Resolved
RESOLVED that the Audit and Procurement Committee notes the progress made in implementing audit recommendations and confirms its satisfaction with this ... view the full minutes text for item 71.
Audit and Procurement Committee decided this item on Monday 25 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Audit and Procurement Committee notes the progress made in implementing audit recommendations and confirms its satisfaction with this ... view the full minutes text for item 71.
The purpose of this report is to provide the Audit and Procurement Committee with an update on the progress made in implementing internal audit recommendations since the last update in March 2018.
The Audit and Procurement Committee is recommended to note the progress made in implementing audit recommendations and confirm its satisfaction with this and the proposed action by the Acting Chief Internal Auditor for audits were actions remain outstanding.
1 List of Appendices included:
Appendix One – Results of Formal Follow up Exercise Appendix Two – Results of Self-Assessment Follow up Exercise
None
Has it or will it be considered by scrutiny?
No other scrutiny consideration other than the Audit and Procurement Committee
Has it, or will it be considered by any other council committee, advisory panel or other body?
No
Will this report go to Council?
No
2 Report title: Internal Audit Recommendation Tracking Report
1. Context (or background)
1.1The Public Sector Internal Audit Standards requires that “the Chief Audit Executive (i.e. Chief Internal Auditor) must establish a follow up process to monitor and ensure that management actions have been effectively implemented or that senior management have accepted the risk of not taking action”.
1.2As reflected within its terms of reference, the Audit and Procurement Committee is required to receive reports on Internal Audit’s follow up process. This report provides an update as to progress in respect of the agreed management actions which have been followed up during the period March 2018 to February 2019.
2. Options considered and recommended proposal
2.1Follow Up Procedure - Given the number of audits that the Internal Audit Service completes every year, it is critical that it has a robust procedure in place for ensuring that it obtains appropriate assurance that audit recommendations have been implemented, but does so in a way that allows the Service to respond to new risks facing the Council. Where appropriate, Internal Audit defines within its audit reports the follow up process to those responsible for the system / area under review and a date is agreed of when this will take place.
Currently, there are three key considerations that will determine the follow up procedure adopted, namely:
1) Whether the area audited is of such significance that it is subject to an annual review.
2) The level of assurance provided in the audit report.
3) A self-assessment process for those reviews where neither of the points above apply, but a follow up review is necessary.
2.2These considerations are expanded upon below:
Annual Audits: These audits are generally included in the Audit Plan on an annual basis because of the nature of the systems, and the fact they are corporate wide and have been identified as key in delivering the Council's objectives (e.g. financial systems, risk management).
Level of Assurance: Any audit which receives 'no' or 'limited' assurance is subject to a follow up review to assess improvements based on a timing agreed between Internal Audit and relevant management. In either of these circumstances, a formal follow up review will take place which involves Internal Audit assessing progress through audit testing to ensure that agreed actions have been implemented and are working effectively.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Recommendation Tracking ReportReport | 131 KB | DownloadRead as text |
Follow Audit and Procurement Committee at Coventry and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jun 2026 | Internal Audit Plan 2026/27RESOLVED that, the Audit and Procurement Committee considered and approves the draft Internal Audit Plan for 2026-27,... | Approved | Open |
| 22 Jun 2026 | Outstanding IssuesRESOLVED that the Audit and Procurement Committee notes the report. | Decided | Open |
| 22 Jun 2026 | Work Programme 2026/2027RESOLVED that the Audit and Procurement Committee notes the Work Programme for 2026-27. | Decided | Open |
| 16 Mar 2026 | Exclusion of Press and PublicRESOLVED that the Audit and Procurement Committee agrees to exclude the press and public under Sections 100(A)(4) of ... | Agreed | Open |
| 16 Mar 2026 | 2025/26 Third Quarter Financial Monitoring Report (to December 2025)RESOLVED that, the Audit and Procurement Committee note the content of the report and confirms that it has no recomme... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.