RESOLVED that the Audit and Procurement Committee note the progress made in response to the recommendations arising from the audit and indicate that there are no recommendations to the Cabinet Member for Policy and Leadership, who is the portfolio holder for information management and governance.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
In November 2017, the Information Commissioner’s Office (ICO) carried out a data protection audit into the City Council’s governance arrangements, training and awareness and data sharing arrangements. The ICO issued its final report in February 2018 which included a range of recommendations. The outcome of the audit and the Council’s action plan were reported to the Audit and Procurement Committee later that month and this report sets out progress over the last year against the agreed actions.
Recommendations
Audit and Procurement Committee is recommended to:
1) Note the progress made in response to the recommendations arising from the audit
2) Make any recommendations to the Cabinet Member for Policy and Leadership who is the portfolio holder for information management and governance List of Appendices included: Appendix 1: Progress against action plan
Background papers: None
Other useful documents Briefing note to Audit and Procurement Committee Information Commissioner’s Office – Data Protection Audit November 2017, 19 February 2018.
Has it been or will it be considered by Scrutiny? No
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body? No
Will this report go to Council? No Report title: Information Commissioner’s Office – Data Protection Audit Progress Report
1. Context (or background)
1.1In October 2015, the Information Commissioner’s Office (ICO) carried out a data protection audit into the City Council’s governance arrangements, training and awareness and data sharing arrangements. In addition to meeting with officers responsible for corporate arrangements, it spoke to staff in Children’s Social Care and the Revenues and Benefits service. The audit concluded that there was “very limited assurance that processes and procedures are in place and deliver data protection compliance.” It made recommendations for the Council to strengthen its arrangements which the City Council implemented as part of a significant programme of work to strengthen its approach to information governance. The Audit and Procurement Committee has received regular reports on progress against the ICO’s recommendations since then.
1.2In November 2017 the ICO revisited the authority to carry out a further data protection audit. It followed the same scope, looking at governance arrangements, training and awareness and data sharing arrangements corporately and in Children’s Social Care and the Revenues and Benefits service. As previously, the audit provided a snapshot of assurance levels at a moment in time rather than specifically looking at the direction of travel or progress since the previous audit.
1.3In commenting on the progress made by the City Council, the ICO’s Lead Auditor, who was a member of the ICO team for both audits wrote that “in our view, comparison between the assurance ratings strongly reflects on the work undertaken at CCC since our original audit. … This demonstrates a clear improvement and progress at an individual, as well as an overall, level”.
1.4The ICO report made 141 detailed recommendations for the Council to consider, some of which were duplicated. Of these recommendations:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.