RESOLVED that the Cabinet: 1) Approves the Council’s revenue monitoring position. 2) Approves the revised capital estimated outturn position for the year of £215.9m incorporating: £14m net increase in spending relating to approved/technical changes of and net rescheduling of expenditure into 2020/21 of £16.6m.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
The purpose of this report is to advise Cabinet of the forecast outturn position for revenue and capital expenditure and the Council’s treasury management activity as at the end of December 2019. The headline revenue forecast for 2019/20 is for a net underspend of £1.9m. At the same point in 2018/19 there was a projected underspend of £1.8m. The headline capital position reports £20.6m of expenditure rescheduled into 2020/21.
The largest areas of budget pressure are within services for Children and Young People and Housing and Homelessness which are projecting overspends of £2.6m and £3.2m respectively. These are offset by a significant underspend within central and contingency budgets.
The Council’s capital spending is projected to be £215.9m and includes major scheme expenditure including investment in the A46 Link Road, Whitley South infrastructure and the National Battery Plant.
Recommendations
The Cabinet is requested to:
1) Approve the Council’s revenue monitoring position; 2) Approve the revised capital estimated outturn position for the year of £215.9m incorporating: £14m net increase in spending relating to approved/technical changes of and net rescheduling of expenditure into 2020/21 of £16.6m. The Audit and Procurement Committee is requested to:
1) Consider the proposals in the report and forward any recommendations to the Cabinet.
List of Appendices included:
Appendix 1 Revenue Position: Detailed Directorate breakdown of forecast outturn position Appendix 2 Capital Programme: Analysis of Budget/Technical Changes Appendix 3 Capital Programme: Estimated Outturn 2019/20 Appendix 4 Capital Programme: Analysis of Rescheduling Appendix 5 Prudential Indicators
Background papers
None
Other useful documents
None
Has it been or will it be considered by Scrutiny?
No
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body?
Audit and Procurement Committee 16th March 2020
Will this report go to Council?
No Report title: 2019/20 Third Quarter Financial Monitoring Report (to December 2019)
1. Context (or background)
1.1Cabinet approved the City Council's revenue budget of £231.5m on the 19th February 2019 and a Directorate Capital Programme of £195.4m. This is the third quarterly monitoring report for 2019/20 to the end of December 2019. The purpose is to advise Cabinet of the forecast outturn position for revenue and capital expenditure and to report on the Council’s treasury management activity.
1.2The current 2019/20 revenue forecast is for an underspend of £1.9m. The reported forecast at the same point in 2018/19 was an underspend of £1.8m. Capital spend is projected to be £215.9m, a reduction of £2.8m since the quarter 2 forecast.
2. Options considered and recommended proposal
2.1This is a budget monitoring report and as such there are no options.
2.2Revenue Position - The revenue forecast position is analysed by service area below.
Table 1 - Forecast Variations
Revised Net Forecast Forecast Service Area Budget Spend Variation £m £m £m Public Health 1.3 0.9 (0.4) People Directorate Management 1.5 1.5 0.0 Education & Skills 12.7 14.3 1.4 Children & Young People 73.7 76.3 2.6 Adult Social Care 77.4 77.4 0.0 Customer Services & 13.6 16.9 3.3 Transformation Human Resources 1.3 1.7 0.4 2.7 Place Directorate Management 2.6 0.1 Business Investment & Culture 7.2 7.4 0.2 Transportation & Highways 4.6 4.8 0.2 Streetscene and Regulatory 28.2 29.9 1.7 Project Management & Property (8.0) (8.8) (0.8) Finance & Corporate Services 7.4 6.8 (0.6) Contingency & Central Budgets 6.7 3.3 (10.0) Total Spend 230.2 228.5 (1.9)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.