RESOLVED that, the Audit and Procurement Committee: 1. Having considered the summary findings of the key audit reviews set out at Appendix One, note the performance as at quarter three against the Internal Audit Plan for 2018/19. 2. Request that an update be circulated to them following the completion of the follow up audit at Frederick Bird School.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
The purpose of this report is to provide the Audit and Procurement Committee with an update on the internal audit activity for the period April to December 2018, against the Internal Audit Plan for 2018-19.
Recommendations
Audit and Procurement Committee is recommended to:
1. Note the performance as at quarter three against the Internal Audit Plan for 2018-19.
2. Consider the summary findings of the key audit reviews (attached at Appendix One).
1 List of Appendices included:
Appendix One - Summary Findings from Key Audit Reports Completed between October and December 2018
Background papers
None
Has it or will it be considered by scrutiny?
No other scrutiny consideration other than the Audit and Procurement Committee
Has it, or will it be considered by any other council committee, advisory panel or other body?
No
Will this report go to Council?
No
2 Report title: Quarter Three Internal Audit Progress Report 2018-19
1. Context (or background)
1.1This report is the second monitoring report for 2018-19, which is presented in order for the Audit and Procurement Committee to discharge its responsibility 'to consider summaries of specific internal audit reports as requested' and 'to consider reports dealing with the management and performance of internal audit'.
2. Options considered and recommended proposal
2.1Delivering the Audit Plan
2.1.1 The key target facing the Internal Audit Service is to complete 90% of its work plan by the 31st March 2019. The chart below provides analysis of progress against planned work for the period April to December 2018.
Chart One: Progress against delivery of Internal Audit Plan 2018-19
As at the end of December 2018, the Service has completed 70% of the Audit Plan against a planned target of 74% (which is based on delivering 100% of the plan) and is on track to meet its key target by the end of 2018-19.
2.1.2 During quarter three, the Service’s ability to complete the original Audit Plan of 550 days has been impacted by an unplanned absence within the Team. As a result, the Plan has been amended to 480 days (which reflects the available resources for the remainder of the financial year). Consequently, the progress reported in 2.1.1 above is based on this revised Audit Plan. This reduction has been accommodated through:
A small number of audits have been postponed until 2019/2020.
Changes in operational requirements for audit involvement.
In the view of the Acting Chief Internal Auditor, these changes will not, in any significant respects, impact on the ability to deliver the annual internal audit opinion.
3 2.2 Other Key Performance Indicators (KPIs)
In addition to the delivery of the Audit Plan, the Internal Audit Service has a number of other KPI’s which underpin its delivery. The table below shows a summary of the performance for 2018-19 to date against these five KPIs, with comparative figures for the financial year 2017-18. There are two indicators (i.e. final report to deadline and audit delivered within budget days) where the Service’s current performance is below expectations. As highlighted in previous reports to Audit and Procurement Committee, targeted actions remain on-going to make improvements and deliver sustainable performance.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.