CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Crawley Borough Council
Audit Committee, Tuesday 19 March 2019 at 6.30pm

Progress Report and Risk Management

Decided Finance 3 papers

Audit Committee decided this item on Tuesday 19 March 2019. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED That the Committee receive the report and note progress to date, as at 28 February 2019.
Word for word from the decision Crawley published for this meeting. Source: democracy.crawley.gov.uk

Follow this further

Built from Crawley's papers

What the report saysPro

Report to Audit Committee

Recommendations

2.1The Committee is requested to receive this report and note progress to date, as at 28th February 2019.

Reasons for the recommendations

3.1The Committee has a responsibility to ensure that action has been taken by relevant Managers on risk based issues identified by Internal Audit.

Background

Work Completed

4.1Since the last report, as at 2nd October 2018, the following review has been completed.

Audit Title Audit Opinion Taxi and Private Hire Vehicles Licensing Substantial Assurance NNDR Substantial Assurance K2 Tender – review of contract award Substantial Assurance Treasury Management Substantial Assurance Commercial Properties including Rents Substantial Assurance Cash and Bank Satisfactory Assurance Gas Servicing – review of contract award Substantial Assurance Creditors Substantial Assurance 4.2 Work in Progress

The reviews in progress and other work that we have undertaken in the period are shown at Appendix A. .

4.3High priority findings in this period

There are no high priority findings to report.

4.4Follow up Audits

Data Centre Post Project Review

It was agreed by management that an independent review would be commissioned at the end of the project (targeted for the end of February 2019), which is now complete barring one final piece of work to move a Vodafone line across to the new data centre. Unfortunately, the Council has been let down badly by the supplier and despite constant chasing over the course of nearly a year since the order was placed, and the subsequent lodging of a formal complaint to Vodafone, this remains outstanding at the end of February. For overall context though, the project has delivered 100% of Server and 98.4% of Application migrations as per the schedule.

This one remaining migration does not however, preclude the commissioning of the post implementation review. Therefore, ICT will procure and commission the independent review work during March 2019. We expect the work to take some time to complete (from procurement, review and interview process, to submission of the final report), so expect to be able to submit to OSC for their review in May 2019.

Community Grants

We reported at the last meeting that whilst we were satisfied that there was sufficient documentation to confirm eligibility for the grants awarded, we were unable to see evidence to confirm the process followed when making the grant award, in verifying that all documentation and evidence had been received from the organisation, and that they met the eligibility criteria.

Status of agreed action – in progress.

An initial checklist has been produced for both the small grants and large grants and we have reviewed copies of these. We have discussed these with the Community Services Manager who has confirmed that there is further work to be done to ensure that the items being checked are definitely meaningful.

Status of agreed action – work in progress.

We will consider this action again in the near future and report the outcome to the next meeting of this Committee.

In addition, we identified that adequate segregation of duties are not in place, with one officer making the decision to award the grant, but with no secondary check, even on a sample basis, to confirm eligibility. Status of agreed action – implemented.

The Community Services Manager currently reviews all grants.

4.5Freedom of Information (FOI) Requests

Between 10th November 2018 and 28th February 2019 we have processed 227 requests, and of these, 2 responses were sent to the requester outside of the 20 working day deadline. This was largely due to the complexity of the requests.

5. Strategic Risks Update

The following have been identified as strategic risks for the Council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Plan Progress ReportAppendix A 52 KB Download
PDF
Town Hall Risk RegisterAppendix B 117 KB Download
PDF
Progress Report and Risk ManagementReport 117 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 9 attended
KS
Councillor Karen SudanChair, present
CE
Councillor Carol EadeVice-Chair, present
RB
Councillor Richard BurrettCommittee Member, present
II
Councillor Ian IrvineCommittee Member, present
LW
Councillor Laura-Lee WillcockCommittee Member, absent
CC
Chris CorkerOfficer, in attendance
KH
Karen HayesOfficer, in attendance
MM
Mez MatthewsOfficer, in attendance
GE
Gillian EdwardsOfficer, apologies

On this subject at Crawley

Search all
  1. Progress Report and Risk ManagementThis decision
  2. Progress Report and Risk ManagementDecided
  3. Progress Report and Risk ManagementDecided
  4. Progress Report and Risk ManagementDecided
  5. Progress Report and Risk ManagementAgreed
  6. Progress Report: Internal Audit and Risk ManagementDecided

More from Crawley Audit Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Audit Planning Report: Year Ended 31 March 2026RESOLVED That the Audit Planning Report for the year ended 31 March 2026 be noted. Noted Open
7 Jul 2026 Internal Audit Annual Conclusion: 2025/26RESOLVED That the Annual Internal Audit Conclusion for 2025/26 be noted. Noted Open
7 Jul 2026 Update on Counter-FraudRESOLVED That the Update on Counter-Fraud (as amended) be noted. Noted Open
7 Jul 2026 Annual Report of the Audit Committee Chair: 2025/26RESOLVED That the Committee confirm it is assured that the Council's governance arrangements, financial management an... Decided Open
7 Jul 2026 Risk Management UpdateRESOLVED The Committee confirmed its satisfaction with the Council's risk management arrangements. That the following... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies