26
  • September 2026: Action date noted for the SEND Home to School Taxi Provision audit. Report P85
  • December 2026: Action date noted for the Occupational Therapy Equipment audit. Report P77

Plain English for the jargon

  • Internal Audit Plan: The annual programme of internal audit reviews agreed for 2025-26, revised to 550 days.
  • One Coventry Plan: The Council's plan setting out its key objectives and priorities.
  • Significant Assurance: Audit opinion indicating generally effective controls with only minor improvements needed.
  • Reasonable Assurance: Audit opinion indicating controls generally work but some improvements are required.
  • Limited Assurance: Audit opinion indicating controls are not operating effectively in several areas and improvements are needed.
  • Global Internal Audit Standards in the UK Public Sector: The professional standards that set out how internal audit should be delivered in the UK public sector.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item60

Resolved

RESOLVED that the Audit and Procurement Committee: 1. Notes the performance as at quarter three against the Internal Audit Plan for 2025-26. 2. Notes the summary findings of the key audit reviews (attached at Appendix Two).
Word for word from the decision Coventry published for this meeting. Source: edemocracy.coventry.gov.uk

Follow this further

Built from Coventry's papers

What the report saysPro

Report to Audit and Procurement Committee

Executive summary

The purpose of this report is to provide the Audit and Procurement Committee with an update on the internal audit activity for the period April to December 2025, against the Internal Audit Plan for 2025-26.

Recommendations

Audit and Procurement Committee is recommended to:

1. Note the performance as at quarter three against the Internal Audit Plan for 2025-26.

2. Consider the summary findings of the key audit reviews (attached at Appendix Two).

1 List of Appendices included:

Appendix One - Audit Reviews Completed between April and December 2025

Appendix Two - Summary Findings from Key Audit Reports

Background papers

None

Other useful documents:

None

Has it or will it be considered by scrutiny?

No other scrutiny consideration other than the Audit and Procurement Committee

Has it, or will it be considered by any other council committee, advisory panel or other body?

No

Will this report go to Council?

No

2 Report title: Quarter Three Internal Audit Progress Report 2025-26

1. Context (or background)

1.1This report is the second monitoring report for 2025-26, which is presented in order for the Audit and Procurement Committee to discharge its responsibility 'to consider summaries of specific internal audit reports as requested' and 'to consider reports dealing with the management and performance of internal audit'.

2. Options considered and recommended proposal

2.1Delivering the Audit Plan

2.1.1 At its meeting on the 2nd February 2026, the Audit and Procurement Committee received an update on the resource position within the Internal Audit Service. As a result, the Committee noted that the Internal Audit Plan had been amended to 550 days, which reflects the impact of unplanned absence in the Service and the time taken to implement the agreed service redesign.

2.1.2 The key target facing the Internal Audit Service is to complete 90% of its work plan by the 31st March 2026. The chart below provides analysis of progress against planned work for the period April to December 2025 based on the revised audit plan of 550 days.

Chart One: Progress against delivery of Internal Audit Plan 2025-26

As at the end of December 2025, the Service had completed 53% of the Audit Plan against a benchmark of 75% (which reflects delivery of 100% of the Plan.) It is recognised that performance is below expectation, with the impact of the unplanned absence being visible in the quarter three performance. However, notwithstanding this, based on an assessment of performance as at February 2026, it is predicted that the Service will achieve over 80% of the plan by the end of March 2026. It

3 should also be noted that whilst the audits which are required to be completed to achieve 90% of the plan may not be finalised by the end of March 2026, the work in support of them will be substantially complete.

2.1.3 Taking into account the points at 2.1.1 and 2.1.2 above, it is the view of the Chief Internal Auditor that these issues will not, in any significant respects, impact on the ability to deliver the annual internal audit conclusion.

2.2Other Key Performance Indicators (KPIs)

At its meeting in November 2025, the Audit and Procurement Committee approved the performance indicators for the Internal Audit Service for 2025-26, in line with the Global Internal Audit Standards in the UK Public Sector. Whilst some of these indicators are measured on an annual basis, there are two (in addition to the indicator in 2.1 above) which are measured quarterly. The table below shows a summary of the performance for 2025-26 to date against these two performance indicators.

Table One: Internal Audit Quarterly Key Performance Indicators 2025-26

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarter Three Internal Audit Progress Report 2025/2026Report 318 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
MA
Councillor Maya AliCommittee Member, absent
JB
Councillor John BlundellCommittee Member, apologies, sent representative
RB
Councillor Richard BrownBy Invitation, expected
AH
Councillor Angela HopkinsCommittee Member, present
AJ
Councillor Abdul JobbarCommittee Member, present
RP
Councillor Ram Parkash Lakha OBEChair, present
JE
Councillor Julia Elizabeth LepoidevinReserve, present as substitute
PM
Councillor Peter MaleCommittee Member, present
BS
Councillor Bally SinghDeputy Chair, present

On this subject at Coventry

Search all
  1. Quarter Three Internal Audit Progress Report 2025/2026This decision
  2. Quarter Three Performance 2025/26 - Adult Social CareDecided
  3. Quarter Three Internal Audit Progress Report 2020-21Decided
  4. Quarter Three Internal Audit Progress Report 2018-2019Noted
  5. Quarter Three Internal Audit Progress Report 2017-2018Noted
  6. Quarter Three Internal Audit Progress Report 2016-17Noted

More from Coventry Audit and Procurement Committee

All decisions
MeetingDecisionOutcome
22 Jun 2026 Internal Audit Plan 2026/27RESOLVED that, the Audit and Procurement Committee considered and approves the draft Internal Audit Plan for 2026-27,... Approved Open
22 Jun 2026 Outstanding IssuesRESOLVED that the Audit and Procurement Committee notes the report. Decided Open
22 Jun 2026 Work Programme 2026/2027RESOLVED that the Audit and Procurement Committee notes the Work Programme for 2026-27. Decided Open
16 Mar 2026 Exclusion of Press and PublicRESOLVED that the Audit and Procurement Committee agrees to exclude the press and public under Sections 100(A)(4) of ... Agreed Open
16 Mar 2026 2025/26 Third Quarter Financial Monitoring Report (to December 2025)RESOLVED that, the Audit and Procurement Committee note the content of the report and confirms that it has no recomme... Noted Open