Resolved
RESOLVED That the ... view the full minutes text for item 5.
Audit Committee decided this item on Monday 19 July 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the ... view the full minutes text for item 5.
2.1The Committee is requested to receive this report and note progress to date, as at 30th June 2021.
3.1The Committee has a responsibility to ensure that action has been taken by relevant Managers on risk based issues identified by Internal Audit.
4.1Work Completed
Since the last report, as at 19th February 2021 the following work has been completed/undertaken:
Audit Title Audit Opinion Temporary Accommodation Substantial COVID-19 Discretionary Grants Substantial COVID-19 Small Business Grant Fund Substantial Disabled Facilities Grants Satisfactory Cash and Bank Substantial Budgetary Control Substantial Financial Management System (FMS) Substantial Payroll Substantial Treasury Management Satisfactory NNDR Substantial Council Tax Substantial K2 N/A Fleet Management Limited Assurance Other Governance Work Throughout the year: Attendance at Corporate Project Assurance Group Attendance at Town Hall Board Member of Information Management Project Board Member of Information Governance Board Freedom of Information Requests Subject Access Requests Complaints Investigate Data Breaches
4.2Work in Progress
The reviews in progress and other work that we have undertaken in the period are shown at Appendix A.
4.3High Priority Findings in this Period
There were two high priority findings identified in this period:
Fleet Management Audit 2020/2021 High Priority Findings – 1 Medium Priority Findings - 4
The contract for the provision of vehicle tracking has expired.
Treasury Management Audit 2020/2021 High Priority Findings – 1 During this review it was noted that a reconciliation between Logotech and the FMS system had not been carried out since February 2020. Whilst we have not identified any errors during this review, the failure to carry out an important check as part of a system where the transaction values are so large is in itself a high priority weakness which should be addressed.
4.4Follow Up Audits
We have undertaken two follow up audits in this period.
Car Parking Permits Audit 2020/2021 We are unable to confirm that the actions agreed at the time of the audit have been satisfactorily implemented due to staff shortages in Parking Services. However, we are advised that changes are in the process of being implemented and we will undertake further work in this area and report the outcome to the next meeting of this Committee.
Treasury Management Audit 2020/2021 As reported at 4.3 above, we identified that reconciliations were not being undertaken in a timely manner. We can confirm that this has been rectified.
4.5Freedom of Information (FOI) Requests
Between 20th February 2021 and 30th June 2021 we have processed 225 requests, and of these, 4 were responded to late. We have responded to requests for information in as timely a manner as possible, but due to the challenges on resources that arose due to the COVID-19 pandemic, some requests were late, and in some cases, the information requested was not provided as it was necessary for resources to be diverted away from usual compliance of information rights work, and be applied to serving and protecting Crawley Borough Council’s communities during this challenging time. Corporate Risks with CMT input – July 21
Failure to deliver key infrastructure projects as planned, on time and within budget, such as:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Progress on Audit PlanAppendix A | 128 KB | Download |
PDF |
Town Hall Project Risk RegisterAppendix B | 557 KB | Download |
PDF |
Progress Report and Risk ManagementReport | 486 KB | DownloadRead as text |
Follow Audit Committee at Crawley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Audit Planning Report: Year Ended 31 March 2026RESOLVED That the Audit Planning Report for the year ended 31 March 2026 be noted. | Noted | Open |
| 7 Jul 2026 | Internal Audit Annual Conclusion: 2025/26RESOLVED That the Annual Internal Audit Conclusion for 2025/26 be noted. | Noted | Open |
| 7 Jul 2026 | Update on Counter-FraudRESOLVED That the Update on Counter-Fraud (as amended) be noted. | Noted | Open |
| 7 Jul 2026 | Annual Report of the Audit Committee Chair: 2025/26RESOLVED That the Committee confirm it is assured that the Council's governance arrangements, financial management an... | Decided | Open |
| 7 Jul 2026 | Risk Management UpdateRESOLVED The Committee confirmed its satisfaction with the Council's risk management arrangements. That the following... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.